Ferd Bauer Engineering & Contracting Co. v. Arctic Ice & Storage Co.

172 S.W. 417, 186 Mo. App. 664, 1915 Mo. App. LEXIS 26
CourtMissouri Court of Appeals
DecidedJanuary 5, 1915
StatusPublished
Cited by8 cases

This text of 172 S.W. 417 (Ferd Bauer Engineering & Contracting Co. v. Arctic Ice & Storage Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ferd Bauer Engineering & Contracting Co. v. Arctic Ice & Storage Co., 172 S.W. 417, 186 Mo. App. 664, 1915 Mo. App. LEXIS 26 (Mo. Ct. App. 1915).

Opinion

REYNOLDS, P. J.

— Plaintiff, appellant here, brought its action against defendant to recover $678.71, claimed to be the balance due for the erection of a cooling tower, for which, upon the erection and completion of the same according to the contract and specifications, defendant was to pay plaintiff $1300. Averring that the tower had been erected and completed according to the contract evidenced by a proposal and specifications set out in the petition, and that defendant had paid $621.29 on account of the contract price, plaintiff demanded judgment for the balance together with interest and costs.

After a general denial of all the allegations in the petition, the answer of defendant sets up a counterclaim averring that according to. the contract, the tower was to be erected and the work on it completed so that if would operate by April 5, 1911, and that it had not been completed until some time in November, 1911, and alleging various defects in it, defendant claims that it lias suffered damage by reason of plaintiff’s failure to comply with the terms of the con[667]*667tract, in the sum of $2040', for which it demands judgment. '

Replying to this hy a general denial of the averments of this part of the answer, the reply avers, that after the erection of the cooling tower in controversy, plaintiff was notified by defendant that the tower was defective and did not operate in accordance with the terms of the contract, and that thereupon plaintiff offered to remedy whatever defects there were in the tower but that defendant had refused to allow plaintiff to make these corrections until about the month of November, 1911.

There was a trial before the court and a jury and a verdict in favor of plaintiff on the cause of action set out in its petition in the sum of $678.71, and a verdict in favor of defendant on its counterclaim in the sum of -$1478.71. Judgment, by nunc pro time entry, correcting the original judgment, was entered in favor of defendant for $800, the difference between the amount awarded plaintiff on its cause of action and that awarded defendant on its counterclaim. Interposing a motion for a new trial and excepting to the action of the court in overruling that motion, plaintiff has duly perfected its appeal to this court.

The only errors assigned by counsel for appellant are on the fourth instruction given to the jury by the court of its own motion, to the action of the court in receiving the verdict of the jury and entering it of record, and in overruling defendant’s motion for a new trial.

That fourth instruction is as -follows:

“If the jury find in favor of plaintiff on the cause of action set out in count one of plaintiff’s petition, and also find in favor of defendant on its counterclaim, the verdict may be written in the following form:

“We the jury find in favor of plaintiff on the cause of action set out in count one of plaintiff’s peti[668]*668tion and we assess the amount of plaintiff’s recovery on the counterclaim at the sum of

" (Insert the amount.)
‘We further find in favor of defendant on defendant’s counterclaim and we assess the amount of defendant’s recovery on’the counterclaim .at the sum of
(Insert the amount.)’ ”

It is argued that this instruction is misleading; that it misled the jury into returning an inconsistent verdict and is contradictory. While the only error assigned is to the giving of this fourth instruction and to the action of the court in receiving the verdict in the form given, we have examined the other instructions given at the instance of plaintiff and defendant. In effect, the jury were instructed that if plaintiff had performed the work under the contract within a reasonable time after entering into the contract, their verdict should be for plaintiff for the contract price, less any sum they found had been paid by defendant. The court further instructed the jury that if they found from the evidence that after the tower in controversy had been erected, defendant began the use and occupation of it and thereafter discovered defects therein which could have been remedied, and that defendant neither caused the defects to be remedied nor permitted plaintiff to remedy them, but continued the use and occupation of the tower to its damage, defendant would not be entitled to recover on its counterclaim for any damage sustained after the defects were discovered, which damage could have been avoided by the correction of the defects; and if they found that plaintiff had erected the tower within a reasonable time after being employed to do so, and that within a reasonable time after notice of the failure of the tower to conform to the contract, had offered to make it conform thereto, but that defendant would not permit plaintiff to do so until on or about November 15, 1911, and that on that date plaintiff did repair the [669]*669tower and make it conform substantially to the contract, then their verdict should be for plaintiff for the amount of the contract price less whatever the jury found had been paid thereon. These instructions were given at the instance of plaintiff.

At the instance of defendant the court instructed the jury that the parties had entered into the contract attached to the petition and read in evidence. Summarizing what the contract obligated the plaintiff to do, the court instructed the jury that if they found from the evidence that defendant complied with and discharged the duties and obligations imposed upon it by the contract and that plaintiff failed to comply with the duties and obligations imposed upon it and that defendant was damaged by plaintiff’s failure to comply with the terms of the contract, they should find for defendant on its counterclaim, assessing the damages on its counterclaim as explained in other instructions.

The third instruction particularized the items for which defendant might be allowed on its counterclaim.

With these instructions before it and in the light of the evidence in the case, so far as it is presented, the appellant in its abstract stating that there was evidence introduced by each party tending to support the allegations of their several pleadings, and the respondent, by an additional abstract, setting out what it considered the most material evidence in detail, we cannot say that this verdict is not so inconsistent as to warrant a reversal of this case, and we are bound to say that with this evidence before- us, we are unable to understand the verdict and apply to it that evidence.

The petition was in two counts, one upon the contract and the other in quantum meruit. The latter was abandoned, leaving the action on the contract. Hence a recovery could be had by plaintiff only upon a finding that plaintiff has at least substantially performed the contract. While this does not mean that a recov[670]*670ery is to be denied for failure to comply with the contract with respect to trivial or nonessential'matters, it certainly must mean that it must be found that there was substantial performance. [Boteler v. Roy, 40 Mo. App. 234, l. c. 238.]

On the other hand, defendant’s right of recovery on the counterclaim interposed depends upon a finding that plaintiff failed to perform the contract whereby the damages accrued to defendant which are sought to be recovered by way of counterclaim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Owens v. McBride
694 P.2d 590 (Utah Supreme Court, 1984)
Albers Milling Co. v. Carney
371 S.W.2d 355 (Missouri Court of Appeals, 1963)
Johnson v. Estate of Girvin
370 S.W.2d 163 (Missouri Court of Appeals, 1963)
Skadal v. Brown
351 S.W.2d 684 (Supreme Court of Missouri, 1961)
Cross v. Robinson
281 S.W.2d 22 (Missouri Court of Appeals, 1955)
Commercial Nat. Bank of Kansas City, Kan. v. White
254 S.W.2d 605 (Supreme Court of Missouri, 1953)
Morey v. Feltz
173 S.W. 82 (Missouri Court of Appeals, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
172 S.W. 417, 186 Mo. App. 664, 1915 Mo. App. LEXIS 26, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ferd-bauer-engineering-contracting-co-v-arctic-ice-storage-co-moctapp-1915.