Charles Crews v. Dexter Road Partners

CourtCourt of Appeals of Tennessee
DecidedJanuary 28, 1998
Docket02A01-9603-CH-00045
StatusPublished

This text of Charles Crews v. Dexter Road Partners (Charles Crews v. Dexter Road Partners) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charles Crews v. Dexter Road Partners, (Tenn. Ct. App. 1998).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE WESTERN SECTION AT JACKSON

CHARLES E. CREWS, ) FILED ) Plaintiff/Appellee ) Shelby Chancery No. 102887 ) vs. ) ) January 28, 1998 DEXTER ROAD PARTNERS, ) Appeal No. 02A01-9603-CH-00045 O.P. ADNEY, JR., Individually, ) LARRY L. TAYLOR, Individually, ) and W. TERRY EDWARDS, Trustee, ) Cecil Crowson, Jr. ) Defendants/Appellants. ) Appellate C ourt Clerk

APPEAL FROM THE CHANCERY COURT OF SHELBY COUNTY AT MEMPHIS, TENNESSEE

THE HONORABLE C. NEAL SMALL, CHANCELLOR

For the Plaintiff/Appellee: For the Defendant/Appellant:

Julie Bartholomew Douglas Hartley Cordova, Tennessee Cordova, Tennessee

AFFIRMED

HOLLY KIRBY LILLARD, JUDGE

CONCUR:

W. FRANK CRAWFORD, P.J., W.S.

ALAN E. HIGHERS, J. OPINION

In this case, the parties entered into a real estate contract in which the seller was required to

construct a road to the property by a specified date. The road was not completed by the agreed

deadline, and the buyer sued for liquidated damages provided for by the contract. The trial court

awarded liquidated damages, and the seller appeals. We affirm.

On December 4, 1991, Appellant Dexter Road Partners (“DRP”) contracted with Appellee

Charles Crews (“Crews”) to sell Crews 4.31 acres of land for $1,450,000. Crews planned to build

a shopping center on the property. Access to the property was to be provided by the completion of

two planned roads, New Dexter Road and Bonnie Lane. An Addendum to the contract provided that

Crews would have sixty days in which to either close the transaction or reject it. The Addendum

also included a condition precedent requiring DRP to convey the property “with all improvements

known as New Dexter Road complete” at the closing.

Negotiations followed in which DRP attempted to convince Crews to close the transaction

prior to the completion of New Dexter Road. Finally, on July 24, 1992, the parties executed a

Memorandum of Agreement (“Memorandum”), drafted by DRP. The Memorandum provided for

full tender of the purchase price in exchange for DRP’s promise to:

substantially complete the General Street Requirements as set forth in that certain City/County Standard Improvement Contract for New Dexter Road and Bonnie Lane by November 1, 1992; provided, however, that failure to complete any such required improvement under said contract beyond the curbs and gutters for such streets, including but not limited to sidewalks, final grading and sodding, if applicable, shall not be subject to the November 1, 1992 completion date.

The City/County Standard Improvement Contract for New Dexter Road and Bonnie Lane

(“Improvement Contract”), referred to in the Memorandum, was not attached to it. Crews had

originally wanted the roads dedicated and accepted by all the necessary government authorities by

November 1, but dropped this demand in signing the Memorandum. The Memorandum further

provided that DRP would pay Crews “a penalty of $1,335.00 per day for each day beyond November

1, 1992, until fully complete.”

DRP contracted with Construction Technologies, Inc. (“CTI”) to perform the road

improvements. A few days after signing the Memorandum, DRP and CTI entered into an Indemnity

Agreement. In this contract, CTI agreed to indemnify DRP for any losses it suffered through default

under the terms of the Memorandum. The Indemnity Agreement referred to the liquidated damages

clause of the Memorandum and recited that time was of the essence, but did not mention the Improvement Contract. In addition, it referred to “full completion and development of New Dexter

Road and Bonnie Lane” by November 1, except for those improvements outside the curbs and

gutters.

As of November 1, no soil cement or asphalt had been laid for the roads. Placement of the

soil cement was completed by November 13. By November 30, the roads were at least partially

barricaded and had not been striped. Asphalt paving was complete by December 2. As of December

28, barricades were still in place on the roads, and the traffic light had been installed but was still

operating in flashing mode. Road signs had not been placed, and the roads were not yet ready for

traffic. Crews demanded payment by DRP of liquidated damages, pursuant to the Memorandum,

of $78,765, representing $1,335 per day for 59 days, the period from November 1 to December 31.

DRP refused to pay, so Crews sued for liquidated damages under the contract.

During discovery, DRP initially failed to respond to Crews’ first set of interrogatories.

Crews filed a motion to compel. Crews and DRP then entered into a consent order, under which

DRP had a deadline of April 1, 1994 to answer the interrogatories. As of April 27, the

interrogatories had not been answered, so Crews filed a petition for scire facias, alleging contempt

and asking for sanctions and attorney’s fees. DRP filed its answers to the interrogatories on June

10. At the hearing on Crews’ petition for scire facias on June 27, 1994, the trial court found that

DRP’s answers were incomplete. The court ordered DRP to file supplemental answers by July 11

and reserved consideration of sanctions. DRP filed its Supplemental Answers on July 15. In

response to Crews’ request for the production of documents, DRP provided three of the documents

requested by plaintiffs.

At the bench trial, DRP’s counsel attended, but no representatives of DRP were present.

DRP’s counsel admitted to breach of contract but maintained that the roads were substantially

complete on December 3, 1992. DRP also argued that the liquidated damages provision in the

contract was unenforceable as a penalty. DRP admitted that its discovery responses had been

dilatory and incomplete but asserted that many of the requested documents were not in DRP’s

possession. Proof at trial established that several of DRP’s answers to Crews’ interrogatories were

incorrect, stating completion dates that were earlier than the actual completion dates. In addition,

one of the three documents produced by DRP, an invoice dated October 20, 1992, indicated that at

least some soil cement and paving work had been done by that date. The document proved to be an

2 invoice for unrelated work performed on an adjacent site. Crews was unable to begin construction

of the commercial structure until March, 1993.

The trial court allowed into evidence documents extrinsic to the Memorandum, including the

Indemnity Agreement and some letters between the parties. In addition, the trial court applied the

missing witness rule against DRP. It found that the roads were not substantially complete until

December 31, 1992, the day on which they were complete from curb to curb and open for traffic.

The trial court upheld the liquidated damages provision of $1,335 per day and awarded Crews

liquidated damages of $78,765. The trial court also awarded Crews pre-judgment interest at the rate

of 10% from December 31, 1992, in the amount of $22,313.32. In addition, it sanctioned DRP for

discovery violations by awarding Crews $7,500 in attorney’s fees. From this decision, DRP now

appeals.

On appeal, DRP raises several issues. First, DRP asserts that, under the contract, the road

was “substantially complete” earlier than the date found by the trial court. Next, DRP contends that

the contractual provision for liquidated damages was a penalty and should not have been enforced.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gredig v. Tennessee Farmers Mutual Insurance Co.
891 S.W.2d 909 (Court of Appeals of Tennessee, 1994)
V. L. Nicholson Co. v. Transcon Investment & Financial Ltd.
27 Cont. Cas. Fed. 80,250 (Tennessee Supreme Court, 1980)
Ammons v. Bonilla
886 S.W.2d 239 (Court of Appeals of Tennessee, 1994)
Rainey v. Stansell
836 S.W.2d 117 (Court of Appeals of Tennessee, 1992)
Airline Construction, Inc. v. Barr
807 S.W.2d 247 (Court of Appeals of Tennessee, 1990)
APAC-Tennessee, Inc. v. J.M. Humphries Construction Co.
732 S.W.2d 601 (Court of Appeals of Tennessee, 1986)
Spencer Ex Rel. Spencer v. A-1 Crane Service, Inc.
880 S.W.2d 938 (Tennessee Supreme Court, 1994)
Harmon v. Eggers
699 S.W.2d 159 (Court of Appeals of Tennessee, 1985)
Testerman v. Home Beneficial Life Ins. Co.
524 S.W.2d 664 (Court of Appeals of Tennessee, 1974)
Beasley v. Horrell
864 S.W.2d 45 (Court of Appeals of Tennessee, 1993)
Kimbrough & Co. v. Schmitt
939 S.W.2d 105 (Court of Appeals of Tennessee, 1996)
Frank Rudy Heirs Associates v. Moore & Associates, Inc.
919 S.W.2d 609 (Court of Appeals of Tennessee, 1995)
Southern Railway Employees Credit Union v. Thornburg
680 S.W.2d 791 (Court of Appeals of Tennessee, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
Charles Crews v. Dexter Road Partners, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charles-crews-v-dexter-road-partners-tennctapp-1998.