Noyes Air Conditioning Contractors, Inc. v. Wilson Towers Ltd. Partnership

712 A.2d 126, 122 Md. App. 283, 1998 Md. App. LEXIS 127
CourtCourt of Special Appeals of Maryland
DecidedJune 29, 1998
Docket1268, Sept. Term, 1997
StatusPublished
Cited by6 cases

This text of 712 A.2d 126 (Noyes Air Conditioning Contractors, Inc. v. Wilson Towers Ltd. Partnership) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Noyes Air Conditioning Contractors, Inc. v. Wilson Towers Ltd. Partnership, 712 A.2d 126, 122 Md. App. 283, 1998 Md. App. LEXIS 127 (Md. Ct. App. 1998).

Opinion

JAMES S. GETTY, Judge

(retired), Specially Assigned.

At the conclusion of a court trial in the Circuit Court for Montgomery County, the trial judge awarded the appellant a judgment in the full amount claimed under two contracts with the appellee for the replacement of air conditioning units in an apartment complex. Appellant’s appeal is based upon the trial judge’s refusal to award attorney’s fees, prejudgment interest, and costs, which appellant claims were expressly provided for *286 in the two contracts. By counterclaim, appellee asserted that the contracts were procured by appellant’s fraud.

Background

From the record, we set forth the chronology of events which, for the most part, are not in dispute. In 1994 and 1995 PEPCO sought to reduce excessive power loads by inducing owners of large facilities to replace older, less efficient air conditioning equipment. The users who participated in the program received a rebate from PEPCO equal to the amount by which the total cost of replacement exceeded the cost of rebuilding the units. Noyes Air Conditioning Contractors, Inc., the appellant herein, was one of the contractors who participated in the replacement program. Wilson Towers Limited Partnership, the appellee, owns and operates a large apartment complex in Oxen Hills.

In the spring of 1994, Noyes advised Wilson of the PEPCO “chiller” retirement program. Thereafter, Noyes and Wilson entered into two substantially identical contracts for the replacement of two chillers in the Wilson complex. Typically, the contractor assisted the property owner in preparing the rebate application and submitting it to PEPCO. Noyes figured the rebate on one of the chillers to be $59,250 and the other to be $55,500.

The rebate applications were not accepted by PEPCO, because the chillers called for in the application would not produce sufficient savings to warrant approval. Noyes revised and resubmitted the application, which included the installation of more expensive, efficient chillers. In August 1994, Noyes submitted two contracts to Wilson reflecting the need for the higher quality chillers. The rebate data, however, remained unchanged from the first application.

Each contract contained the following language on the first page:

PLEASE NOTE:
A. This proposal is contingent on acceptance by PEPCO for the early chiller retirement program and will not be *287 binding until this approval is obtained. Amounts quoted as rebates are estimates and are subject to approval by PEPCO, with final payment for the project being the ultimate responsibility of Wilson Towers Apartments.

On page two of the quotation, the following figures appear as to each contract:

PRICE GOOD FOR 30-DAYS INSTALLATION COST (REBATE CALCULATIONS)

#2

INSTALLED COST OF NEW CHILLERS $82,750.00

Less Resale Value of Refrigerant 50.00

Less Rebuild Cost of Existing Chiller 5,200.00

PEPCO REBATE $77,500.00

OWNERS COST

Installed cost-less PEPCO rebate = OWNERS COST

$82,750.00 — $77,5400.00 = $ 5,250.00

On the second contract, the figures are as follows:

# 3

Cost etc. $82,750.00

Resale-etc. 50.00

Rebuild etc. 8,950.00

PEPCO REBATE $73,750.00

OWNERS COST OWNERS COST

$82,750.00 $ 9,000.00 — $73,750.00 =

On or about August 31, 1994, PEPCO approved the application for rebates but reduced the amount allowable on each contract as follows:

#2 $ 77,500.00 to $51,603.22

#3 $ 73,750.00 to $44,000.00

$151,250.00 3.22 $55,656.78

This information was submitted by PEPCO, by letter on August 31, to Wilson’s property manager. The property manager notified Noyes of the rebate approval from PEPCO, but he failed to mention that PEPCO reduced the amount of the rebate it would allow on each chiller.

The contracts to install the chillers were executed in early 1995, and Noyes proceeded with the installation. Wilson *288 assigned to Noyes the right to reeeive the rebates. In June 1995, Noyes received checks from PEPCO for the amounts of the rebates. According to Noyes, that was the first knowledge the company had of the amounts approved by PEPCO. Noyes applied the amount of the rebates to the contract amount and billed Wilson for the difference after subtracting the “Owner’s Costs” that Wilson paid previously. The litigation ensued when Wilson refused to pay the additional amounts claimed by Noyes.

Appellant argues that the contract expressly provided for the payment of prejudgment interest, attorney’s fees, and court costs. The trial court reasoned that each contract provided a total price for installing a chiller and that Wilson was obligated to pay the difference between that price and the rebate received from PEPCO. The court stated:

So, the total amount is $55,656.78, and I am not awarding any attorney’s fees or interests or costs.

Whether the court, by using the term “interests,” meant to exclude both prejudgment and post-judgment interest is unclear. The court apparently believed that an award of attorney’s fees and, presumably, interest and costs, would amount to a sanction which the court did not impose. That assumption is based upon the court’s comment that “If I gave you attorney’s fees, it would be because I would find that this defendant had no basis to defend this case.” The issue of fees and costs being awards as a contractual right does not appear to have been considered by the court.

The contractual provision relied on by Noyes states:

All work will be completed in a workmanlike manner according to standard practices. It is agreed the contractor will retain title to any equipment and/or material furnished until payment is made in full. If payment is not made as agreed, contractor has the right to remove same and be held harmless for any damages resulting from the removal of equipment and/or material. A one and one-half percentage (Vk%) finance charge per month will be added to Past Due accounts. Customer agrees to pay all reasonable collection *289 fees, attorney’s fees and court costs if such services are required and judgment is made against customer.

Noyes raises six issues which can be condensed into whether a plaintiff seeking a liquidated sum under a contract is entitled to collection fees, attorney’s fees and costs when the contract provides for the payment of such expenses by the party in default. The remaining issues relate to a right to prejudgment interest, and to what extent the court may exercise discretion in awarding or denying collection fees, attorney’s fees, and costs incurred in the collection thereof.

Discussion

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
712 A.2d 126, 122 Md. App. 283, 1998 Md. App. LEXIS 127, Counsel Stack Legal Research, https://law.counselstack.com/opinion/noyes-air-conditioning-contractors-inc-v-wilson-towers-ltd-partnership-mdctspecapp-1998.