Wickersham Construction and Engineering, Inc. v. The Town of Sudlersville, Maryland

CourtDistrict Court, D. Maryland
DecidedSeptember 22, 2020
Docket1:16-cv-04087
StatusUnknown

This text of Wickersham Construction and Engineering, Inc. v. The Town of Sudlersville, Maryland (Wickersham Construction and Engineering, Inc. v. The Town of Sudlersville, Maryland) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wickersham Construction and Engineering, Inc. v. The Town of Sudlersville, Maryland, (D. Md. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

Wickersham Construction and * Engineering, Inc. * * v. * Civil Action No. CCB-16-4087 * The Town of Sudlersville, Maryland * MEMORANDUM

This is a breach of contract action brought by Wickersham Construction and Engineering, Inc. (“Wickersham”) against the Town of Sudlersville, Maryland (“Sudlersville”). The court held a four-day bench trial beginning January 27, 2020. What follows constitutes the court’s findings of fact and conclusions of law pursuant to Fed. R. Civ. P. 52. For the reasons stated below, the court finds that Sudlersville materially breached the contract by paying Wickersham late, and caused some of the delays for which an equitable adjustment of the contract price is warranted. The court will award damages to Wickersham in the amount of $402,000.22. I. BACKGROUND This case arises from a construction project to upgrade a wastewater treatment plant in Sudlersville, Maryland. Sudlersville is a small town in the eastern part of Maryland, with a population of about 415. (Testimony of Jo Manning). Sometime in 2012, the state of Maryland required that Sudlersville upgrade its wastewater processing, which involved building a new wastewater treatment plant. (Testimony of Manning and Ronald Ford). As Sudlersville did not have the money to do this, it obtained a loan and grant from the U.S. Department of Agriculture and grants from the Maryland Department of Energy (“MDE”). (Testimony of Manning). The town’s engineer, KCI Technologies, Inc. (“KCI”), designed the new treatment plant. Dan String of KCI was the project designer, Peter Bourne was the liaison between the town and KCI, and, after construction started, Jessie Downey was the inspector for the project. (Id.). Sudlersville employed a part-time town manager, Jo Manning, who helped to administer the project on behalf of the town. She procured funding for the project, obtained permits, and was involved in the bidding process. (Id.). KCI also played a large role in contract administration and in the bidding process. (Testimony of Dan String). The bid was eventually awarded to Wickersham Constructing and Engineering, a general contractor located in Pennsylvania. (Testimony of Manning). Sudlersville and Wickersham entered into the contract on July 18, 2014. The contract

consisted of the Form of Agreement (Joint Exhibit (“J.X.”) 1), the Standard General Conditions of the Construction Contract (J.X. 2), and the Supplementary Conditions (J.X. 3). The total contract price was $6,204,000. (Plaintiff’s Exhibit (“P.X.”) 102, Change Order No. 4 showing original contract price). The supplementary conditions specified that the project was financed in whole or in part by the USDA Rural Utilities Service, and the Agency for the contract was USDA Rural Development (“USDA”). (Supplementary Condition 1.01.A.2). KCI, the engineer, was the town’s representative under the contract. (General Condition 9.01). KCI was responsible for initially approving Wickersham’s payment applications, and for monitoring Wickersham’s work on site. KCI was also, under the contract, the first point of contact for dispute resolution and contract interpretation, and performed some contract administration

duties, such as leading project meetings. (Testimony of String). The parties to the contract were Sudlersville (as the owner) and Wickersham (as the contractor); neither USDA, MDE, nor KCI were parties. (See Form of Agreement at 6, Signature Page). The contract provided for progress payments to Wickersham. First, applications for payments were submitted to the engineer. (General Condition 14.02.A.1). The engineer would, within ten days, either recommend payment and present the application to Sudlersville, or refuse to recommend payment and indicate the reasons why. (General Condition 14.02.B.1). Sudlersville then sent the payment applications to the agency (USDA) for approval, which was required for payment. (Supplementary Conditions 1.01.A.3, 14.02.A.4 (“The Agency must approve all Applications for Payment before payment is made”)). The contract provided that: The Application for Payment with Engineer’s recommendations will be presented to the Owner and Agency for consideration. If both the Owner and Agency find the Application for Payment acceptable, the recommended amount less any reductions under the provisions of Paragraph 14.02.D will become due ten days after the Application for Payment is presented to the Owner, and the Owner will make payment to the Contractor.

(Supplementary Condition 14.02.C.1).

The notes of the July 18, 2014, preconstruction meeting indicate, however, that Wickersham was informed that payment could be expected thirty days after the pay application was submitted. (Defense Exhibit (“D.X.”) 43, at PC-20). This is different from the terms of the contract, which appear to provide a maximum of twenty days for payment if the engineer, Sudlersville, and USDA approve: ten days for KCI to approve and present to Sudlersville (General Condition 14.02.B.1), and ten days for Sudlersville to pay (Supplementary Condition 14.02.C.1). The contract unfortunately did not state what would happen if USDA did not approve the application for payment within ten days after the application was presented to the owner, and did not mention MDE’s role at all. Additionally, the process by which Sudlersville received the funds was not conducive to meeting the twenty-day deadline. Manning testified that obtaining the release of funds from the agencies was a cumbersome process: she would send the pay request for MDE to approve, then create a USDA pay request and three MDE pay requests (for the three MDE grants), get MDE to sign the documents, and then get USDA to sign the documents. (Testimony of Manning). According to Manning, MDE generally took significantly longer than USDA to release funds, with USDA typically taking ten days, and MDE typically taking thirty to forty-five days. (Id.). Further, USDA did not know how much it had to pay as to each application (even if it had already approved the application) until MDE had also approved the application and stated how much it would pay. (Id.). At one point, Sudlersville attempted to obtain additional funding for an interim loan to bridge the gap in agency funding, but was only able to obtain a $550,000 loan, with the ability to redraw up to $850,000. (Id.). KCI was responsible for answering requests for information (“RFI”). An RFI might reveal missing design elements, in which case Wickersham would submit a pricing change order

(“PCO”), which would allow Wickersham to do additional necessary work that was not included in the original design, and to be paid for that work. (Testimony of Brad Smith). A PCO, if approved by the engineer, became a change order. A change order officially modified the contract, to give the contractor extra pay and/or extra time in accordance with the new work that must be completed. (Id.). A. August 2014–September 2015 Wickersham was issued a Notice to Proceed with a start date of August 4, 2014. (D.X. 43, Pre-Construction Meeting Minutes, at PC-5). The Notice to Proceed provided a substantial completion date for the wastewater treatment project of July 30, 2015, and a final completion date of August 29, 2015. (Id.; P.X. 97, Versaw’s Report of Findings (“Expert Report”) at 7).1

Although there were delays, including some due to weather, it appears the first major change did not come until June 2015, when the parties executed Change Order 4. (Expert Report at 22). Change Order 4 changed the design of the influent pump station, which cost an additional $86,740,2 and added eighteen days to the substantial completion date and 133 days to the final

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Munday v. Waste Management of North America, Inc.
997 F. Supp. 681 (D. Maryland, 1998)
Chirichella v. Erwin
310 A.2d 555 (Court of Appeals of Maryland, 1973)
Richard F. Kline, Inc. v. Shook Excavating & Hauling, Inc.
885 A.2d 381 (Court of Special Appeals of Maryland, 2005)
Nova Research, Inc. v. Penske Truck Leasing Co.
952 A.2d 275 (Court of Appeals of Maryland, 2008)
Harford County v. Town of Bel Air
704 A.2d 421 (Court of Appeals of Maryland, 1998)
Baltimore Luggage Co. v. Ligon
118 A.2d 665 (Court of Appeals of Maryland, 1955)
Noyes Air Conditioning Contractors, Inc. v. Wilson Towers Ltd. Partnership
712 A.2d 126 (Court of Special Appeals of Maryland, 1998)
Taylor v. NationsBank, N.A.
776 A.2d 645 (Court of Appeals of Maryland, 2001)
Atlantic Contracting & Material Co. v. Ulico Casualty Co.
844 A.2d 460 (Court of Appeals of Maryland, 2004)
Maryland National Bank v. Cummins
588 A.2d 1205 (Court of Appeals of Maryland, 1991)
Asibem Assoc., Ltd. v. Rill
286 A.2d 160 (Court of Appeals of Maryland, 1972)
Stone v. Stone
368 A.2d 496 (Court of Special Appeals of Maryland, 1977)
Harford County v. Saks Fifth Avenue Distribution Co.
923 A.2d 1 (Court of Appeals of Maryland, 2007)
Baltimore County v. Aecom Services, Inc.
28 A.3d 11 (Court of Special Appeals of Maryland, 2011)
Buxton v. Buxton
770 A.2d 152 (Court of Appeals of Maryland, 2001)
Ocean City, MD., Chamber of Commerce, Inc. v. Barufaldi
75 A.3d 952 (Court of Appeals of Maryland, 2013)
Deyesu v. Donhauser
846 A.2d 28 (Court of Special Appeals of Maryland, 2004)
Johnson v. Oroweat Foods Co.
785 F.2d 503 (Fourth Circuit, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Wickersham Construction and Engineering, Inc. v. The Town of Sudlersville, Maryland, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wickersham-construction-and-engineering-inc-v-the-town-of-sudlersville-mdd-2020.