Aesco Steel, Inc. v. J.A. Jones Construction Co.

621 F. Supp. 1576, 1985 U.S. Dist. LEXIS 13531
CourtDistrict Court, E.D. Louisiana
DecidedNovember 29, 1985
Docket85-0903
StatusPublished
Cited by8 cases

This text of 621 F. Supp. 1576 (Aesco Steel, Inc. v. J.A. Jones Construction Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aesco Steel, Inc. v. J.A. Jones Construction Co., 621 F. Supp. 1576, 1985 U.S. Dist. LEXIS 13531 (E.D. La. 1985).

Opinion

ORDER & REASONS

CHARLES SCHWARTZ, Jr., District Judge.

This matter is before the Court on the motion of plaintiff, Aesco Steel, for summary judgment and the motion of defendants, J.A. Jones Construction Company, now known as the Jones Group Inc. (“Jones”), and Fidelity Deposit Company of Maryland for summary judgment. There being no disputed issues of fact, the parties having stipulated to all pertinent facts for the purpose of this motion, the motion of Aesco Steel is GRANTED; the motion of J.A. Jones Construction Company, now known as the Jones Group Inc., and Fidelity Deposit Company of Maryland is DENIED.

*1577 Facts

The parties have stipulated to the following material facts for the purpose of this motion. Jones, as contractor, entered into a construction contract with the Louisiana World Exposition, Inc. (“LWE”), as owner, on October 1, 1982, for work in connection with the construction of the International Pavilion, the U.S. Pavilion and Amphitheater at the 1984 Louisiana World Exposition. A notice of that contract was filed in the Mortgage Office for the Parish of Orleans at M.O.B. 2387, Folio 792, on October 1, 1982.

Jones as principal and defendant Fidelity & Deposit Company of Maryland (“F & D”), as surety executed payment and performance bonds in the amount of $23,916,-581. On September 28, 1983, Aesco Steel, Inc. (“Aesco”) as subcontractor, and Jones, as contractor, entered into a subcontract in the amount of $1,592,645 wherein Aesco agreed to furnish the structural steel and metal floor deck for the Amphitheater Project. The subcontract was executed on Jones’ subcontract form. Six change orders to the subcontract were issued increasing the subcontract price to $1,844,-949.

Several change orders were issued by LWE to Jones increasing the contract price to $39,693,298. Jones has received payment in the aggregate amount of $34,843,-101, leaving an unpaid contract balance of $4,850,197.

The construction contract between LWE and Jones was successfully completed by Jones. Aesco fully performed its subcontract with Jones. A certificate of substantial completion was executed by representatives of LWE and Jones on May 1, 1984. A Notice of Termination of the contract was filed in the Mortgage Records of Orleans Parish on May 30, 1985 at M.O.B. 2387, Folio 792.

Pursuant to the contract with LWE, Jones submitted to LWE Applications for Payment on a monthly basis and an Application for Final Payment seeking payment of retainage. Jones was paid in full for work billed and completed through March 1984. The April and May 1984 Applications for Payment and Retainage Withheld were not paid by LWE. To date, these remain either unpaid or partially unpaid.

On May 1, 1984, Jones paid Aesco $84,-000 in retainage. On July 10, 1984, Aesco, through its attorneys, made formal demand on Jones and F & D for the amount of $228,379.90. No payment was received by Aesco from either Jones or F & D within thirty days of the receipt of that demand. On September 11, 1984, Jones paid Aesco an additional $78,000 in retainage. Accordingly, when, on February 27, 1985, Aesco filed suit, the balance of the contractual obligation between Jones and Aesco was $149,852.40. After the filing of the suit, two payments were received from Jones by Aesco — one in the amount of $57,279.85 and the other in the amount of $11,479.19. Both of these amounts were paid on March 24, 1985. As of the date of the submission of this motion, the remaining unpaid subcontract balance was $80,320.73 of which Jones claims $22,244.40 is retainage.

In August 1984, Jones executed a Contractor’s Joinder Agreement, which allowed LWE Contractors, such as Jones, to participate in certain revenues flowing from the Co-operative Endeavor Agreement dated July 1, 1984. Additionally, Jones entered into an agreement with the Rouse Company, Inc. (“Rouse”) agreeing to grant a partial release of its lien on that portion of the International Pavilion which was purchased by Rouse. In exchange for this release, Jones was entitled to participation in the revenues generated by the Rouse purchase of LWE assets.

LWE experienced financial difficulties and filed a Chapter 11 Reorganization Proceeding (Bankruptcy Case No. 84-02314-K) on November 6, 1984. That case is still pending in the United States Bankruptcy Court for the Eastern District of Louisiana.

In an effort to recover the unpaid balances owed Jones by LWE, Jones has filed a Proof of Claim in the Bankruptcy Proceedings and is one of the contractors of the “Contractors Creditors Committee” in that proceeding. That Committee obtained an order authorizing the bringing of an *1578 action and did bring an action in the name of LWE against certain officers and directors of LWE and their insurers. The Bankruptcy Court appointed an examiner to issue a preliminary report recommending that a preference action be filed seeking recovery of all payments made to contractors under the Co-operative Endeavor Agreement and the Rouse Agreement.

On June 22, 1984, Jones filed a lien which includes any amounts yet to be paid to Aesco. On June 28, 1985, Jones filed suit to enforce the lien in the Civil District Court for the Parish of Orleans, Case No. 85-11173.

Jones has paid Aesco all amounts paid to Jones by LWE and attributable to work performed by Aesco. Jones continues to pursue collections of monies owed to Jones by LWE under the contract by pursuing its claim in the United States Bankruptcy Court for the Eastern District of Louisiana.

The Liability of the Contractor

A J.A. Jones Construction subcontract form was executed by the parties in late October or early November 1983. The applicable section of that contract, Article 4, provides “[a] final payment, consisting of the unpaid balance of the Price, shall be made within forty-five (45) days after the last of the following to occur: (a) full completion of the Work by Subcontractor, (b) final acceptance of the work by the Architect and Owner[,] (c) final payment by Owner to Contractor under the Contract, (d) the furnishing of satisfactory evidence by Subcontractor to Contractor that the Subcontractor has paid in full all persons furnishing labor, materials or service in connection with the Work and that neither Subcontractor nor any person claiming under or through Subcontractor has filed or has the right to maintain a lien or other claim against the Owner, the Contractor, Contractor’s surety, if any, or the Project premises, (e) the return of all drawings, plans and specifications to the Contractor or Architect, and (f) the delivery of all guarantees, warranties, bonds, instruction manuals, performance charts, diagrams, as built drawings and similar items with respect to the Work.” 1 The parties agree that all of the enumerated items in Article 4 have been fulfilled but for Section (c), “final payment by Owner to Contractor under the Contract.” The owner, LWE, has been unable or unwilling to make final payment and is presently involved in a still pending Chapter 11 Reorganization proceeding in the United States Bankruptcy Court for the Eastern District of Louisiana.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
621 F. Supp. 1576, 1985 U.S. Dist. LEXIS 13531, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aesco-steel-inc-v-ja-jones-construction-co-laed-1985.