Southern Maryland Hospital Center v. Edward M. Crough, Inc.

427 A.2d 1051, 48 Md. App. 401, 1981 Md. App. LEXIS 255
CourtCourt of Special Appeals of Maryland
DecidedApril 10, 1981
Docket820, September Term, 1980
StatusPublished
Cited by21 cases

This text of 427 A.2d 1051 (Southern Maryland Hospital Center v. Edward M. Crough, Inc.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Maryland Hospital Center v. Edward M. Crough, Inc., 427 A.2d 1051, 48 Md. App. 401, 1981 Md. App. LEXIS 255 (Md. Ct. App. 1981).

Opinion

Liss, J.,

delivered the opinion of the Court.

*402 This case arises out of a petition to enforce an arbitration award filed by appellee, Edward M. Crough, Inc., in the Circuit Court for Prince George’s County. The award was rendered in a construction contract dispute between appellants, Southern Maryland Hospital Center, et al., and appellees. Appellants filed an answer to appellees’ petition, as well as a counterclaim seeking to have the arbitration award vacated or set aside pursuant to the provisions of Maryland Code, Uniform Arbitration Act, Section 3-201, et seq., of the Courts and Judicial Proceedings Article (1974, 1980 Repl. Vol.) Both parties filed cross-motions for summary judgment based upon the record of the proceedings before the American Arbitration Association’s panel of three arbitrators and applicable law, and on May 12, 1980 the Circuit Court for Prince George’s County (Melbourne, J.) denied appellants’ motion for summary judgment, upheld the arbitrators’ award, and granted appellees’ motion for summary judgment. Appellants thereafter filed this appeal on the grounds that the court below failed to apply properly the standards of Sections 3-224 (b) (1) and (3) of the Courts and Judicial Proceedings Article and controlling precedent. Appellants raise two questions to be determined by this appeal:

1. Did the trial court err in granting summary judgment confirming the arbitration award based upon issues presented and considered by the arbitration panel and the decision of the panel?

2. Did the court below err in granting summary judgment confirming the arbitration award in the light of the established standards of review of arbitration awards in Maryland?

The Facts

In May 1976, appellee Edward M. Crough, Inc., (hereinafter referred to as "Crough”) and Dr. Francis P. Chiaramonte entered into a "Construction Management Agreement” by which Crough agreed (a) to provide design consultation, including efficient scheduling of the work and limiting the costs of the construction of a 300 bed full service *403 hospital in Prince George’s County, Maryland, and (b) to organize and direct the actual construction of the hospital. The agreement was supplemented by two American Institute of Architect (AIA) Forms (A201 and A201/SC) entitled, respectively, "General Conditions of the Contract for Construction” and "Supplementary Conditions of the Contract for Construction.” Crough’s fee for these services was contractually set at $334,520.

The contract contained a "Guaranteed Maximum Price” of $11.4 million. Crough’s owner and chief executive officer, Edward M. Crough, testified that his counsel reviewed the CM Agreement and Crough both had prior experience with such clauses and understood them.

Dr. Chiaramonte is the only general partner in the limited partnership which owns the appellant hospital and will hereafter be referred to as the "owner.” The owner testified that by entering into a CM Agreement containing the Guaranteed Maximum Price (hereafter, "GMP”), it was his intent to limit the cost of construction to a sum certain of $11.4 million.

Pursuant to its undertaking to perform this job at or below $11.4 million, Crough segregated the work into approximately 25 "line items” or "bid packages,” such as excavation, concrete work, mechanical, electrical, landscaping, etc. Crough estimated the cost of each of these bid packages, which were then let out for competitive bidding. After Crough awarded contracts based upon the bids received, a surplus of over $798,000 was generated from the difference between Crough’s bid package estimates and the actual contracts awarded. Stated another way, the projected cost of building the hospital was approximately $10.6 million at that point — well below the $11.4 million GMP, providing a "cushion” or "surplus” for the parties.

Even before the owner signed the CM Agreement, the parties were aware of a problem that the structural engineer was having with regard to some soil borings. As a result of ground conditions, the engineer advised changing the nature of the foundation, which had originally been *404 designed to use "spread” footings. The CM Agreement was signed by the owner and the parties then discussed possible alternative foundations. Ultimately it was determined that construction could only proceed with a "mat” foundation, i.e., an approximately two foot-thick slab of concrete underlying a layer of sand and the building’s floor slab.

As a result, the original plans and specifications had to be changed to reflect the required mat foundation and the subcontractors, such as the excavator, whose contracts had already been awarded, were notified of the changes. Those subcontractors asked for and received additional funds to perform the changed work.

The foundation redesign affected not only the excavating bid package, but also a number of other items, such as concrete, mechanical and electrical work. Crough advised the owner that the increased costs caused by the mat foundation could easily be absorbed by the nearly $800,000 surplus.

Article 12 of the General Conditions Section of the CM Agreement sets forth the exclusive method for changing the GMP under the contract. It provides, in relevant part (at Sections 12.1.2 and 12.2.1), as follows:

12.1.2 A Change Order is a written order to the Contractor signed by the Owner and the Architect, issued after the execution of the Contract, authorizing a Change in the Work or an adjustment in the Contract Sum or the Contract Time. Alternatively, the Change Order may be signed by the Architect alone, provided he has written authority from the Owner for such procedure and that a copy of such written authority is furnished to the Contractor upon request. A Change Order may also be signed by the Contractor if he agrees to the adjustment in the Contract Sum or the Contract Time. The Contract Sum and the Contract Time may be changed only by Change Order.
12.2.1 If the Contractor wishes to make a claim for an increase in the Contract Sum, he shall give the Architect written notice thereof within twenty days *405 after the occurrence of the event giving rise to such claim. This notice shall be given by the Contractor before proceeding to execute the Work, except in an emergency endangering life or property in which case the Contractor shall proceed in accordance with Subparagraph 10.3.1. No such claim shall be valid unless so made. If the Owner and the Contractor cannot agree on the amount of the adjustment in the Contract Sum, it shall be determined by the Architect. Any change in the Contract Sum resulting from such claim shall be authorized hy Change Order.

It is conceded that Crough neither prepared, nor requested anyone else to prepare, a change order during construction of the project, either for the mat foundation work or for any other work (including "extras,” which are the subject matter of this dispute). Nor did the owner’s architect prepare or request Crough to prepare a change order even though the architect did order and approve many of the changes proposed during the course of the construction of the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gordon v. Lewis
81 A.3d 491 (Court of Special Appeals of Maryland, 2013)
Sharp v. Downey
13 A.3d 1 (Court of Special Appeals of Maryland, 2010)
Letke Security Contractors, Inc. v. United States Surety Co.
991 A.2d 1306 (Court of Special Appeals of Maryland, 2010)
Doyle v. Finance America, LLC
918 A.2d 1266 (Court of Special Appeals of Maryland, 2007)
Mandl v. Bailey
858 A.2d 508 (Court of Special Appeals of Maryland, 2004)
Salvagno v. Frew
857 A.2d 506 (Court of Special Appeals of Maryland, 2004)
Rourke v. Amchem Products, Inc.
835 A.2d 193 (Court of Special Appeals of Maryland, 2003)
MCR of America, Inc. v. Greene
811 A.2d 331 (Court of Special Appeals of Maryland, 2002)
Goldstein v. 91st Street Joint Venture
750 A.2d 602 (Court of Special Appeals of Maryland, 2000)
Hott v. Mazzocco
916 F. Supp. 510 (D. Maryland, 1996)
Contract Construction, Inc. v. Power Technology Center Ltd. Partnership
640 A.2d 251 (Court of Special Appeals of Maryland, 1994)
Snyder v. BERLINER CONSTRUCTION CO.
555 A.2d 523 (Court of Special Appeals of Maryland, 1989)
International Ass'n of Firefighters v. Prince George's County
538 A.2d 329 (Court of Special Appeals of Maryland, 1988)
Barclay Townhouse Associates v. Stephen L. Messersmith, Inc.
508 A.2d 507 (Court of Special Appeals of Maryland, 1986)
James Julian, Inc. v. State Highway Administration
492 A.2d 308 (Court of Special Appeals of Maryland, 1985)
Prince George's County Educators' Ass'n v. Board of Education
486 A.2d 228 (Court of Special Appeals of Maryland, 1985)
PG CTY. EDUCATORS'ASS'N, INC. v. Bd. of Educ.
486 A.2d 228 (Court of Special Appeals of Maryland, 1985)
Wicomico County Education Ass'n v. Board of Education
477 A.2d 279 (Court of Special Appeals of Maryland, 1984)
Gold Coast Mall, Inc. v. Larmar Corp.
468 A.2d 91 (Court of Appeals of Maryland, 1983)
Stauffer Construction Co. v. Board of Education
460 A.2d 609 (Court of Special Appeals of Maryland, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
427 A.2d 1051, 48 Md. App. 401, 1981 Md. App. LEXIS 255, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-maryland-hospital-center-v-edward-m-crough-inc-mdctspecapp-1981.