Smith v. Ray M. Dilschneider, Inc.

283 S.W.2d 631, 1955 Mo. LEXIS 777
CourtSupreme Court of Missouri
DecidedNovember 14, 1955
DocketNo. 44604
StatusPublished
Cited by10 cases

This text of 283 S.W.2d 631 (Smith v. Ray M. Dilschneider, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Ray M. Dilschneider, Inc., 283 S.W.2d 631, 1955 Mo. LEXIS 777 (Mo. 1955).

Opinion

DEW, Special Judge.

The plaintiff sued to recover from the defendant the reasonable value of work and labor alleged to have been furnished to the defendant under a subcontract in the construction of an airport at Gideon, Missouri. The defendant filed an answer denying liability and pleading breach of the contract by plaintiff, and filed a counterclaim for damages for such breach. At the close of the plaintiff’s evidence the defendant offered a motion for a directed verdict in its favor, which the court sustained. Thereupon the defendant dismissed its counterclaim. From the judgment rendered on the directed verdict the plaintiff has appealed.

According to the petition the defendant was a general contractor for the construction of an airport and through exchange of correspondence entered into a written subcontract with the plaintiff for the various classifications of excavation named in the correspondence in the various quantities therein specified and at the various prices designated. The contract provided that the unit prices were based on the right of the plaintiff to perform all of the work covered by the classifications and for the prices named. The proposal was accepted by letter from the defendant subject to the plans and specifications of the project. The petition alleged further that the contract provided for certain progress payments to be made to the plaintiff which the defendant failed and refused to make; that plaintiff furnished the labor and material under said contract in the reasonable value of $29,447.-16 on which the defendant has paid $8,581.-88, leaving due the plaintiff the sum of $20,865.28, for which judgment is asked with interest from November 2, 1951, the date of the last work performed.

By its answer defendant, among other matters, admitted that a contract had been made by the defendant, as pleaded, except as to the exact date; denied that the unit prices were applicable only in the event that plaintiff should complete all of the work contemplated by the contract; denied that it had breached any agreement to make progress payments; or that the work was halted at any time due to the breach of the contract by the defendant; or that the plaintiff, upon the cessation of his operations, was entitled to the reasonable value [633]*633of the work and labor specified; or that it had failed to make any payments due the plaintiff, and pleaded that it had made certain payments to plaintiff’s creditors on the project, and had refused to make other payments because they were not due to the plaintiff; that it had been agreed that 10 per cent of the amounts due were to be retained by the defendant until completion of the job and approval thereof by the engineer; that plaintiff, as a condition precedent to the progress payments, had agreed to furnish lien waivers on lienable items, and that on numerous occasions plaintiff was requested to complete the work contemplated by his agreement, but failed to do so.

Further answering, the defendant filed a counterclaim and pleaded therein that under its general contract it had agreed with the owners to be subject to a liquidated damage of $30 a day for delay in the performance of his general contract; that it had entered into the subcontract with the defendant to furnish the labor and materials for a certain portion thereof on a unit price basis, with the final amount due subject to the approval of the consulting engineer upon final check of the total unit completed by the plaintiff; that plaintiff was notified June 19, 1951, to proceed with the work for which he had contracted; that plaintiff continued to work upon the project until on or about November 9, 1951, at which time plaintiff had completed approximately one-half of the job for which he had contracted, and that regardless of the repeated requests of the defendant so to do, plaintiff refused and failed to perform further work on the project, thereby breaching the terms of said contract ; that due to plaintiff’s improper finishing of the gravel in the roadway at the airport, improper drainage resulted and additional grading and additional gravel were required to repair the same; that due to plaintiff’s delay in making proper preparations for the winter season, large quantities of dirt were washed into the apron and taxiways of the airport, requiring additional work for its repair; that further damage was thereby caused to the existing runway; that by reason of the plaintiff’s breaches of the contract, it was necessary for defendant to employ another contractor to complete the job which plaintiff had contracted to perform; that, to conform to the general contract, it was necessary to employ another contractor to repair the damage by reason of such delay and faulty work, for which defendant paid the sum of $2329.80, which was a proper value of the goods and services furnished. The counterclaim further provides that the defendant was required to complete the project free of all liens and claims, and that plaintiff had failed to pay certain bills for labor and material, which bills the defendant was required to pay in the sum of $910.11. The counterclaim further stated that defendant, by reason of plaintiff’s breaches of the contract, was subjected to liquidated damages under its general contract with the city at the rate of $30 a day for the delay. The counterclaim prayed judgment for $3,239.91, less $1,107.49, the total sums withheld by the defendant in accordance with the agreement for progressive payments, with interest on such balance of $2,132.42, from date of filing of the counterclaim.

According to the plaintiff’s evidence he wrote a letter to the defendant on May 5, 1951, proposing to perform eight items of certain quantities of different classifications of excavation at prices named therein, all of which to constitute a subcontract for the construction of an airport at Gideon, Missouri. This proposal was accepted in writing by the defendant on June 7, 1951. By oral agreement two additional items were added thereto. It was further agreed orally that plaintiff would be paid monthly 90 percent of the work completed as disclosed by the engineer’s estimates. It is claimed by the plaintiff that defendant failed to make the progress payments as agreed and because of such breach of the defendant’s contract, plaintiff ceased his performance of the subcontract and brought this action for reasonable value of the work done by him thereunder. According to plaintiff’s computation the work for which he contracted would amount to a total of $21,218.15, based on the contract price. He [634]*634acknowledges credits by advances for materials and otherwise, amounting to $8,581.-88. Added to these credits there was shown an expenditure by defendant of a total of $2,329.80 for completion of the subcontract by others under the limitation of time, after plaintiff stopped work on the project in November, 1951. Plaintiff contends that he is entitled to the difference between his total contract price of $21,218.15 and the total advances and costs of final completion, $10.-911.68, or a balance of $10,306.47. As late as February 19, 1952, plaintiff, in his letter to defendant, acknowledged that the payment of a balance then claimed to be due him on estimates must await information from one Mr. Clinton to satisfy government requirements. He testified, however, that he had finished the part of the work Clinton had been engaged to perform.

As a part of plaintiffs evidence he introduced a paragraph of defendant’s counterclaim, wherein it was alleged that after plaintiff ceased working on the job, defendant employed other contractors to repair the damages from the delay and faulty workmanship at a cost of $2,389.80.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Metro Insurance Agency v. Mannino
856 S.W.2d 81 (Missouri Court of Appeals, 1993)
Wakefield v. Puckett
584 So. 2d 1266 (Mississippi Supreme Court, 1991)
State Ex Rel. Missouri Highways & Transportation Commission v. Legere
706 S.W.2d 560 (Missouri Court of Appeals, 1986)
Crossroads Economic Development Corp. of St. Charles County v. West
704 S.W.2d 300 (Missouri Court of Appeals, 1986)
Springdale Gardens, Inc. v. Countryland Development, Inc.
638 S.W.2d 813 (Missouri Court of Appeals, 1982)
Moss v. Greyhound Lines, Inc.
607 S.W.2d 192 (Missouri Court of Appeals, 1980)
Pride v. Lamberg
366 S.W.2d 441 (Supreme Court of Missouri, 1963)
State ex rel. Francesconi v. Aetna Casualty & Surety Co.
350 S.W.2d 418 (Missouri Court of Appeals, 1961)
King v. Furry
317 S.W.2d 690 (Missouri Court of Appeals, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
283 S.W.2d 631, 1955 Mo. LEXIS 777, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-ray-m-dilschneider-inc-mo-1955.