City of St. Louis ex rel. Carroll-Porter Boiler & Tank Co. v. Parker-Washington Co.

196 S.W. 767, 271 Mo. 229, 1917 Mo. LEXIS 82
CourtSupreme Court of Missouri
DecidedJune 30, 1917
StatusPublished
Cited by17 cases

This text of 196 S.W. 767 (City of St. Louis ex rel. Carroll-Porter Boiler & Tank Co. v. Parker-Washington Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of St. Louis ex rel. Carroll-Porter Boiler & Tank Co. v. Parker-Washington Co., 196 S.W. 767, 271 Mo. 229, 1917 Mo. LEXIS 82 (Mo. 1917).

Opinions

GRAVES, C. J.

In the lower court this case' was first heard by a referee. This referee made a complete finding of facts, and stated .his conclusions of law. Such referee recommended judgment for relator in the sum of $27,513.85, and to his report both parties filed exceptions. Relator’s exceptions were, by the court, sustained in part and overruled in part. Defendants’ exceptions were overruled in toto. Both sides have appealed.

[234]*234The court 'gave judgment for relator in the sum of $38,441.28. The record recites that the reference was by consent, the order therefor reading:

“Tuesday, January 5, 1909.
“Now at this day come the parties, plaintiff and defendants, by their respective attorneys, and consent and agree that this cause may be referred to Francis J. McMaster, Esq., whereupon it is ordered by the court that this cause be, and the same is hereby referred to Francis J. McMaster, Esq., to try all the issues involved therein, and to report his findings and proceedings to the court with all convenient speed.”

The referee has, with great care, outlined the case and the pleadings therein, and this we borrow from him ;

“This suit was instituted by plaintiffs to recover from defendants the unpaid balance of the contract price for certain materials furnished defendants, the Parker ~ Washington Company, under a contract with it, to be used by it in constructing' what is known as a ‘flow line,’ for the city of St. Louis, from the Chain of Rocks to the Baden Pumping Station, under and in pursuance of a contract between said city and said defendants, and in pursuance of Ordinance No. 21807 of said city, approved March 24,1905.
“Plaintiff’s petition shows that this suit was instituted in the name of the city of St. Louis to the use of Carroll-Porter Boiler & Tank Company against the Parker-Washington Company, and the Title Guaranty & Surety Company of Scranton, Pennsylvania, the latter company being the company that executed the bond, required by the city of St. Louis from the Parker-Washington Company, for the faithful performance of its contract with the city.
“The petition further alleges that the Carroll-Porter Company was incorporated under the laws of the State of Pennsylvania, and that the Surety Company was incorporated under the laws of the State of Pennsylvania, and further alleges, by an amendment, that the Surety Company ‘has been duly authorized to do business in this [235]*235State under the statutes relating to Foreign Insurance Companies. ’
“That on May 2,1905, the Parker-Washington Company made a contract with the city of St. Louis, hereinafter called ‘the City,’ under its charter and ordinance, to construct and lay certain piping, complete in place, from Chain of Rocks to Baden Pumping Station. That the work was to be done under the direction and subject to the inspection of the Water Department of the city, the consideration being $478,000, which was to be paid on monthly estimates, less fifteen per cent on the contract price, which latter was to be paid after final acceptance by the city.
“That the Parker-Washington Company made and delivered to the city its bond signed by said Surety Company in the sum of $126,660.62 for the faithful performance of its contract, and would, when the work was completed, pay the proper parties all amounts due for material and labor used.
“And the bond further provided that it could be sued on in the name of the city of St. Louis to the use of any material-man.
“ That after the contract was awarded the Parker-Washington Company, the latter on the 22nd day of May, 1905, made a contract with the Carroll-Porter Company to furnish and deliver the pipe and appurtenances called for by the contract between the Parker-Washington Company and the city, in such quantities as and when called for by the Parker-Washington Company. That this contract referred to the contract between the Parker-Washington Company and the city, and provided that the Carroll-Porter Company should complete the delivery of the entire requirement of the ‘ said pipe and appurtenances. ’ That it' was to be paid by the Parker-Washington Company, monthly, the sum of $14.25 per linear foot of pipe delivered, free on board cars at waterworks in Baden, the payments to be made on the 10th of the month, for pipe delivered the previous month, save fifteen per cent of the amount, which latter was to be retained until fifteen days [236]*236after final acceptance of the pipe in place by the city, when this fifteen per cent was to be paid.
‘ ‘ That plaintiff has fully complied with all the terms and conditions of its contract. That the construction of the pipe and appurtenances was superintended at its factory by inspectors of the Water Department of the city, and that the same had been constructed, delivered and accepted by the Parker-Washington Company (hereinafter designated as defendant) and the city, as in full compliance with the plans and specifications of the principal contract.
‘ ‘ That the work under the principal contract had been completed and accepted by the city and the total amount due defendant was paid in full by the city on the 17th day of April, 1908.
“That although defendant had been paid in full and more than fifteen days had elapsed since such final payment, plaintiff had not been paid the amount due it for material and labor furnished and employed therein. That $11,644.81 was due from defendant to plaintiff prior to the acceptance of the work by the city, which has not been paid, though often demanded, and in addition fifteen per cent, which had been reserved until the acceptance of the work by the city and fifteen days thereafter, amounting to $33,710.79, had not been paid, although the period of fifteen days had expired, making a total of $45,357.50 due plaintiff from defendant, and which was unpaid although often demanded.
“That the Title Guaranty & Trust Company, surety for defendant, had changed its name since executing the bonds to the Title Guaranty & Surety Company of Scranton, Pennsylvania, and was thus impleaded in this cause. That there had been a breach of said bond by defendant and the^ Surety Company for the faithful performance of the principal contract, in that defendant had failed to comply with the terms of the principal contract by refusing to pay plaintiff the amount due it under contract for materials furnished and labor employed in its performance, and then claimed that a cause of action had accrued to the city of St. Louis to the use of the Carroll-Porter [237]*237Boiler & Tank Company, against defendant and the Title Guaranty & Surety Company, and asking judgment for the penalty of the bond, the sum of $126,660.62 and execution for the amount due plaintiff, to-wit, the sum of $45,-357.50, with interest and costs.
“The Parker-Washington Company’s answer admits its incorporation and that of the Surety Company as alleged in the petition,- and further answering alleges:
“1. That the city of St. Louis has no warrant or authority to bring or maintain this action, and that it has no legal capacity to maintain this action in the manner and form that the same is brought.
“2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Merchandising Corporation v. McAlpin
440 S.W.2d 489 (Missouri Court of Appeals, 1969)
Jones v. Hartman Bev. Co., Inc.
203 S.W.2d 166 (Court of Appeals of Tennessee, 1946)
United States v. Henke Const. Co.
157 F.2d 13 (Eighth Circuit, 1946)
United States v. Henke Const. Co.
67 F. Supp. 123 (U.S. Circuit Court for the District of Western Missouri, 1945)
Sandwich Manufacturing Co. v. Bogie
298 S.W. 56 (Supreme Court of Missouri, 1927)
State Ex Rel. Roberts v. Trimble
289 S.W. 796 (Supreme Court of Missouri, 1926)
Yerxa, Andrews & Thurston v. Randazzo MacAroni Manufacturing Co.
288 S.W. 20 (Supreme Court of Missouri, 1926)
Klingenberg Son v. Davis
268 S.W. 99 (Missouri Court of Appeals, 1925)
Bauch v. Weber Flour Mills Co.
238 S.W. 581 (Missouri Court of Appeals, 1922)
National Refrigerator Co. v. Southwest Missouri Light Co.
231 S.W. 930 (Supreme Court of Missouri, 1921)
Universal Construction Co. v. City of St. Louis
223 S.W. 931 (Supreme Court of Missouri, 1920)
Keleher v. Johnson
206 S.W. 261 (Missouri Court of Appeals, 1918)
Roloson v. Riggs
203 S.W. 973 (Supreme Court of Missouri, 1918)
Johnston v. Star Bucket Pump Co.
202 S.W. 1143 (Supreme Court of Missouri, 1918)
Mecartney v. Guardian Trust Co.
202 S.W. 1131 (Supreme Court of Missouri, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
196 S.W. 767, 271 Mo. 229, 1917 Mo. LEXIS 82, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-st-louis-ex-rel-carroll-porter-boiler-tank-co-v-mo-1917.