Wright v. King

292 S.W. 602
Court of Appeals of Texas·Decided January 29, 1927·No. No. 9687.·Published·Cited by 1 cases

Opinions

In a suit in the district court of Dallas county, appellee was awarded a judgment in the sum of $2,872.43 against appellant, and this judgment and the matters involved therein are duly brought before this court for review. *Page 603

Appellant caused to be constructed what is known as the Circle Theater building in the city of Dallas. Appellee was awarded the contract for the construction of the stone work, brick work, cement work, stage joists, first and second floor joists, ceiling joists, and shiplap for roof. The other portions of the building were constructed under separate and independent contracts, and by other parties. The contract contained the stipulation that the work done by him should not exceed the sum of $26,712.50, and that he was to receive from the owner for doing this work a "flat fee" of $2,175, and further that, if the work was completed for a less sum than the guarantee, the contractor was to be paid 50 per cent. of the amount saved under the guaranteed cost.

Two clauses of this contract are essential to the question here involved. They are as follows:

"Art. VI. The contractor shall complete the several portions, and the whole of the work comprehended in this agreement by and at the time or times hereinafter stated, to wit, fifty-five working days.

"Art. VII. Should the contractor be delayed in the prosecution or completion of the work by the act, neglect or default of the owner, of the architect, or of any other contractor employed by the owner upon the work, or by any damage caused by fire, or other casualty for which the contractor is not responsible, or by combined action of workmen in no wise caused by or resulting from default or collusion on the part of the contractor, then the time herein fixed for the completion of the work shall be extended for a period equivalent to the time lost by reason of any or all the causes aforesaid, which extended period shall be determined and fixed by the architect; but no such allowance shall be made unless a claim therefor is presented in writing to the architect within forty-eight hours of the occurrence of such delay."

The amount of the recovery consists of a balance alleged to be due on the contract price and the agreed price for extra work that the contractor was required to do, including an item of approximately $400 alleged to be the contractor's share of the saving under the guaranteed price.

Appellant defended the suit by attempting to offset appellee's claim on allegations to the effect that, before he had entered into the contract with appellee, he had leased the building for a rental of $15,000 per annum, to begin from the day the building was completed and ready for the lessee, and that appellee knew that the building had been so leased, and that by reason of the long delay he had suffered damages in loss of rentals from the lessee in a sum in excess of the amount claimed by appellant. Appellant also controverted a number of items on which appellee sought recovery, and prayed for judgment against appellee in the amount shown by his answer to be due him. The issue on these controverted items was submitted for the determination of the jury, and is not material to the questions involved on this appeal, as only the cross-action for damages by reason of delay in completing the work under appellant's contract is under review.

In answer to appellant's cross-action for damages for delay, appellee filed a supplemental petition, in which it was alleged that the work was completed on November 8, 1923, or after the lapse of 113 days from the beginning of the work, and undertook to excuse himself in not completing the work within 55 working days by alleging that, under the generally accepted meaning of the term "working days," all Sundays, the one legal holiday that intervened, one-half day for each intervening Saturday, and all days in which he could not work, either on account of the stormy condition of the weather, or delay by the act of appellant, or his architect, should be excluded in the computation, and that, by excluding such days, the work was completed within less than 55 working days. Appellee also alleged a waiver by appellant of the provisions of article VII of the contract in reference to the manner in which he could get credit for the therein named delays. These allegations, except as to the time used in completing the work, all went out on appellant's special exceptions.

The case was tried to a jury and submitted on special issues, and those issues that are responsive to the assignments of error and necessary for a decision on this appeal are as follows:

"Question No. 3: Was the plaintiff informed at and before the time the contract sued upon was executed of the lease of the building by the defendant, and of the terms of said lease? Answer: No.

"Question No. 5: Did the failure, if any, of the plaintiff to complete his work within the time stipulated delay the completion of the building for any length of time? Answer: No.

"Question No. 6: What length of time, if any, was the completion of the building delayed by the failure of the plaintiff to complete the work covered by his contract within the time stipulated? Answer: No days."

Appellant has assigned error on the submission of special issue No. 3 because such submission places a greater burden on appellant than the law required, in that, before an affirmative answer could be given to said issue as submitted, the jury must believe not only that appellee knew that the building had been leased under a rental contract, but also knew the terms of such lease contract. Appellant requested an instruction curing the alleged error in the framing of said issue, which was refused. This assignment of error, however, will only become material in the event that appellant's contention in reference to the findings of the jury on special issues 5 and 6 shall be sustained. The assignment of error in reference to each of *Page 604 these issues is that these findings are contrary to the undisputed evidence in the case, and that their submission is not supported by any defensive pleading, such pleading having been stricken out on exceptions. We will consider the assignments in reference to special issues 5 and 6 before considering the assignment in reference to special issue No. 3.

Free access — add to your briefcase to read the full text and ask questions with AI

Wright v. King, 292 S.W. 602 (Tex. Ct. App. 1927).

292 S.W. 602 (Wright v. King) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Wright v. King
17 S.W.2d 98 (Court of Appeals of Texas, 1929)