Wickersham Construction and Engineering, Inc. v. The Town of Sudlersville, Maryland

CourtDistrict Court, D. Maryland
DecidedAugust 23, 2019
Docket1:16-cv-04087
StatusUnknown

This text of Wickersham Construction and Engineering, Inc. v. The Town of Sudlersville, Maryland (Wickersham Construction and Engineering, Inc. v. The Town of Sudlersville, Maryland) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wickersham Construction and Engineering, Inc. v. The Town of Sudlersville, Maryland, (D. Md. 2019).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND WICKERSHAM CONSTRUCTION & * ENGINEERING, INC. *

v. * Civil Action No. CCB-16-4087

THE TOWN OF SUDLERSVILLE, * MARYLAND * MEMORANDUM Pending before the court is the plaintiff s motion for partial summary judgment. On June 6, 2019, the court heard oral argument in this matter. For the reasons stated below, the court will deny the motion. FACTUAL AND PROCEDURAL HISTORY This case involves. a prolonged contractual dispute between plaintiff Wickersham Construction and Engineering (“Wickersham”) and defendant the Town of Sudlersville, Maryland (“Sudiersville”). The parties have been engaged in a years-long disagreement regarding Wickersham’s construction of an updated wastewater treatment system for Sudlersville, and the court will recite only the relevant portions of the parties’ history here. Sudlersville is a town located on the Eastern Shore of Maryland. Populated by approximately 560 residents, Sudlersville is a small, quiet community with two town employees and an annual budget under $400,000.00. Ex. 8, ECF 42-8 at 2-3. Elizabeth Manning, Sudlersville’s town administrator, manages much of the town’s affairs by working two days a week from 9:30 a.m. until 5:00 p.m. and another partial day each week from 1:00 p.m. until 5:00 p.m. Ex. 1, ECF 63-2 at p. 3. By virtue of its proximity to the Chesapeake Bay, Sudlersville was required to update its wastewater treatment system. Unable to afford the approximately $8,000,000,00 update on its

own, the town received significant grant funding from the federal and state government to enable Sudlersville to finance the project. The sources of the grant funding included the U.S. Department of Agriculture (“USDA”) and the Maryland Department of the Environment (“MDE”). Ex. 1, ECF 63-2 at p. 4. On July 18, 2014, the parties entered into a contract for the installation and construction of the updated wastewater treatment system. The contract is comprised of three separate documents: the form of agreement, Ex. 2, ECF 56-4, the standard general conditions, Ex. 3, ECF 56-5, and the supplementary conditions, Ex. 4, ECF 56-6. The supplementary conditions note that the USDA □ financed the project in whole or in part, and that the USDA had to approve ail payment applications prior to payment being made. Ex. 4, ECF 56-6 at ff SC-101.A.2, SC-101.A.3. The contract was based on a form contract that USDA provided to the parties, but a boilerplate paragraph requiring interest for late payments was excluded from the final agreement. See Ex. 2, ECF 56-4 at p. 4; Angela Tilghman Dep., Ex. 2, ECF 63-3 at p. 3. The USDA and the MDE were not parties to the contract and were not involved in its drafting, although the contract acknowledged explicitly that the USDA funded the project. Ex. 4, ECF 56-6 at | SC-1.01.A.2. The contract specified that it is to be governed by Maryland law. Ex. 3, ECF 56-5 at 917.05. The parties do not dispute that this contract is valid and enforceable. The contract obligated Sudlersville to pay Wickersham for its construction services, and payments essentially were due twenty days after Wickersham submitted the request for payment, referred to as the “payment application.”’ Ex. 3, ECF 56-5 at § 14.02. The contract provided for

' The parties’ construction contract states that: Engineer will, within 10 days after receipt of each.Application for Payment, either indicate in writing a recommendation of payment and present to [sic] Application to Owner or return the Application to Contractor indicating in writing Engineer's reasons for refusing

ry

twenty such payment applications. At the time of oral argument, all of the payment applications except payments nineteen and twenty, totaling approximately $125,000.00, had been satisfied, and

the outstanding payments form the center of the parties’ dispute.” Neither party disputed that every submitted payment application was paid after the 20-day period. Ms. Manning claimed that, due to the grant funding of the project, she would complete payment requests immediately after receiving approval of the requests and the related funds from MDE or USDA, with KCI’s certification. Ex. 1, ECF 63-2 at p. 12. Despite the payment schedule outlined in the contract, no payments were satisfied on time, and most were paid significantly after the expiration of the 20-day period. Ex. 7, ECF 56-9 at pp, 1-2. After the first eight payments were paid late, and with payments nine and ten past due, Wickersham notified Sudlersville on or about September 9, 2015, that it was considering suspending work on the project. Ex, 8, ECF 56-10. On September 22, 2015, Wickersham suspended work. Ex. 9, ECF 56-11. In an attempt to rectify the problems regarding its payments, Sudlersville then obtained separate financing from Shore National Bank to serve as an intermediary source of funds while the USDA reviewed payment applications. In addition to the notices regarding suspension, Wickersham sent Sudlersville at least one letter regarding the

to recommend payment. In the latter case, Contractor may make the necessary corrections and resubmit the Application: Standard General Conditions, Ex. 3, ECF 56-5 at { 14.02B1. Further, the contract provides that “[t]en days after presentation of the Application for Payment to Owner with Engineer’s recommendation, the amount recommended will (subject to the provisions of Paragraph 14.02D) become due, and when due will be paid by Owner to Contractor,” resulting in the 20-day period noted above. Id. at § 14.02C1. During the June 6, 2019, hearing, Wickersham clarified that, in providing information about how each of the eighteen completed payments were paid late, it was attempting to illustrate the history between the parties rather than asserting a claim for breach of contract based on those late payments. It is unclear how much of the total damages requested in the amended complaint reflect damages incurred solely due to outstanding payments nineteen and twenty, but the court need not resolve the issue at this time, given that Wickersham has requested summary judgment solely on the issue of liability rather than liability and damages.

delayed payments. Ex. 4; ECF 63-5. On March 7, 2016, Wickersham resumed work on the project following assurances from Sudlersville that it would make payments on time due to its separate financing through Shore National Bank. Ex. 1, ECF 56-2 at JJ 8-9. Wickersham claimed that it reached substantial completion on the project no later than November 3, 2016, Ex. 5, ECF 56-7 at p. 3, and that it therefore terniinated the project on September 19, 2017, Ex. 13, ECF 56-15 at p. 1. During the June 6 hearing, Wickersham asserted that the plant’s upgrades have operated in compliance with the project’s terms for three years. As a result, Wickersham claimed that it has long been owed payments nineteen and twenty, and that Sudlersville’s failure to complete these payments constituted breach of contract. Sudlersville disputed Wickersham’ s claim, asserting that, while the plant was operational throughout the project’s construction, the project remains open under the terms of the contract due to Wickersham’s failure to satisfy certain conditions precedent to termination of the contract. This, Sudlersville claimed, insulated it from liability for failure to complete the final two payment applications, as its payment obligation could not be triggered absent completion of those conditions precedent. Additionally, Sudlersville noted that it had not, at the time of the June 6 hearing, received approval of those payment applications from either USDA or KCI, precluding it from completing the payment applications pursuant to the contract’s terms. Wickersham initiated suit on December 23, 2016, and filed its amended complaint on January 1, 2018, after the parties were unable to reach an agreement in mediation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Dulaney v. Packaging Corp. of America
673 F.3d 323 (Fourth Circuit, 2012)
Libertarian Party of Virginia v. Charles Judd
718 F.3d 308 (Fourth Circuit, 2013)
Chirichella v. Erwin
310 A.2d 555 (Court of Appeals of Maryland, 1973)
Christina Jacobs v. N.C. Admin. Office of the Courts
780 F.3d 562 (Fourth Circuit, 2015)
Chevron U.S.A. Inc. v. Apex Oil Co.
113 F. Supp. 3d 807 (D. Maryland, 2015)
White Marlin Open, Inc. v. Heasley
262 F. Supp. 3d 228 (D. Maryland, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Wickersham Construction and Engineering, Inc. v. The Town of Sudlersville, Maryland, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wickersham-construction-and-engineering-inc-v-the-town-of-sudlersville-mdd-2019.