Cross v. Robinson

281 S.W.2d 22, 1955 Mo. App. LEXIS 157
CourtMissouri Court of Appeals
DecidedJune 13, 1955
Docket22222
StatusPublished
Cited by10 cases

This text of 281 S.W.2d 22 (Cross v. Robinson) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cross v. Robinson, 281 S.W.2d 22, 1955 Mo. App. LEXIS 157 (Mo. Ct. App. 1955).

Opinion

CAVE, Judge.

This suit is based on two written contracts between plaintiff and defendant. Trial before a jury resulted in a verdict for plaintiff on the first count for $1,250, and on the second count for $200, and judgment entered for $1,450. Defendant’s motion for new trial was overruled and appeal was perfected.

The contract pleaded in Count I called for the construction of a small house by plaintiff for the defendant. The contract price was $2,950, one-half of which was paid at the signing of the contract and the remainder to be paid on completion of the construction. The petition alleged that the work had been completed according to contract; that defendant had refused to pay the balance due; and prayed judgment for $1,475. The answer to Count I admitted the execution of the contract, but alleged that plaintiff had failed to fully complete the, contract in certain respects, and prayed to be discharged from further liability. The reply was a general denial.

The amended second count alleged that plaintiff and, defendant executed a written contract wherein plaintiff agreed to construct and install, on same lot as the above house, “a septic tank and drains, deep well pump, -rough in bathroom, build flue * * * inside of house * * * ”, for $950; that $450 was paid at the signing of the contract; that “plaintiff thereafter commenced work under said contract and completed same except for the laying of approximately 21 feet of pipe, having a value, when laid, of approximately $39. Plaintiff did not complete said contract because defendant failed and refused to pay plaintiff the balance due under the contract referred to in Count I of this petition. The reasonable value of plaintiff’s services actually rendered in connection with the installation of said, septic tank, drains, pump, flue and bathroom is $911, less the following credits: (a) a credit of $450 cash hereinbefore re *24 ferred to, and (b) a credit of $188 representing a deep well pump and bathroom items which plaintiff took back when he ceased working under said contract * *

The answer to Count II admits the execution of the alleged contract, and that defendant paid plaintiff $450 at the time of the signing of the same, but denied all other allegations of Count II. She also filed a counterclaim, the material part of which is, “For her counterclaim defendant states that plaintiff performed only a part of the contract referred to in Count II of his petition, delayed operations, used defective labor' and materials, refused to.complete the contract, removed fixtures and equipment, and abandoned the work; that the work and materials furnished, by the plaintiff was valueless and useless to the defendant; and that defendant was thereby damaged in the sum of $450.” the amount she paid at signing of the contract, for which.she prayed-judgment. ...

At the close of all the evidence, the court sustained plaintiff’s motion for a directed verdict on the counterclaim; but overruled defendant’s motion for a directed verdict in her favor on plaintiff’s petition.

It is apparent that the first count is - founded on a written contract, and seeks recovery thereon, and that the amended second count seeks recovery on quantum meruit.

Because of the points raised on appeal, we will not copy or refer to the contracts in detail. They were written with a lead pencil and the provisions are extremely general. There were no drawn plans, specifications or blue prints.

Defendant’s first assignment, as to Count I, is that the court erred in overruling her motion for a directed verdict, because tire plaintiff admitted that he had removed certain bathroom fixtures contracted for, consequently he had not “completely performed” the contract and was not entitled to recover the balance of the contract price. In support of this contention, defendant cites O’Neal v. Mavrakos Candy Co., Mo.App., 255 S.W.2d 138, and same case in Mo., 263 S.W.2d 430; Beckemeier v. Baessler, Mo., 270 S.W.2d 782; Usona Mfg. Co. v. Shubert-Christy Corp., Mo.App., 132 S.W.2d 1101. Those cases hold that a party may not sue on an express contract and recover on quantum meruit. They are not controlling in the present case.

The first count of the petition is based on a building contract, and all the courts are united in holding that a substantial performance of such a contract will support a recovery. There are at least two reasons given by the courts for this rule.- The first is that the work on a building is such that, even, if rejected, the owner of the land must receive the benefit of the contractor’s labor- and materials, which - is not the. case where a chattel is constructed, as the chattel may be returned. Since the owner must receive the fruits of the builder’s labor, it- is deemed equitable to require the former to pay for what he gets. The second reason given for the substantial-performance rule is that it is next to impossible for a builder to comply literally with all the minute specifications of the building contract.

There is a division of opinion as to whether the action should be brought on the contract or on quantum meruit. The majority rule is that the action may be brought on the contract, and the measure of recovery is the sum stipulated in the agreement, less 'any damages sustained by the failure strictly to perform. 9 Am.Jur. “Building Contracts”, Secs. 40, 43, 118; Foeller v. Heintz, 137 Wis. 169, 118 N.W. 543, 24 L.R.A.,N.S., 327 et seq. The rule in this state was clearly announced by this court in Boteler v. Roy, 40 Mo.App. 234, where we said: “The contractor in a building contract need not literally and precisely perform the contract in order to recover thereon. Slight or trivial defects,imperfections or variations will not bar him of his action on the contract, if he has made an honest endeavor to comply and has substantially done so. But a just allowance for such defects, though they be trivial, must be made to the owner.” See, also, Ferd Bauer Engineering & Contract *25 ing Co. v. Arctic Ice & Storage Co., 186 Mo.App. 664, 670, 172 S.W. 417; Knost v. Van Hoose, 182 Mo.App. 40, 167 S.W. 596; Bushnell v. Boyers, 146 Mo.App. 197, 123 S.W. 956.

Defendant recognized this rule, because, by her Instruction 3, she submitted to the jury the issue whether plaintiff had sub-" stantially performed the contract, by directing that if the jury found plaintiff had “omitted any substantial portion thereof, and that said work was not done in a good and workmanlike manner, * * * ”; then the verdict should be for defendant. It is clear that plaintiff’s Instruction I and defendant’s Instruction 3 submitted the issue of plaintiff’s substantial compliance with the contract. That was the proper theory.

The evidence is conflicting as to whether plaintiff completed the contract in a workmanlike manner.. That issue was submitted’ and the jury found against defendant. The only failure of performance claimed by the defendant, in her brief, is that plaintiff removed the bathroom fixtures (bathtub, stool and basin) after she refused to pay the balance due on the contract. The approximate value of these items is $115.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Looney v. Davis
802 S.W.2d 192 (Missouri Court of Appeals, 1991)
Estate of Moore
802 S.W.2d 192 (Missouri Court of Appeals, 1991)
Watkins Investment Co. v. William B. Tanner Co.
684 S.W.2d 929 (Missouri Court of Appeals, 1985)
Bodde v. Burnham
588 S.W.2d 516 (Missouri Court of Appeals, 1979)
Clinton v. Staples
423 S.W.2d 1 (Missouri Court of Appeals, 1967)
Franken v. Carpenter
364 S.W.2d 15 (Missouri Court of Appeals, 1963)
State ex rel. Francesconi v. Aetna Casualty & Surety Co.
350 S.W.2d 418 (Missouri Court of Appeals, 1961)
McAlpine Company v. Graham
320 S.W.2d 951 (Missouri Court of Appeals, 1959)
Adams v. Smith
307 S.W.2d 525 (Missouri Court of Appeals, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
281 S.W.2d 22, 1955 Mo. App. LEXIS 157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cross-v-robinson-moctapp-1955.