Industrial Indemnity Co. v. Wick Construction Co.

680 P.2d 1100, 1984 Alas. LEXIS 278
Alaska Supreme Court·Decided March 2, 1984·No. 6012/6759, 6059/6758·Published·Cited by 35 cases

Opinions

OPINION

MATTHEWS, Justice.

These consolidated appeals arise out of a contract awarded to Wick Construction Company for the construction of the Juneau courthouse and office building. Appellants Kenai Glass Company and Industrial Indemnity Company raise numerous issues on appeal.

In February 1973, the Alaska State Housing Authority (ASHA) awarded the contract to construct the Juneau court and office building to Wick Construction Company. Wick subcontracted all work relating to the fabrication and erection of the curtainwall, an aluminum and glass structure enclosing the building, to Kenai Glass Company. Kenai’s performance was secured by a performance bond issued by Industrial Indemnity Company.

For various reasons, the building was completed and accepted 414 days late. Inasmuch as the principal cause for the delay appeared to be Kenai’s failure to install the curtainwall before the onset of winter, Wick withheld the final payment due Kenai under the subcontract. Kenai sued for the [1103]*1103retamage. Wick counterclaimed, alleging that Kenai breached the subcontract by failing to fabricate and install the curtain-wall in a timely manner. Wick also filed a third party complaint against ASHA, alleging that the architectural specifications provided by that entity were defective and the cause of some, if not all, of the delay. ASHA in turn proceeded against its architects, CCC/HOK.

In August 1980, Wick settled with ASHA and the third party complaint was dismissed. Due to a clerical error, notice of the settlement was not communicated to Kenai until October 28, 1980. On November 17, Kenai moved to continue the December 1 trial date. The motion was denied. Wick prevailed at trial.

Kenai then moved for a new trial on the grounds of newly discovered evidence; the motion was denied. Kenai and Industrial Indemnity filed separate appeals, alleging numerous errors in the conduct of the trial, [appeal nos. 6012 and 6059]. Subsequently, Kenai and Industrial Indemnity also moved for relief from judgment under Alaska Rule Civ.P. 60(b). These motions were denied and the movants appealed [appeal nos. 6758 and 6759]. The cases have been consolidated for argument and decision.

I. DAMAGE ISSUES

A. Introduction

The lower court found that’ Kenai’s delay in fabricating and erecting the eurtainwall accounted for 264 days of the 414 day delay. The court isolated four specific causes of delay: (1) delay in ordering the mullions and muntins (aluminum extrusions forming part of the eurtainwall); (2) delay in requesting permission to change to a two-piece mullion; (3) delay in manufacturing and testing a sample insulated cur-tainwall panel; and, (4) delay in installing the various components.

The lower court found that Wick had suffered three distinct types of harm as a result of Kenai’s failure to install the cur-tainwall in a timely manner: (1) direct damage, consisting of increased labor costs, extended job overhead, unabsorbed home office overhead, and unanticipated winter protection costs; (2) indirect damage in the form of liquidated delay damages paid to the state; and (3) indirect damages in the form of delay damages paid or owing to the other subcontractors on the project. Wick was awarded $765,654.00 in total damages, including profits on its increased costs but excluding interest and attorney’s fees.

Kenai advances an argument with respect to each element of damage. First, it argues that the subcontract limits Wick’s recovery for its direct damage to $400.00 per day of delay.1 Second, it argues that Wick did not actually pay any liquidated damages to the state and thus cannot recover the liquidated damages amount from Kenai. Finally, Kenai argues that it is under no obligation to indemnify Wick for damages paid or owing to the various subcontractors injured by Kenai’s breach.

Subsidiary damage issues include the lower court’s failure to offset the $360,000 received in settlement from ASHA against the judgment returned against Kenai Glass and the proper amount of prejudgment interest.

B. Liquidated Damages.

Clause (a) of the subcontract provides in relevant part:

So far as the SUBCONTRACT work is concerned, SUBCONTRACTOR shall assume toward the CONTRACTOR all the obligations and responsibilities which the [1104]*1104CONTRACTOR assumed toward the owner, and shall be entitled to all the privileges and protections granted to the CONTRACTOR by the owner, by the main contract, ...

Clause (a) is what is known as a flow down or conduit clause. R. Cushman, The Construction Industry Formbook, § 5.08 (1979). Such clauses are designed to incorporate into the subcontract those provisions of the general contract relevant to the subcontractor’s performance. If a conduit clause is used, “the same rights and duties should flow equally from the owner down through the general contractor to the subcontractor, as well as flowing from the subcontractor up through the general contractor to the owner.” Id. The parties to the subcontract thus assume the correlative position of the parties to the prime contract. A. Dib, Forms and Agreements for Architects, Engineers and Contractors, Chap. 7, § 1[1] (1979).

Kenai argues that clause (a) incorporates the liquidated damages provision of the prime contract into the subcontract. The liquidated damages figure specified in the supplementary provisions to the prime contract is $400 per day of delay.2 Accordingly, Kenai asserts that its liability for direct damages incurred by Wick is restricted to $400 per day of delay for which it was responsible. We agree.

Clause (a) of the subcontract confers on Kenai all of the “privileges and protections” as against Wick that the prime contract confers on Wick as against ASHA. The liquidation of delay damages in the prime contract is clearly within the ambit of “privileges and protections” afforded Wick by ASHA. The liquidation provision limits Wick’s liability for delay damages incurred by ASHA to the stipulated amount of $400 per day and thus precludes recovery by ASHA of actual damages in excess of that amount, even if proved. The same limitation of liability for delay damages passes through the conduit clause from the prime contract into the subcontract to protect Kenai as against Wick. This result is in accord with cases in other jurisdictions wherein a damage limitation clause in the prime contract was incorporated into the subcontract through a conduit clause to protect the subcontractor from liability for actual damages incurred by the general contractor. See, e.g., McDaniel v. Ashton-Mardian & Co., 357 F.2d 511, 516-17 (9th Cir.1966); Walter R. Cliffe v. Dupont Eng. Co., 298 F. 649 (D.Del.1924); and Coast Sash and Door Company v. Strom Construction Company, 65 Wash.2d 279, 396 P.2d 803 (1964).

Wick argues to the effect that the conduit clause incorporates only the substantive aspects of the prime contract relating to Kenai’s portion of the work, such as building specifications, and not the remedial provisions.

Free access — add to your briefcase to read the full text and ask questions with AI

Industrial Indemnity Co. v. Wick Construction Co., 680 P.2d 1100, 1984 Alas. LEXIS 278 (Ala. 1984).

680 P.2d 1100 (Industrial Indemnity Co. v. Wick Construction Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Eugene Water & Elec. Bd. v. MWH Ams., Inc.
426 P.3d 142 (Court of Appeals of Oregon, 2018)
Nelson v. Vernco Constr., Inc.
566 S.W.3d 716 (Court of Appeals of Texas, 2018)
Riggs v. Coonradt
335 P.3d 1103 (Alaska Supreme Court, 2014)
Williams v. GEICO Casualty Co.
301 P.3d 1220 (Alaska Supreme Court, 2013)
Safar v. Wells Fargo Bank, N.A.
254 P.3d 1112 (Alaska Supreme Court, 2011)
Barnett v. Barnett
238 P.3d 594 (Alaska Supreme Court, 2010)
Sandy B. v. State, Department of Health & Social Services
216 P.3d 1174 (Alaska Supreme Court, 2009)
Sandy B. v. State, Dept. of Health & Social Services
216 P.3d 1180 (Alaska Supreme Court, 2009)
Harris v. Ahtna, Inc.
193 P.3d 300 (Alaska Supreme Court, 2008)
US EX REL. QUALITY TRUST v. Cajun Contractors
486 F. Supp. 2d 1255 (D. Kansas, 2007)
Miller v. Miller
105 P.3d 1136 (Alaska Supreme Court, 2005)
Bernotas v. Super Fresh Food Markets, Inc.
863 A.2d 478 (Supreme Court of Pennsylvania, 2004)
A.F. Lusi Construction, Inc. v. Peerless Insurance
847 A.2d 254 (Supreme Court of Rhode Island, 2004)
Jackson v. State
31 P.3d 105 (Court of Appeals of Alaska, 2001)
McDougall v. Lumpkin
11 P.3d 990 (Alaska Supreme Court, 2000)