Information Systems v. City of Kansas City

CourtCourt of Appeals for the Eighth Circuit
DecidedJune 18, 1998
Docket97-3043
StatusPublished

This text of Information Systems v. City of Kansas City (Information Systems v. City of Kansas City) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Information Systems v. City of Kansas City, (8th Cir. 1998).

Opinion

United States Court of Appeals FOR THE EIGHTH CIRCUIT ___________

No. 97-3043 ___________

Information Systems and * Networks Corporation, * * Plaintiff-Appellant * * Appeal from the United States v. * District Court for the Western * District of Missouri City of Kansas City, MO, * * Defendant-Appellee * * ___________

Submitted: April 13, 1998

Filed: June 18, 1998 ___________

Before FAGG and HANSEN, Circuit Judges, and STROM,1 Senior District Judge. ___________

STROM, Senior District Judge.

1 The HONORABLE LYLE E. STROM, Senior United States District Judge for the District of Nebraska, sitting by designation. Information Systems and Networks Corporation (ISN) appeals from a judgment entered in the district court2 following a jury verdict finding for the City of Kansas City (the City) and awarding damages on its counterclaim. ISN argues that the district court erred in allowing the jury to assess damages not recognized under Missouri law. ISN also asserts that the district court committed reversible error in admitting a certain damage estimate. For the reasons set forth below, we affirm.

I. BACKGROUND

In May of 1991, ISN entered into a contract with the City to provide and install an automated access control security system at the Kansas City International Airport. The contract required that the security system be completely installed and operational by March 15, 1992. The contract included a liquidated damages clause that provided for varying per day damage amounts if five progression dates (milestones) were not met. The contract also contained a default and termination clause which provided as follows:

All costs and charges incurred by the City, together with the cost of completing the work under the contract, will be deducted from any monies due or which may become due to [ISN]. If such expense exceeds the sum which would have been payable under the contract, then [ISN] and the surety shall be liable and shall pay to the City the amount of such excess.

2 The HONORABLE JOHN T. MAUGHNER, Chief Magistrate Judge, United States District Court for the Western District of Missouri, to whom the case was referred for final disposition by consent of the parties pursuant to 28 U.S.C. § 636(c).

-2- In late 1991, ISN began having difficulties completing the project and requested an extension. On January 3, 1992, the parties agreed to a change order that extended the contract completion date by thirty days and increased the number of milestones and corresponding liquidated damage amounts from five to twelve. For various reasons, ISN failed to meet the contract milestones and complete the project by the April 15, 1992, deadline. On January 21, 1993, the City ordered ISN off the job and ultimately terminated the contract on March 1, 1993. Subsequently, the City decided not to complete the security system called for in the contract, but instead decided it would install a more advanced system.

ISN filed this suit against the City for breach of contract and the City counterclaimed. The case was tried to a jury which found for the City on both ISN's breach of contract claim and on the City's counterclaim and awarded the City $1,686,630 in damages. ISN does not appeal any decision regarding its performance under the contract. It appeals only the type of damages the jury was allowed to award and the admission of a damage estimate.

II. DISCUSSION

A. Cost to Complete Damages

ISN's first argument on appeal is that the district court erred in allowing the City to recover "cost to complete" damages. ISN asserts that recovery of non-incurred completion costs is contrary to Missouri law and to the contract's termination clause. We review the district court's interpretation of Missouri law de novo. Transit Cas. Co. v. Selective Ins. Co. of Southeast, 137 F.3d 540, 543 (8th Cir. 1998).

Under Missouri law, it “is well settled where a contractor has partially performed the work promised, the owner’s damages are the cost of completion.” Stege v. Hoffman, 822 S.W.2d 517, 520 (Mo. App. 1992). “Where the contractor’s

-3- performance is defective, the owner’s damages are either cost of completion according to the contract terms or the difference in the value of the [project] as constructed and the value it should have if constructed according to the specifications.” Id. However, the preferred measure is the cost to complete, which may include not only the cost to complete the project, but also the cost to repair and replace defective construction. County Asphalt Paving Co. Inc. v. The 1861 Group, Ltd., 908 S.W.2d 184 (Mo. App. 1995); Stege, supra. This is true even if the owner does not complete the work. White River Development Co. v. Meco Systems, Inc., 806 S.W.2d 735 (Mo. Ct. App. 1991). Thus, the district court did not err in its determination that Missouri law allows the City to recover cost to complete damages even if the completion costs are not incurred.

ISN also asserts that the district court misinterpreted the contract. It contends that the phrase in the termination clause, "together with the cost of completing the work," makes cost to complete damages a direct subcategory of "all costs incurred by the City." As such, the City must incur the cost of completing the project before they can recover those costs as damages.

Interpretation of the contract's termination clause is a question of law that we review de novo. Lamb Eng’g & Constr. Co. v. Nebraska Pub. Power Dist., 103 F.3d 1422 (8th Cir. 1997). The phrase "together with the cost of completing the work" is unambiguous. "Together with" is a conjunctive phrase, meaning that damages under the contract are not limited to the incurred costs, but are expanded to also include the cost to complete, the form of damages preferred under Missouri law. If the contract was intended to be contrary to law, it would have had to limit the City's damages to the incurred costs only and require the City to finish the project.

With respect to ISN's remaining arguments regarding the award of cost to complete damages, the Court has considered these arguments and finds them to be without merit.

-4- B. Liquidated Damages.

ISN's also argues that the contract's liquidated damages clause constituted a penalty. Under Missouri law liquidated damages clauses are valid and enforceable, while penalty clauses are invalid. Taos Constr. Co. v. Penzel Constr. Co., 750 S.W.2d 522, 525 (Mo. App. 1988). The validity of the liquidated damages clause must be viewed at the time the contract was executed. Southwest Eng’g Co. v. United States, 341 F.2d 998 (8th Cir. 1965), cert. denied, 382 U.S. 819 (1965).

In order that a liquidated damages clause be valid: (1) the amount fixed as damages must be a reasonable forecast for the harm caused by the breach; and (2) the harm that is caused by the breach must be of a kind difficult to accurately estimate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

White River Development Co. v. Meco Systems, Inc.
806 S.W.2d 735 (Missouri Court of Appeals, 1991)
Stege v. Hoffman
822 S.W.2d 517 (Missouri Court of Appeals, 1991)
Grand Bissell Towers, Inc. v. Joan Gagnon Enterprises, Inc.
657 S.W.2d 378 (Missouri Court of Appeals, 1983)
Taos Construction Co. v. Penzel Construction Co.
750 S.W.2d 522 (Missouri Court of Appeals, 1988)
Jennings v. First National Bank of Kansas City
30 S.W.2d 1049 (Missouri Court of Appeals, 1930)
County Asphalt Paving Co. v. 1861 Group, Ltd.
908 S.W.2d 184 (Missouri Court of Appeals, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Information Systems v. City of Kansas City, Counsel Stack Legal Research, https://law.counselstack.com/opinion/information-systems-v-city-of-kansas-city-ca8-1998.