Subdivision Plan. Eng., Inc. v. Manor Develop. Corp.

290 So. 2d 375
CourtLouisiana Court of Appeal
DecidedFebruary 15, 1974
Docket5683
StatusPublished
Cited by13 cases

This text of 290 So. 2d 375 (Subdivision Plan. Eng., Inc. v. Manor Develop. Corp.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Subdivision Plan. Eng., Inc. v. Manor Develop. Corp., 290 So. 2d 375 (La. Ct. App. 1974).

Opinion

290 So.2d 375 (1974)

SUBDIVISION PLANNING ENGINEERS, INC.
v.
MANOR DEVELOPMENT CORPORATION and Trinity Universal Insurance Company.

No. 5683.

Court of Appeal of Louisiana, Fourth Circuit.

February 15, 1974.
Rehearing Denied March 8, 1974.

*376 Greenberg, Cohen & Dallam, (Nathan Greenberg) Gretna, for plaintiff-appellee.

Zeringer & Zeringer (Harold J. Zeringer, Jr.), James H. Drury, and Bienvenu & Culver (P. A. Bienvenu), New Orleans, for defendants-appellants.

Before STOULIG, J., and MALIK and MARINO, JJ. Pro Tem.

STOULIG, Judge.

Plaintiff, Subdivision Planning Engineers, Inc., filed suit to recover a $57,240 balance it alleged is due for engineering *377 and surveying work performed in the Live Oak Manor Subdivision near Waggaman, Louisiana. Alternatively, plaintiff sought a judgment in quantum meruit. It further prayed for recognition of its lien on all 1,129 lots of the subdivision. Named defendants were the owner and developer, Manor Development Corporation (Manor), and Trinity Universal Insurance Company, who furnished the lien bond to effect the cancellation of the recorded encumbrances against the subdivision so that individual houses could be sold.

From a judgment awarding plaintiff $21,540 and recognizing lien rights on 534 of the lots, the defendants have appealed. Plaintiffs have answered the appeal seeking an increase in the award.

Before considering the merits, we point out that we will not apply the presumption that the findings of the trial court are correct. This is so because this matter was tried by one judge but decided by another. After Judge Frederick Heebe was appointed to the federal bench before the trial was concluded, counsel stipulated his successor, the Honorable Frank Zaccaria, could adjudicate this cause on the evidence previously adduced. Since Judge Zaccaria did not have the opportunity to observe the witnesses as they testified his factual findings cannot be accorded the weight usually assigned to a trial judge's conclusions of fact. Smythe v. Great American Indemnity Co., 35 So.2d 267 (La.App. 2d Cir. 1948); Walker v. Mire, 197 So. 798 (La.App. 1st Cir. 1940).

Turning to the merits, the record indicates MacDuff Fletcher of Manor entered into preliminary negotiations with Ralph Davenport and John Mitchell, the principals of plaintiff corporation, to obtain preliminary engineering and surveying services in laying out a subdivision defendant planned to develop. The principals of Manor were Fletcher, James Culotta and Joseph Montaldo.

The testimony of Fletcher, Davenport and Mitchell is in accord on these points: plaintiff was asked to engineer and survey the entire subdivision which was to be composed of 1,129 lots; plaintiff was not advised that Manor did not own the entire tract when its services were requested; plaintiff's agents did not inquire whether Manor owned the entire tract before commencing work; plaintiff agreed to undertake the contract for a total price of $67,540 and at defendant's request figured the job on a unit basis arriving at a $60-per-lot figure; and plaintiff had performed a substantial amount of the work required under the contract by June 22, 1959.

During the first six months of 1959, defendant's principals began implementing their plans so that construction could begin once the preliminary engineering and surveying were complete. They formed three business entities, i. e. Manor Development Corporation, Mercury Construction Company, Inc., and M. M. & J. Co., a partnership. Through the various companies, defendant's principals obtained 500 FHA loan commitments (250 operative builders commitments and 250 conditional commitments). Interim financing with the National Bank of Commerce and permanent financing with Fidelity Bond and Mortgage Co., Inc., had been arranged by Manor for the proposed construction.

On June 22, 1959, at which time plaintiff was already furnishing services, Fletcher, acting as an officer of Manor, wrote the following letter to the plaintiff corporation summarizing their verbal contract:

"This letter will serve to confirm our agreement and understanding relative to the services and work which you are performing and rendering for us in Live Oak Manor Sub-Division, Jefferson Parish, Louisiana.
"You have undertaken for us to do all of the preliminary surveying and engineering, including installation of square cornered stakes, roadway design, drainage, water, and sewer layout design, the establishing of base control lines in Live *378 Oak Manor Sub-Division, containing 1129 lots, of Jefferson Parish, all for the sum and price of $60.00 per lot, plus the exclusive rights for the closing surveys at a price of $30.00 per lot (consideration for these closing surveys to be paid at act of sale). The total contract price, based on 1129 lots at $60.00 per lot is $67,740.00.
"Said sum of $60.00 per lot is to be paid in three payments of $20.00 each, as the developer receives its payments. It is further understood and agreed that the above price shall cover only the cost of installing the initial stakes. Your responsibility includes checking the off-site contractor's work, to preclude errors on his part which might cause delay.
"A substantial part of this work has already been completed and accepted, in fact, commitments have already been received from the FHA as to a part of the sub-division.
"The purpose of this letter is to properly reflect our agreement and our records show that you have already received payments totaling $2,590.14 from us against the total contract price. The remainder of the funds due you will, of course, only be paid to you as we receive funds under our owner-builder commitments."

It was not until three days later (June 25) that M. M. & J. Co. acquired the entire tract of ground, consisting of 1,129 lots, of which it conveyed only 534 sites to Manor for development.

On July 30, 1959, the Jefferson Parish Council adopted an ordinance accepting the plan of subdivision of the 1,129 lots prepared by plaintiff.

Almost from the outset, the developer encountered financial difficulties. First, the National Bank of Commerce limited its commitment of interim financing to 100 homes; next the off-site improvements contract for the first section did not progress as anticipated; and when the homes were completed, the sales were slow. Although Manor obtained two further interim loans to finance construction of a total of 90 more homes, the project was doomed to financial failure.

In the spring of 1961, the two principal mortgage holders, Mehr, Inc. (M. M. & J. Co.'s vendor), and the National Bank of Commerce, interim financing institution, initiated foreclosure proceedings. At this point, defendant Trinity, surety on the performance bond of the on-site construction being built by Mercury Construction Co., intervened in an attempt to salvage what it could from the operation. Without going into great detail, we simply note Manor transferred the remaining 160 lots it owned to another corporation, Wiljon,[1] who was to undertake completion of the unfinished homes and also was to construct the balance of the houses for which FHA commitments had been issued. So that these properties could be sold, Trinity had executed a lien bond on October 17, 1961 and paid some $285,000 on previously recorded liens. However, the plaintiff's lien affidavit for $57,240 filed on September 14, 1961 was not one of those paid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern St. Masonry v. JA Jones Const.
507 So. 2d 198 (Supreme Court of Louisiana, 1987)
Strahan v. LANDIS CONST. CO., INC.
499 So. 2d 417 (Louisiana Court of Appeal, 1987)
Southern States Masonry, Inc. v. JA JONES CONST. CO., INC.
498 So. 2d 151 (Louisiana Court of Appeal, 1987)
Cahn Elec. Co., Inc. v. Robert E. McKee, Inc.
490 So. 2d 647 (Louisiana Court of Appeal, 1986)
Aesco Steel, Inc. v. J.A. Jones Construction Co.
621 F. Supp. 1576 (E.D. Louisiana, 1985)
McGee v. SEWERAGE AND WATER BD., ETC.
396 So. 2d 430 (Louisiana Court of Appeal, 1981)
Merchant v. Dept. of Finance
391 So. 2d 587 (Louisiana Court of Appeal, 1980)
Johansen v. Port Jewell Inc.
351 So. 2d 184 (Louisiana Court of Appeal, 1977)
Subdivision Planning Engineers, Inc. v. Manor Development Corp.
349 So. 2d 247 (Supreme Court of Louisiana, 1977)
Subdivision Planning Engineers, Inc. v. Manor Development Corp.
337 So. 2d 618 (Louisiana Court of Appeal, 1976)
Gauguin, Incorporated v. Spring
316 So. 2d 858 (Louisiana Court of Appeal, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
290 So. 2d 375, Counsel Stack Legal Research, https://law.counselstack.com/opinion/subdivision-plan-eng-inc-v-manor-develop-corp-lactapp-1974.