State ex rel. Francesconi v. Aetna Casualty & Surety Co.

350 S.W.2d 418, 1961 Mo. App. LEXIS 543
CourtMissouri Court of Appeals
DecidedOctober 2, 1961
DocketNos. 23299, 23300
StatusPublished
Cited by10 cases

This text of 350 S.W.2d 418 (State ex rel. Francesconi v. Aetna Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State ex rel. Francesconi v. Aetna Casualty & Surety Co., 350 S.W.2d 418, 1961 Mo. App. LEXIS 543 (Mo. Ct. App. 1961).

Opinion

MAUGHMER, Commissioner.

This appeal reached the writer by way of reassignment.

Section 107.170 of the statutes requires the contractor for state public works to furnish a bond conditioned upon payment for all materials and labor used thereon. Section 522.300 authorizes a person furnishing such labor or materials to sue on that bond in the name of the state. It was under these provisions that the State of Missouri became a nominal party participant in this case. The purpose of the bond requirement is to provide persons furnishing labor and material the bond security in lieu of mechanics’ liens which are inapplicable to public property. Camdenton Consol. School Dist. No. 6 of Camden County ex rel. W. H. Powell Lumber Co. v. New York Casualty Co., 340 Mo. 1070, 104 S.W.2d 319, 322.

Plaintiffs, Robert and Angelina Fran-cesconi, son and mother, d/b/a The International Terrazzo & Mosaic Flooring Company, are engaged in the business of furnishing and installing terrazzo flooring. A terrazzo floor consists of crushed marble mixed with cement — then ground and trow-elled. Defendant Sharp Brothers Construction Company on December 17, 1957, was awarded a contract by the State of Missouri (Department of Public Health and Welfare) for the construction of three dormitory buildings at the Missouri State School, Higginsville, Missouri, at a total cost of $880,986. Defendant Aetna Casualty & Surety Company is surety on the prime contractor’s (Sharp) performance bond.

The specifications provided for terrazzo flooring in all three buildings totaling 46,000 square feet. The three dormitories to be built were alike as to size and as to the amount of terrazzo floor in each building. Plaintiffs by a written subcontract dated January 15, 1958, agreed to furnish all labor and materials and to do all of the terrazzo work in accordance with the general over-all plans and specifications for a consideration of $49,000. Plaintiffs performed fully as to two of the buildings and were paid $18,429.40 by Sharp. By letter dated February 9, 1959, Sharp terminated plaintiffs’ contract as to the third building and that work was done by another subcontractor, Frank Corazin, on a “cost plus” basis, which amounted to approximately $21,000.

Plaintiffs’ petition is in two counts. Count 1, after identifying the parties, recites the general contract, the subcontract, [420]*420charges a breach by Sharp, then alleges complete performance as to the two dormitories and asserts that by reason thereof defendant Sharp became obligated to plaintiffs in the amount of $32,667.67 for materials and labor expended on the two buildings, acknowledges receipt of $18,429.40 as payment thereon and asks judgment for the difference of $14,237.27. Count 2 sought recovery of $2,446.87 as prospective profit allegedly lost through denial of opportunity tO' perform as to the third building. Defendants denied generally and Sharp counterclaimed for $23,288.60, asserting damages in this amount by reason of plaintiffs’ alleged delay in performance and the cost of completion as to building number three. The verdict and judgment was for plaintiffs under Count 1 in the sum of $14,237.27, the amount sued for. The finding and judgment was for defendants under Count 2 and against defendant Sharp on its counterclaim. Both defendants appealed from the adverse judgment on Count 1 and defendant Sharp- appealed from the judgment on the counterclaim.

The parties hotly contested as to whether plaintiffs or Sharp or other subcontractors occasioned the admitted delay. Sharp contended the plaintiffs did not get the materials, equipment and workmen on the job promptly. Francesconi said the general contractor’s progress was not timely and that he worked as quickly as the buildings were ready for him. We think there was substantial evidence both ways as to responsibility for the delay, but the jury decided this disputed factual issue and since the sufficiency of the evidence is not questioned on appeal, we need not discuss the question extensively. We believe it was for the jury.

Mr. Francesconi testified that his actual cost outlay for labor and materials on the two buildings was $27,772.92, although plaintiffs asked judgment for two-thirds of the over-all contract price for the two buildings which were completed and claimed such a recovery would be reasonable.

Appellants list eight assignments of error on appeal. No. S asserts the verdict on the counterclaim should not stand because the jury on their first return reported a finding as to Counts 1 and 2, but no finding as to the counterclaim. The Court directed the jury to go. back, make a finding on the counterclaim and return it as a part of the verdict. The jury did so. This procedure was quite proper. In Kaimann v. Kaimann Bros., Inc., Mo.App., 182 S.W.2d 458, 462, the court said: “Where the jury returns a verdict containing a patent ambiguity or defect, it is the duty of tire court, at the time the verdict is read, to call the jury’s attention to such ambiguity or defect so that the jury itself may correct its verdict before it is received and judgment entered thereon.” Nor do we consider the verdict to be inconsistent. It was a finding for plaintiffs on the petition and against defendant Sharp on the counterclaim which arose out of the same matter. Any other finding on the counterclaim in the light of the verdict on the petition would, we think, have been inconsistent.

The other seven assignments allege error in giving Instructions 1, 2, 3 and 4, and especially Nos. 1 and 2. Appellants’ basic challenge of these instructions is that both breach of contract and quantum meruit were submitted when quantum meruit was not pleaded, and that these two separate submissions are inconsistent and improper. Instruction No. 4 had to do- with allowance of damages if the verdict was for plaintiffs under Count 2 (for loss of profits on the third building). Instruction No. 3 listed the requisites for a plaintiff verdict under Count 2. Since the verdict and judgment is for defendants under Count 2, it is difficult to rule prejudicial error against defendants from these instructions. With respect to Count 2, the utmost defendants could have received would have been a finding and verdict for defendants. They received exactly that. The chief appellate controversy has to do with the correctness of Instruc[421]*421tions numbered 1 and 2, and we set out the texts thereof:

“Instruction No. 1.
⅜ ⅜ ⅜ ⅜ ⅜ ⅜
“The Court further instructs the jury that it is admitted that on or about December 10, 1957, plaintiffs submitted to Defendant-Sharp the written proposal mentioned in evidence covering certain Terrazzo work in dormitory buildings of the Missouri State School in Higginsville, Missouri; that thereafter, prior to January 15, 1958, the Defendant-Sharp submitted to plaintiffs an instrument styled ‘Subcontract’, mentioned in evidence, covering said Terrazzo work, and that the plaintiffs inserted in said written subcontract the following words:
“ ‘Conditions and articles in proposal of International Terrazzo dated December 10, 1957, to become a part of this contract;’

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Layne, Inc. v. Moody
886 S.W.2d 115 (Missouri Court of Appeals, 1994)
Finch Equipment Corporation v. Robert Frieden
901 F.2d 665 (Eighth Circuit, 1990)
Finch Equipment Corp. v. Frieden
901 F.2d 665 (Eighth Circuit, 1990)
Maurer v. Werner
748 S.W.2d 839 (Missouri Court of Appeals, 1988)
Bodde v. Burnham
588 S.W.2d 516 (Missouri Court of Appeals, 1979)
Wright v. Wright
538 S.W.2d 750 (Missouri Court of Appeals, 1976)
Crystal Tire Co. v. Home Service Oil Co.
525 S.W.2d 317 (Supreme Court of Missouri, 1975)
Boyd v. Margolin
421 S.W.2d 761 (Supreme Court of Missouri, 1967)
Wallace v. Bounds
369 S.W.2d 138 (Supreme Court of Missouri, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
350 S.W.2d 418, 1961 Mo. App. LEXIS 543, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-francesconi-v-aetna-casualty-surety-co-moctapp-1961.