Perini/Tompkins Joint Venture v. ACE American Insurance Company

738 F.3d 95, 2013 WL 6570947, 2013 U.S. App. LEXIS 24865
CourtCourt of Appeals for the Fourth Circuit
DecidedDecember 16, 2013
Docket19-7756
StatusPublished
Cited by60 cases

This text of 738 F.3d 95 (Perini/Tompkins Joint Venture v. ACE American Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perini/Tompkins Joint Venture v. ACE American Insurance Company, 738 F.3d 95, 2013 WL 6570947, 2013 U.S. App. LEXIS 24865 (4th Cir. 2013).

Opinion

Affirmed by published opinion. Judge THACKER wrote the opinion, in which Judge SHEDD and Senior Judge HAMILTON joined.

THACKER, Circuit Judge:

Perini/Tompkins Joint Venture (“PTJV” or “Appellant”) appeals the district court’s grant of summary judgment in favor of ACE American Insurance Co. (“ACE” or “Appellee”). PTJV filed suit, claiming coverage under primary and excess insurance policies with regard to a large-scale construction project in Oxon Hill, Maryland. The district court determined ACE was entitled to summary judgment because PTJV did not obtain ACE’s consent before settling the underlying dispute regarding property damage at the construction site and, pursuant to the insurance contract, PTJV was required to do so at the risk of relinquishing coverage. We hold that under Maryland and Tennessee law, PTJV violated the terms of both the primary and excess policies by not obtaining ACE’s consent before settlement, and as ■ such, cannot now claim reimbursement under those policies. We thus affirm the district court.

I.

A.

The Project

In 2005, Gaylord National LLC (“Gay-lord”) hired PTJV, a joint venture between *98 the Perini Building Company and Turner Construction Company, to serve as manager in connection with the construction of a $900 million hotel and convention center in Oxon Hill, Maryland (the “Project”). As part of the construction contract between PTJV and Gaylord (the “Contract”), Gay-lord agreed to purchase and maintain an Owner Controlled Insurance Program (“OCIP”), which was a program crafted and sold by ACE to insure only the Project and its participants.

Gaylord then purchased from ACE an OCIP Commercial General Liability Insurance Policy (the “Primary Policy”), providing a limit of $2 million per occurrence, and an OCIP Excess Liability Policy (the “Excess Policy”), providing a limit of $25 million per occurrence (collectively, the “Policies”). The Policies provided coverage for the period from May 23, 2005, to August 30, 2008. By endorsement, PTJV was added as a named insured on the Policies. The Project was also insured by a Builders Risk Policy through Factory Mutual Insurance Company (“FM Global”).

During construction of the signature feature of the building — an 18-story, 2,400 ton glass atrium — serious property damage occurred. The damage is described in the Complaint as follows:

10. A significant portion of the Project involved the construction of a glass roof atrium. The atrium was composed of numerous subsections, called trusses, that were preassembled on the ground and lifted via crane into place. Each truss contained several components, including supportive tension rods that were connected by rod/clevis junctures.
11. The atrium was under construction on or about August 28, 2007 while Truss H4 was lifted into position and, on or about August 31, 2007, certain components were added to the atrium that placed additional pressure and tension on Truss H4, causing, unbeknownst to either Gaylord or PTJV, one of the rod/clevis junctures on Truss H4 to slowly erode.
12. On September 5, 2007, the rod/clevis juncture on Truss H4, which began eroding no later than August 31, 2007, failed. That failure caused a loss of tension that substantially impaired the structural integrity of the atrium (the “Collapse”).
13. The Collapse caused damage to various components of the Project and required a temporary suspension of the Project and such damages were neither expected nor intended from the standpoint of PTJV.

J.A. 21. 1 A representative from ACE was on site at the Project at the time of the Collapse and thereafter. The Project was scheduled to be completed in December 2007, but due to various delays (including the Collapse), the completion date was pushed to March 2008.

B.

The Underlying Litigation

After the Project was completed, litigation ensued. On September 18, 2008, PTJV filed a complaint against Gaylord for establishment and enforcement of a mechanic’s lien, breach of contract, quantum meruit, and violation of the Maryland Prompt Payment Act. See Perini/Tompkins Joint Venture, et al. v. Gaylord Nat’l, LLC, No. CAE08-24316 (Cir.Ct.Md. Sept. 18, 2008) (the “PTJV action”). PTJV alleged Gaylord still owed $79,656,098 under the Contract and asked for damages plus interest, costs, and fees. The claims were based on the costs allegedly incurred due *99 to Gaylord’s late delivery of the Project designs and its alleged changes to the original scope of the work.

Subsequently, on October 10, 2008, Gay-lord countersued, filing a complaint against PTJV for breach of contract and breach of fiduciary duty. See Gaylord Nat'l LLC v. Perini/Tompkins Joint Venture, No. CAE08-27201 (Cir.Ct.Md. Oct. 10, 2008) (the “Gaylord action”). Gaylord claimed PTJV failed to properly manage scheduling, costs, and budgets, and failed to build a high-quality project at the agreed-upon price. Specifically, Gaylord alleged it paid .PTJV $802,085,712, when it • should have only paid $737,091,338. Thus, • Gaylord sought reimbursement of approximately $65 million in damages resulting from the alleged overpayment. Notably, PTJV did not notify ACE of the Gaylord action.

Gaylord and PTJV settled the Gaylord action on November 26, 2008. 2 Gaylord paid an additional $42,301,875 (for a total of almost $845 million) and PTJV credited $26,157,912 back to Gaylord. Crucial to this appeal, PTJV never sought to obtain ACE’s consent prior to entering into this settlement.

C.

The Coverage Litigation

On May 6, 2009, almost six months after the settlement and nearly two years after the Collapse, PTJV sent a letter to ACE advising that, to the extent FM Global did not pay the claim related to the Collapse, PTJV intended to seek reimbursement from ACE. This letter was the first formal, written notice of a claim to ACE, although ACE concedes its representative was present on the site when the Collapse occurred. However, this letter did not mention the settlement or the Gaylord action at all. Over ten months later, on February 23, 2010, ACE issued a reservation of rights letter, citing “[bjusiness [rjisk” exclusions, late notice, and voluntary payments made without ACE’s consent as potential grounds for denial of coverage. -On April 29, 2010, FM Global denied PTJV’s claims.

After several additional months of baek- and-forth between PTJV and ACE, on December 13, 2010, PTJV filed suit against ACE in the United States District Court for the District-of Maryland, alleging

(1) Count One: breach of contract/bad faith/implied covenant of good faith and fair dealing (ACE “refused and/or neglected to pay any portion of the [cjlaims [regarding the Collapse] pursuant to the Primary Policy or the Excess Policy and is in breach of its contractual obligations to PTJV.”);
(2) Count Two: a declaratory judgment “to determine the rights and duties of PTJV and ACE pursuant to the Primary Policy and the Excess Policy”; and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
738 F.3d 95, 2013 WL 6570947, 2013 U.S. App. LEXIS 24865, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perinitompkins-joint-venture-v-ace-american-insurance-company-ca4-2013.