Universal Construction Co. v. City of St. Louis

223 S.W. 931, 284 Mo. 89, 1920 Mo. LEXIS 54
CourtSupreme Court of Missouri
DecidedJuly 16, 1920
StatusPublished
Cited by6 cases

This text of 223 S.W. 931 (Universal Construction Co. v. City of St. Louis) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Universal Construction Co. v. City of St. Louis, 223 S.W. 931, 284 Mo. 89, 1920 Mo. LEXIS 54 (Mo. 1920).

Opinion

WILLIAMSON, J.

The plaintiff, the Universal Concrete Construction Company, sued the defendant, the City of St. Louis, in the sum of $212,088.96, as the balance claimed by plaintiff to be due it upon a contract for the building of the River Des Peres Foul Water Sewer. Defendant in its answer filed April 30, 1914, admitted liability in the sum of $70,407.73. Sundry payments were made by defendant thereafter and before judgment, and on December 6, 1916, judgment was ren-. dered in favor of plaintiff in the sum of $22,152.40. Both parties have appealed from this judgment. Separate *94 appeals were taken, but they have been consolidated and will be decided as one.

We take from plaintiff’s brief tbe following statement, which, with slight additions, will suffice for a perliminary statement of the facts.

“These are cross-appeals from the judgment of the Circuit Court, of City of St. Louis, in a reference case. . . . By agrément of parties, these cross-appeals are briefed as one case. ...

“Pursuant to certain ordinances passed by the Municipal Assembly of the City of St. Louis, the city entered into a contract dated July 1, 1910, with the Universal Construction Company . . . for the construction of the River des Peres Foul Water Sewer, Second Section, a part of the public sewer system of the city. The contract was a former one containing various provisions and requiring the work to be done in accordance with certain plans and specifications and involved, roughly speaking, something in the neighborhood of half a million dollars. Payments to the contractor were provided for on monthly estimates of the engineer and on the completion of the work the balance due the contractor, except five per cent, was to be paid, the five per cent to be retained for one year as a guaranty of the work. The plaintiff entered upon the execution of the contract and completed the work in the fall of 1913, the sewer being accepted by the city on December 12, 1913. During the progress of the work divers controversies arose between the contractor and the city over estimates, classification of materials and other questions that came up, and when the work was completed the plaintiff presented to the sewer commissioner of the city, under whose supervision the work was done, a list of claims which were considered by him-in connection with the preparation of his final estimate of the work. Some of these claims the commissioner allowed, some he rejected and as to others he made .allowances in lieu thereof. The final estimate was completed by the sewer commissioner on February 12, 1914, *95 showing to he due the contractor at that time the sum of $98,716.59, of which $70,407.73 was then payable, and the balance of $28,308.86, being five per cent of the total amount accrued under the contract, was to be retained by the city for one year. The plaintiff refused to concur in this final estimate or to accept the amount shown thereby to be due and instituted this suit, making the Mercantile Trust Company a party plaintiff, because of an assignment executed by the Universal Construction Company, of the retained percentage held by the city under the contract.

“The petition sets out the facts in regard to the contract and the construction of the sewer, and then in paragraphs numbered 7 to 19, inclusive, specifies the facts and details of the claims and amounts which plaintiff alleges it is entitled to recover over and above what is shown to be due in the sewer commissioner’s final estimate. Judgment is prayed for the total amount of these claims, together with interest and costs. The answer of the city admitted the contract and the execution of the work, denied the facts as to most of the claims, admitted the final estimate, pleaded the decision of the sewer commissioner as being final under the terms of the contract, and set up that the city could not pay plaintiff because a suit had been brought by certain materialmen of a sub-contractor who did work on the sewer seeking payment of their claims out of the moneys due plaintiff from the city for the sewer construction. The reply attacked the decision of the sewer commissioner as being arbitrary, mistaken, wrongful, and based upon erroneous, uncertain and insufficient data and misconstruction of the contract provisions.

‘£ The case was referred to Hon. Edgar R. Rombauer, as referee, who heard the testimony, and in due course filed his report. The transcript of the testimony taken before the referee was voluminous, amounting to 1194 printed pages, and the referee in connection with his report made an abstract of the testimony which was filed *96 and printed in the court below. The referee passed on each of the claims set out in the petition, rejecting some, allowing others, and recommended a judgment in favor of the plaintiff for $146,145.62. This report was filed and shortly, afterwards the case was re-referred to the referee to hear certain evidence bearing upon the question of interest, and payments on account, made by the city while the case was pending before the referee. This the referee did, and filed a supplemental report. Both parties filed exceptions to the report of the referee, and these coming on for hearing the court overruled all the exceptions of plaintiff, sustained divers exceptions of the defendant, and entered a judgment in favor of plaintiffs, which, in effect was the amount shown on the final estimate of the sewer commissioner with interest, plus an amount of $282 on one of the claims for lumber left in the trenches. Thereupon, motions for new trial by both parties were filed and overruled and these appeals perfected to this court.

“On some of the claims set out in the petition and denied by the referee, the evidence was of such character that it might be held, not unreasonably, that plaintiff had failed to sustain the burden of proof. All such claims have been eliminated on this appeal, leaving the following as the ones in controversy here, viz.:

“ 1. Claim in paragraph 8 of the petition on account of classification of material. Allowed by the referee for $7,952.83. Plaintiff’s exception for inadequacy overruled, and defendant’s exceptions sustained and claim disallowed.
“2. Claim in paragraph 9 of the petition as to the amount of brick masonry in the sewer. Disallowed by the refer'ee, and plaintiff’s exception thereto overruled.
“3. Claim in paragraph 10 of the petition for foundation material. Allowed by the referee for $31,542.19. Defendant’s exceptions sustained and the claim disallowed.
*97 “4. Claim in' paragraph 11 of the petition for extra masonry between certain points. Disallowed by the referee, and plaintiff’s exception overruled.
“5. Claim in paragraph 15 of the petition, for pointing and striking masonry joints. Allowed by the referee for $309. Plaintiff’s exception for inadequacy overruled, and defendant’s exceptions sustained, and claim disallowed.
“6. Claim in paragraph 16 of the petition, for rebuilding a caved-in portion of the sewer. Allowed by the referee for $437.15. Defendant’s exceptions sustained and claim disallowed.
“7.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Massman Construction Co. v. Lake Lotawana Ass'n
210 S.W.2d 398 (Missouri Court of Appeals, 1948)
United States ex rel. Tobin Quarries, Inc. v. Glasscock
27 F. Supp. 534 (E.D. Missouri, 1939)
United Construction Co. v. City of St. Louis
69 S.W.2d 639 (Supreme Court of Missouri, 1934)
State Ex Rel. Raleigh Investment Co. v. Allen
242 S.W. 77 (Supreme Court of Missouri, 1922)
Kline Cloak & Suit Co. v. Morris
240 S.W. 96 (Supreme Court of Missouri, 1922)
State Ex Rel. Saline County v. Wilson
232 S.W. 140 (Supreme Court of Missouri, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
223 S.W. 931, 284 Mo. 89, 1920 Mo. LEXIS 54, Counsel Stack Legal Research, https://law.counselstack.com/opinion/universal-construction-co-v-city-of-st-louis-mo-1920.