Bethlehem Steel Company v. City of Chicago

234 F. Supp. 726, 1964 U.S. Dist. LEXIS 8030
CourtDistrict Court, N.D. Illinois
DecidedOctober 22, 1964
Docket64 C 181
StatusPublished
Cited by4 cases

This text of 234 F. Supp. 726 (Bethlehem Steel Company v. City of Chicago) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bethlehem Steel Company v. City of Chicago, 234 F. Supp. 726, 1964 U.S. Dist. LEXIS 8030 (N.D. Ill. 1964).

Opinion

ROBSON, District Judge.

Defendant has moved for summary-judgment and plaintiff has filed a countermotion for the same relief. Plaintiff has also moved to strike portions of the-defendant’s answer, as amended. The-suit involves the parties’ rights and liabilities under a written construction contract of December 21, 1961, governing-plaintiff’s furnishing and erecting for $1,734,200 the steel work for a section-of the South Route Superhighway known-as Section S-2424.3-2HF.

The critical provision of the contract here involved is that which provides for-$1,000 “liquidated damages” for each day of delay. The work was originally to-have been completed on or before July-29, 1962, but that date was extended by the City to September 20, 1962. The-work was actually completed November 21, 1962—52 days late — giving rise to-the City’s claim of the right to deduct. $52,000 from the contract price.

The court concludes that there is no-genuine issue of fact, and that the defendant’s motion for summary judgment, should be granted as to the $52,000 item.. The plaintiff’s countermotion for summary judgment should be denied as well.’ as its motion to strike portions of the-defendant’s answer, as amended.

Plaintiff raises the further issue of the-right to five per cent interest on $98,-464.69, the remainder of the balance owed’ it, from February 7, 1963, or, in the alternative, from January 29, 1964, from-, which latter date (the time this suit was-, instituted) it also seeks interest on the: $52,000 item.

*727 Pursuant to the court’s direction, defendant prepared and filed on July 7, 1964, its proposed stipulation of facts, which plaintiff has refused to sign. However, as the court reviews the proposed stipulation it concludes that it is founded on unchallenged documentary proof.

The work which Bethlehem undertook was the erection in Chicago of structural steel for a 22-span steel stringer elevated highway structure, approximately 1,815 feet long, to carry the South Route Superhighway from South Canal Street to the South Branch of the Chicago River. Bethlehem’s work was preceded and followed by the work of other contractors on the same section.

The “Proposal and Acceptance” in the instructions to bidders required the bidders to “ * * * complete * * * within the specified time the work required. * * * ” Time was expressly stated to be the essence of the contract and specified provisions were made for delivery of the steel within 105 days thereafter, or a total of 195 days after commencement of work, which was to be not later than 15 days from notification. The successful bidder was to submit to the Commissioner of Public Works a “Time Schedule” for his work and if “less than the amount * * * specified to be completed” were accomplished “the City may declare this contract forfeited. * * * ” The work had to be completed irrespective of weather conditions.

The all important provision specifying $1,000 a day “liquidated damages” for delay is as follows:

“The work under this contract covers a very important section of the South Route Superhighway, and any delay in the completion of this work will materially delay the completion of and opening of the South Route Superhighway thereby causing great inconvenience to the public, added cost of engineering and supervision, maintenance of detours, and other tangible and intangible losses. Therefore, if any work shall remain uncompleted after the time specified in the Contract Documents for the completion of the work or after any authorized extension of such stipulated time, the Contractor shall pay to the City the sum listed in the following schedule for each and every day that such work remains uncompleted, and such moneys shall be paid as liquidated damages, not a penalty, to partially cover losses and expenses to the City.
“Amount of Liquidated Damages per Day * * * $1,000.00.
“The City shall recover said liquidated damages by deducting the amount thereof out of any moneys due or that may become due the Contractor. * * * ”

Provision was made to cover delay in a contractor’s starting due to preceding contractor’s delay. Unavoidable delays by the contractor were also covered, and extensions therefor accordingly granted.

There was delay in the preceding contractor’s work, and Bethlehem was advised that certain parts of the work would be ready to receive the structural steel by May 10, 1962. Bethlehem noted the day and asked a 32-ealendar day extension of its own completion date, and in a letter of June 2, 1962, requested instead a 35-day extension; still later a 52-day extension and then a 69-day extension. In reply to the last letter, the Chief Engineer of the City wrote Bethlehem on July 3, 1962:

“This will acknowledge receipt of your letter dated June 29, 1962 in which you claim an additional extension of time of seventeen (17) calendar days making a total of sixty-nine (69) days.
“Our records show that due to your own delay in fabrication you were unable to deliver the steel for erection as scheduled. Had the piers in question been completed you still were unable to supply the structural steel for erection. * * *
“We wish to advise you at this time that the full length of time claimed as a delay will not be allowed as most of your delay has been *728 caused within your own organization and not by our sub-structure contractor.” (Italics supplied.)

The contractor whose work depended on Bethlehem’s wrote on July 13, 1962, to the City’s Chief Engineer with reference to Bethlehem's delay:

“We are greatly alarmed by the lack of progress on the erection of structural steel. We have started framing for deck slabs in Spans 2, 3, 4 and 5, but it appears that we will very shortly run out of space to work to keep our deck slab pouring operation continuous. Since Bethlehem Steel Company is not our subcontractor on this steel erection, we are turning to you for assistance in expediting erection to enable us to proceed with docks and complete them. * * * ”

The same contractor wrote again on July 20, 1962, in regard to Bethlehem’s delay:

“ * * * [i]t will be noted that steel erection is pushed back over one month, which indicates their work will be two months behind their contract completion date of July 29, 1962.
“This structural steel delay, over which we have absolutely no control, will delay final completion of the job, unless some measures are taken to expedite the framing and placing of deck concrete. * * *
“The additional costs should be determined within the next ten days.”

Still further complaint was made by the same contractor on July 27, 1962, when it wrote:

“We have not been able to complete our deck framing * * * because of Bethlehem Steel Company’s work that still has to be completed in these piers. Beyond this point none of the structural steel is ready for deck framing. Leaving gaps in our deck framing, which we have had to do at Piers 7 and 8,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
234 F. Supp. 726, 1964 U.S. Dist. LEXIS 8030, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bethlehem-steel-company-v-city-of-chicago-ilnd-1964.