Plum Creek Wastewater Authority v. Aqua-Aerobic Systems, Inc.

597 F. Supp. 2d 1228, 2009 U.S. Dist. LEXIS 3452, 2009 WL 130567
CourtDistrict Court, D. Colorado
DecidedJanuary 20, 2009
DocketCivil Case 08-cv-01606-LTB-KLM
StatusPublished
Cited by3 cases

This text of 597 F. Supp. 2d 1228 (Plum Creek Wastewater Authority v. Aqua-Aerobic Systems, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Plum Creek Wastewater Authority v. Aqua-Aerobic Systems, Inc., 597 F. Supp. 2d 1228, 2009 U.S. Dist. LEXIS 3452, 2009 WL 130567 (D. Colo. 2009).

Opinion

MEMORANDUM OPINION AND ORDER

BABCOCK, District Judge.

This matter is before me on a Motion to Remand Pursuant to 28 U.S.C. § 1447(c) [Doc. # 11], in which Plaintiff, Plum Creek Wastewater Authority (“Plum Creek”), asks that this matter be remanded back to District Court for Douglas County, Colorado, following a Notice of Removal filed by Defendant Aqua-Aerobic Systems, Inc. (“Aqua-Aerobic”). Oral arguments will not materially aid in the resolution of this request. After consideration of the law and the parties’ briefing, I GRANT Plum Creek’s request to remand this case.

On May 23, 2008, Plum Creek filed its complaint in this matter seeking damages against Aqua-Aerobic as the seller/supplier of allegedly faulty “phosphorus filters” that were installed in a wastewater treatment plant constructed and owned by Plum Creek for: breach of contract; breach of express warranty; failure of essential purpose of limited remedy; revocation of acceptance; and negligent misrepresentation. The complaint was initially filed in the District Court for the City and County of Denver, Colorado (Case No. 08-cv-4424), but was subsequently transferred to Douglas County District Court. Aqua-Aerobic then filed a Notice of Removal with this court on July 29, 2008. Plum Creek objects to the removal pursuant to 28 U.S.C. § 1447(c), and seeks remand back to the District Court for Douglas County.

I. REMOVAL

Under 28 U.S.C. § 1441, any action filed in state court in which this court has original jurisdiction may be removed to federal court. Aqua-Aerobic’s Notice of Removal alleges federal jurisdiction pursuant to diversity of citizenship as set forth in 28 *1230 U.S.C. § 1332(a). Section 1332(a) provides that federal district courts have original jurisdiction of all civil actions where the matter in controversy exceeds that sum or value of $75,000.00, exclusive of interest and costs, and there is complete diversity of citizenship between the parties.

Plum Creek concedes that this ease involves complete diversity of citizenship, and does not contest the allegation that matter in controversy exceeds the sum or value of $75,000. Rather, Plum Creek challenges the removal to this court on the basis that this dispute is subject to a forum selection clause that provides that “all civil actions brought in relation to this Contract shall be filed in District Court, Douglas County, State of Colorado.”

II. BACKGROUND

The relevant underlying facts, as alleged in the complaint, are as follows. In 2001, Plum Creek decided to expand its waste-water treatment plant located in Castle Rock, Colorado. Plum Creek retained engineers Rothberg, Tamburini & Winsor (“RTW”) to design and prepare plans and specifications for construction of the plant expansion. RTW’s plan required the use of “phosphorus filters.” In the winter and spring of 2002, prior the bid process for construction, RTW and Plum Creek negotiated with Aqua-Aerobic to use their “tertiary cloth media filter systems” as the phosphorus filters in the expanded waste-water plant. The agreed upon purchase price for the phosphorus filters was $430,000.

When the construction of the wastewa-ter plant went out for bid, the plans and specifications required the general or prime contractor to purchase (for $430,000) and install the phosphorus filters from Aqua-Aerobic. The contract to build the plant was ultimately awarded to Grimm Construction Company (now known as Garvey Construction Company) on or about August 20, 2002. Substantial completion of the project occurred, three years later, on or about June 27, 2005. Plum Creek alleges that after the completion of the wastewater plant, and within the two year warranty period, the filters did not perform as promised despite numerous attempts to repair the system. Thereafter, Plum Creek filed this lawsuit against Aqua-Aerobic.

III. FORUM SELECTION CLAUSE

A plaintiff has an “absolute” statutory right to remove a case to federal court, but this right may be contractually waived by virtue of a forum selection clause. See Excell, Inc. v. Sterling Boiler & Mechanical, Inc., 106 F.3d 318 (10th Cir.1997). Where a forum selection clause agreed to during arms-length negotiations by sophisticated parties, specifies venue and jurisdiction with mandatory or obligatory language, the clause is presumptively valid and must be enforced unless the party seeking to avoid the agreed-to forum demonstrates that enforcement would be unreasonable under the circumstances. In re D.E. Frey Group, Inc., 387 B.R. 799, 804 (D.Colo.2008)(citing M/S Bremen v. Zapata Off-Shore Co., 407 U.S. 1, 10, 92 S.Ct. 1907, 32. L.Ed.2d 513 (1972)); see also Edge Telecom, Inc. v. Sterling Bank, 143 P.3d 1155, 1158 -1159 (Colo.App.2006).

The forum selection clause relied upon here by Plum Creek is set forth in the Prime Contract, dated August 20, 2002, between Plum Creek, as the “Owner,” and Grimm Construction as the “Contractor.” It is entitled “Controlling Law” and states that:

This Contract shall be governed and construed according to the law of the State of Colorado. All civil actions brought in relation to this Contract shall be filed in the District Court, Douglas County, State of Colorado.

*1231 Aqua-Aerobic does not challenge the validity of the forum selection provision. Rather, it argues that it is not bound by the clause and that it is not applicable to this lawsuit. Plum Creek maintains that Aqua-Aerobic is bound to the clause through a flow down clause in the Prime Contract, and a related provision in the applicable Purchase Order.

IV. RELEVANT CONTRACT PROVISIONS

In addition to the forum selection clause, the Prime Contract contains a flow down provision. That provision is entitled “Concerning Subcontractors, Suppliers, and Others” and provides, in its entirety, as follows:

All Work performed for CONTRACTOR by a Subcontractor or Supplier will be pursuant to an appropriate agreement between CONTRACTOR and the Subcontractor or Supplier which specifically binds the Subcontractor or Supplier to the applicable terms and conditions of the Contract Documents for the benefit of the OWNER and ENGINEER.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dynamic CRM v. UMA Education
31 F.4th 914 (Fifth Circuit, 2022)
Nelson v. Vernco Constr., Inc.
566 S.W.3d 716 (Court of Appeals of Texas, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
597 F. Supp. 2d 1228, 2009 U.S. Dist. LEXIS 3452, 2009 WL 130567, Counsel Stack Legal Research, https://law.counselstack.com/opinion/plum-creek-wastewater-authority-v-aqua-aerobic-systems-inc-cod-2009.