Contract Construction, Inc. v. Power Technology Center Ltd. Partnership

640 A.2d 251, 100 Md. App. 173, 1994 Md. App. LEXIS 74
CourtCourt of Special Appeals of Maryland
DecidedApril 29, 1994
Docket1313, September Term, 1993
StatusPublished
Cited by8 cases

This text of 640 A.2d 251 (Contract Construction, Inc. v. Power Technology Center Ltd. Partnership) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Contract Construction, Inc. v. Power Technology Center Ltd. Partnership, 640 A.2d 251, 100 Md. App. 173, 1994 Md. App. LEXIS 74 (Md. Ct. App. 1994).

Opinion

*177 WENNER, Judge.

In this appeal, appellant is Contract Construction, Inc. (CCI). Appellees are Power Technology Center Limited Partnership (PTCLP), Cohen Power Corporation (Cohen), and Powertek Realty Corporation (PRC). Cohen and PRC are general partners of PTCLP. For clarity’s sake, we will refer collectively to appellees as “Powertech.”

In November of 1989, Powertech entered into a contract (the Contract) with CCI. CCI was to be general contractor for an office building and parking garage, known as Power Technology Center. Glen Andrew Fahy (Fahy), an employee of a subcontractor, was killed in an accident during construction of Power Technology Center. Fahy’s daughter and estate (the Fahys) filed a complaint against CCI, Powertech, and others alleging negligence and strict liability (the primary suit). The complaint against CCI was dismissed because it was Fahy’s statutory employer and thus immune from suit under the Maryland Workers’ Compensation Act. Maryland Code (1991), § 9-509(a) of the Labor and Employment Article.

Upon CCI’s dismissal, Powertech filed a third-party complaint against CCI claiming indemnification and breach of contract. In response, CCI moved to Compel Arbitration and Stay Powertech’s Third Party Complaint, contending that the Contract required arbitration. This appeal followed the Circuit Court for Prince George’s County’s denial of CCI’s motion. The sole issue presented on appeal is whether the circuit court erred in holding that Powertech’s third party-claims were not covered by the Contract’s arbitration clause.

Concluding that the circuit court erred, we shall reverse its decision and remand this case with instructions to order arbitration. 1

*178 Discussion

I.

The Maryland Uniform Arbitration Act (the Act), Maryland Code (1973, 1989 Repl.Vol.), §§ 3-201 to 3-234 of the Courts and Judicial Proceedings Article (CJP), embodies Maryland’s policy of favoring arbitration. Crown Oil & Wax Co. v. Glen Construction Co., 320 Md. 546, 558, 578 A.2d 1184 (1990); Gold Coast Mall v. Larmar Corp., 298 Md. 96, 103, 468 A.2d 91 (1983); Bel Pre Medical Center, Inc. v. Frederick Contractors, Inc., 21 Md.App. 307, 320, 320 A.2d 558 (1974), modified on other grounds, 274 Md. 307, 334 A.2d 526 (1975). Although the parties’ intention controls, the use of a broad, all encompassing arbitration clause ordinarily leads to the presumption that the parties intended the arbitration of all disputes. Crown Oil, 320 Md. at 558, 578 A.2d 1184. Hence, if the arbitration clause calls for the arbitration of any and all disputes arising out of the contract, all issues are arbitrable unless expressly excluded. Id. at 560, 578 A.2d 1184; Gold Coast, 298 Md. at 104, 468 A.2d 91; Bel Pre, 21 Md.App. at 321, 320 A.2d 558.

In suits to compel or stay arbitration, the circuit court is confined to resolve but one issue: “Is there an agreement to arbitrate the subject matter of a particular dispute.” Crown Oil, 320 Md. at 559, 578 A.2d 1184 (quoting Gold Coast, 298 Md. at 103-04, 468 A.2d 91). There are three categories of disputes involving the scope of an arbitration clause. Id. First, if the language of the arbitration clause is clear and the dispute in question falls clearly within the provision, arbitration must be compelled. Id. at 560, 578 A.2d 1184. Second, if the dispute sought to be arbitrated is clearly outside the scope of the arbitration clause, arbitration must be denied. Id. Third, if the language of the arbitration clause is unclear with respect to whether the dispute is within the scope of the arbitration clause, the issue of arbitrability is for the arbitrators to decide, and arbitration must be compelled. Id. Thus, it is only when the matter in dispute is unequivocally outside the scope of the arbitration clause that a motion to *179 compel arbitration may be denied and litigation be allowed to proceed.

II.

Powertech’s third-party claims against CCI are derived from the Contract. The Contract is composed of the Agreement Between Owner and General Contractor (the Agreement); the General Conditions of the Contract for Construction, AIA Document A201, Fourteenth Edition, 1987 (the General Conditions); and various specifications and drawings (collectively, the Contract Documents). The General Conditions consist of a form document promulgated by the American Institute of Architects (AIA), containing standardized provisions designed to govern the construction process and the relationship between the Owner, Contractor, and Architect. According to Section 1.1 of the Agreement, the General Conditions “are as fully a part of the contract as if attached to this Agreement or repeated herein.” Subparagraph 1.2.3 of the General Conditions provides that “the Contract Documents are complementary, and what is required by one shall be as binding as if required by all.” On the other hand, Section 1.1 provides that if anything in the Contract Documents is inconsistent with the Agreement, the Agreement governs.

Article 10 of the General Conditions is captioned “Protection of Persons and Property.” Subparagraph 10.1.1 provides that “[t]he Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the performance of the Contract.” Subparagraph 10.2.1 requires the Contractor to “take reasonable precautions for safety of, and shall provide reasonable protection to prevent damage, injury or loss” to “employees on the Work and other persons who may be affected thereby.”

Indemnification clauses are contained in both the Agreement and the General Conditions. Section 16.7 of the Agreement provides:

The Owner and the Contractor shall indemnify and hold harmless each other and their agents and employees from *180

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kyere v. Durand
Court of Special Appeals of Maryland, 2026
Gannett Fleming, Inc. v. Corman Const.
243 Md. App. 376 (Court of Special Appeals of Maryland, 2019)
Sharp v. Downey
13 A.3d 1 (Court of Special Appeals of Maryland, 2010)
Essex Corp. v. Susan Katharine Tate Burrowbridge, LLC
940 A.2d 199 (Court of Special Appeals of Maryland, 2008)
Mandl v. Bailey
858 A.2d 508 (Court of Special Appeals of Maryland, 2004)
Nowak v. NAHB RESEARCH CENTER, INC.
848 A.2d 705 (Court of Special Appeals of Maryland, 2004)
NRT Mid-Atlantic, Inc. v. Innovative Properties, Inc.
797 A.2d 824 (Court of Special Appeals of Maryland, 2002)
Society of American Foresters v. Renewable Natural Resources Foundation
689 A.2d 662 (Court of Special Appeals of Maryland, 1997)
Kilsheimer v. Davis
665 A.2d 723 (Court of Special Appeals of Maryland, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
640 A.2d 251, 100 Md. App. 173, 1994 Md. App. LEXIS 74, Counsel Stack Legal Research, https://law.counselstack.com/opinion/contract-construction-inc-v-power-technology-center-ltd-partnership-mdctspecapp-1994.