Deyesu v. Donhauser

846 A.2d 28, 156 Md. App. 124, 2004 Md. App. LEXIS 30, 2004 WL 690929
CourtCourt of Special Appeals of Maryland
DecidedApril 2, 2004
DocketNo. 301
StatusPublished
Cited by4 cases

This text of 846 A.2d 28 (Deyesu v. Donhauser) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Deyesu v. Donhauser, 846 A.2d 28, 156 Md. App. 124, 2004 Md. App. LEXIS 30, 2004 WL 690929 (Md. Ct. App. 2004).

Opinion

DEBORAH S. EYLER, J.

In the Circuit Court for Harford County, Dale and Jean M. Donhauser, d/b/a Wizard’s Knoll Log Homes (“Wizard’s Knoll”), the appellees, brought a mechanic’s lien claim against Jodie and Anthony Deyesu, the appellants. Wizard’s Knoll sought to recover for work performed under a contract they entered into with the Deyesus to construct the exterior of their log cabin home. The Deyesus opposed the mechanic’s lien claim and filed a counterclaim against Wizard’s Knoll alleging breach of contract and unfair and deceptive trade practices in violation of the Custom Home Protection Act and the Consumer Protection Act. The case went to trial on the merits of the underlying dispute over the contract. Following a bench trial, the court found in favor of Wizard’s Knoll on all claims, and entered judgment against the Deyesus for $8,643.50.

The Deyesus, who represented themselves at trial and are pro se in this appeal, present the following six questions for review, which we have reordered and rephrased:

I. Did the circuit court err in determining that the Custom Home Protection Act, Md.Code (1974, 2003 Repl.Vol.) sections 10-501 et seq., of the Real Property Article (“RP”), Md.Code (1999 Repl.Vol.) section 4-301 of the Family Law Article (“FL”), and the Consumer Protection Act, Md.Code (2000 Repl.Vol.) sections 13-301 et seq., of the Commercial Law Article (“CL”), did not apply to the facts of the case?
II. Did the circuit court err as a matter of law by failing to find that Wizard’s Knoll breached the contract?
III. Were certain factual findings made by the circuit court clearly erroneous and improperly weighed?
IV. Did the circuit court err in making certain evidentiary rulings?
[128]*128V. Did the circuit court err in failing to consider whether the Deyesus’ counterclaims were ripe for trial?
VI. Did the circuit court err in not dismissing the breach of contract claim against the Deyesus after they could no longer afford to be represented by an attorney? 1

For the reasons set forth below, we shall affirm the judgment of the circuit court.

FACTS AND PROCEEDINGS

In late October 1999, the Deyesus purchased an unassem-bled log cabin home from Jim Barna Log Homes Unlimited, [129]*129LLC (“Jim Barna”). Jim Barna shipped the home from Indiana to the Deyesus’ property in Pylesville, Maryland, and supplied a construction crew to assemble the exterior of the home. The project was expected to take four to six weeks to complete. On December 7, 1999, before the project was completed, one of the gables supporting the home collapsed, and a member of the construction crew was seriously injured. Following the accident, the crew did not return to finish the project.

On January 14, 2000, the Deyesus contracted with D.W. Smith Contracting, Inc. (“Smith”) to complete the assembly of the exterior of the home. Smith abandoned the project in March of 2000, claiming the Deyesus had defaulted on payments.

On March 30, 2000, the Deyesus entered into a second contract, this time with Wizard’s Knoll. Under the contract, Wizard’s Knoll agreed to perform the labor necessary to complete construction of the exterior of the home, and the Deyesus agreed to supply all materials. The total contract price was $20,475.00. By its terms, the contract expired on April 30, 2000; it contained provisions allowing the expiration date to be extended in the event of inclement weather, or upon the agreement of the parties, however.

Due to several problems, including Wizard’s Knoll’s arriving to find the construction site disorganized, the Deyesus’ supplying incorrect or unusable materials, latent construction problems caused by earlier work on the home, and inclement weather, work on the project extended beyond the April 30, 2000 expiration date. The Deyesus did not object to the contract’s being extended in order to complete the project.

By early June 2000, Wizard’s Knoll had completed most of its work on the exterior of the home. The only work remaining was the installation of felt paper, shingles, and flashing on the roof. Wizard’s Knoll hired a roofing subcontractor, but that roofer failed to show up to perform the work and eventually backed out of the job. On June 15, 2000, Wizard’s Knoll notified Mrs. Deyesu that there was a problem with the roofer it had hired, but that it had contacted another roofing compa[130]*130ny, Daniel F. Smith Roofing, Inc. (“Smith Roofing”), that could begin work in two days. Mrs. Deyesu objected to the delay caused by Wizard’s Knoll’s failure to have a roofer in place to immediately begin working on the final phase of the project. Following a heated argument, Wizard’s Knoll agreed that if the Deyesus were not satisfied with Smith Roofing, then they (the Deyesus) could arrange for another roofer to complete the project and Wizard’s Knoll would subtract the cost of the roofing work from the total contract price.

On June 16, 2000, the Deyesus entered into a contract with Buttermilk Home Builders to complete the remaining work on the project. They faxed a copy of that contract to Wizard’s Knoll. Realizing its work on the project was finished, Wizard’s Knoll subtracted $1,950, the amount it had agreed to pay Smith Roofing to complete the roofing work, from the total contract price, and sent a final bill to the Deyesus for $8,643.50, the balance of the contract price due. The Deyesus refused to pay.

On July 17, 2000, Wizard’s Knoll filed in the Circuit Court for Harford County a suit to establish and enforce a mechanic’s lien, to recover the unpaid balance of the contract price. On August 28, 2000, the court issued a show cause order directing the Deyesus to answer the mechanic’s lien claim and appear and present evidence as to why a mechanic’s lien should not attach to their property. On September 18, 2000, the Deyesus filed a “Response to Claim for Mechanic’s Lien,” opposing the mechanic’s lien claim and counterclaiming for breach of contract, and unfair and deceptive trade practices in violation of the Custom Home Protection Act and the Consumer Protection Act.

A show cause hearing was held before the court on December 15, 2000. On December 21, 2000, the court issued an order ruling that there was no probable cause for the entry of an interlocutory mechanic’s lien, and further ruling that the case would be dismissed unless a request that the claim be assigned for trial was made within 30 days. Wizard’s Knoll timely filed its request for trial, and the case proceeded to trial on August 31 and September 4, 2001.

[131]*131At the outset of the trial, the court began by stating that the matter had been scheduled for trial in order for the Deyesus to show cause as to why a final mechanic’s lien should not be entered. The case continued in that posture for approximately fifteen minutes. At that point, however, the trial judge realized that the court previously had denied the interlocutory mechanic’s lien claim, and that the trial, in fact, had been scheduled on the merits of the underlying breach of contract dispute. The court then struck the record, withdrew the evidence that had been introduced to that point, and started the trial over, as a breach of contract action. At the close of the evidence, the court held the matter sub curia.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Duckett v. Riley
52 A.3d 84 (Court of Appeals of Maryland, 2012)
Sweet v. State
882 A.2d 296 (Court of Special Appeals of Maryland, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
846 A.2d 28, 156 Md. App. 124, 2004 Md. App. LEXIS 30, 2004 WL 690929, Counsel Stack Legal Research, https://law.counselstack.com/opinion/deyesu-v-donhauser-mdctspecapp-2004.