United Order of American Bricklayers and Stone Masons Union No. 21 v. Thorleif Larsen and Son, Incorporated

519 F.2d 331, 89 L.R.R.M. (BNA) 3113, 1975 U.S. App. LEXIS 13428
CourtCourt of Appeals for the Seventh Circuit
DecidedJuly 29, 1975
Docket74-1404
StatusPublished
Cited by37 cases

This text of 519 F.2d 331 (United Order of American Bricklayers and Stone Masons Union No. 21 v. Thorleif Larsen and Son, Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Order of American Bricklayers and Stone Masons Union No. 21 v. Thorleif Larsen and Son, Incorporated, 519 F.2d 331, 89 L.R.R.M. (BNA) 3113, 1975 U.S. App. LEXIS 13428 (7th Cir. 1975).

Opinion

PELL, Circuit Judge.

The sole issue in this appeal is whether a “liquidated damages” provision in a contract between the parties is enforceable as denominated or is unenforceable as a penalty. Plaintiff brought suit in the district court against defendant, an employer, pursuant to Section 301 of the Labor Management Relations Act of 1947, as amended, 29 U.S.C. § 185 et seq., to recover money due jointly administered fringe benefit funds plus “liquidated' damages” which had accrued under the provisions of the contract as a result of payments being made after the due dates. The only contested issue in the case was the validity of the liquidated damages provision. The district court found the provision unenforceable as a penalty and granted summary judgment for the defendant. This appeal resulted.

The portion of the contract in issue provides:

“Any Employer failing to make prompt and timely payment of the contribution to the Masonry Institute or to the Pension Fund or to the Apprenticeship Program in accordance with this Agreement, shall in addition to the aforesaid hourly contributions pay an additional amount of ten (10%) percent of the amount due in liquidated damages for failure to pay in accordance with this Agreement.
“If delinquency continues uncured for forty-eight (48) hours after written notice of such delinquency is mailed or delivered to the delinquent employer, the Employer shall be liable for claims for the extent of benefits to which the employee would have been entitled if the Employer had made the required contributions, and for all contributions and liquidated damages due thereunder, plus all reasonable legal fees incurred by the Masonry Institute, the Trustees of the Apprenticeship Program or the Pension Fund in enforcing the payment thereof.”

Both parties agree that § 339 of the Second Restatement of Contracts sets forth the applicable standard for determining whether the agreement should be enforced:

“An Agreement, made in advance of breach, fixing the damages therefor, is not enforceable as a contract and does not affect the damages recoverable for the breach, unless
(a) the amount so fixed is a reasonable forecast of just compensation for the harm that is caused by the breach, and
(b) the harm that is caused by the breach is one that is incapable or very difficult of accurate estimation.” 1

Plaintiff argues that the harm caused is difficult to estimate and that the provision was negotiated at arm’s length between parties of equal bargaining strength. Defendant argues that use of the term “liquidated damages” in the contract does not preclude a court from determining that the provision actually provides a penalty and that the amount provided is unreasonable because it fails to take into account the length of the delay.

Courts often state that the intention of the parties is the key to deciding whether a provision is to be considered a penalty or liquidated damages. E. g. Kothe v. Taylor Trust, 280 U.S. 224, 226, 50 S.Ct. 142, 74 L.Ed. 382 (1930); Wise v. United States, 249 U.S. *333 361, 365, 39 S.Ct. 303, 63 L.Ed. 647 (1919); Parker-Washington Co. v. Chicago, 267 Ill. 136, 139, 107 N.E. 872 (1915). Nevertheless, use of the term “liquidated damages” by the parties is not conclusive, United States v. Bethlehem Steel Co., 205 U.S. 105, 120, 27 S.Ct. 450, 51 L.Ed. 731 (1907); Giesecke v. Cullerton, 280 Ill. 510, 513, 117 N.E. 777 (1917); Parker-Washington Co. v. Chicago, supra; A. Corbin, Corbin on Contracts § 1058 at 337 (1964); but the terms chosen by the parties should be given some evidentiary value. 5 S. Williston, Williston on Contracts § 778 at 690 — 91 (1961). Thus, in relation to this issue determination of the parties intentions must be an inquiry of broader scope than interpretation of their language. In issue is whether they have made a good faith attempt to name a sum as an equivalent of the damages that they anticipate from breach. Williston, supra, § 778 at 693. In contrast, a penalty is a sum which is disproportionate to anticipated damages “which is agreed upon in order to enforce performance of the main purpose of the contract by the compulsion of this very disproportion.” Williston, supra, § 776 at 668.

A critical question thus becomes whether the damages stipulated are so unreasonable that we should refuse on the grounds of the public policy against enforcing penalties to enforce the agreement of the parties to pay the sum and ignore their agreed-upon statement that the sum is to be considered as liquidated damages. In determining whether the amount stated is unreasonable, we must view it in relation to damages which could be reasonably anticipated at the time of making the contract. Bethlehem Steel Co. v. Chicago, 234 F.Supp. 726, 729 (N.D.Ill.1964), aff’d 350 F.2d 649 (7th Cir. 1965) (opinion of the district court adopted as the opinion of the 7th Cir.); Parker-Washington, supra 267 Ill. at 141, 107 N.E. 872. The law is clear that the unreasonable nature of the sum provided is sufficient grounds for finding that it was intended to be a penalty. Kothe, supra 280 U.S. at 226, 50 S.Ct. 142; Mel-lor v. Budget Advisors Inc., 415 F.2d 1218 (7th Cir. 1969).

In this case the damages that could be anticipated included: the loss of the benefits of the use of the funds, increased administrative costs resulting from collection efforts, the difficulties the trustees would have in forecasting receipts, and possible loss of benefits to employees. Although the contract made the employer liable for any benefits lost by employees, the value of this liability was contingent on his ability to pay. The extent of these damages vary with the size of the contribution not made and the length of the delay. The damages specified are proportionate to the size of the contribution because they are a percentage of it. They are not proportionate to the length of the delay; regardless of the length of the delay, the damages are the same percentage of the total sum due. This is in contrast to an agreement made subsequent to the one in issue in which liquidated damages were agreed to be one half percent of the unpaid balance pier month.

The liquidated damages provision in issue had been in the various contracts between plaintiff and the Employers’ Association from 1957 to 1973. The parties differ somewhat as to the relevance of the fact that when the defendant became an individual signatory to the agreement, the change indicated in the text, supra, was made effective.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Jackson v. Mv Realty Pbc, LLC
2026 NCBC 2 (North Carolina Business Court, 2026)
Mau v. L.A. Fitness International, LLC
749 F. Supp. 2d 845 (N.D. Illinois, 2010)
Automotive Finance Corp. v. Ridge Chrysler Plymouth L.L.C.
219 F. Supp. 2d 945 (N.D. Illinois, 2002)
United States v. Rueth Development Co.
189 F. Supp. 2d 874 (N.D. Indiana, 2002)
Checkers Eight Limited Partnership v. La-Van Hawkins
241 F.3d 558 (Seventh Circuit, 2001)
Hidden Grove Condominium Ass'n v. Crooks
Appellate Court of Illinois, 2001
Penske Truck Leasing Co., L.P. v. Chemetco, Inc.
Appellate Court of Illinois, 2000
Penske Truck Leasing Co. v. Chemetco, Inc.
725 N.E.2d 13 (Appellate Court of Illinois, 2000)
United Cable Television of Baltimore Ltd. Partnership v. Burch
732 A.2d 887 (Court of Appeals of Maryland, 1999)
Garcia v. Canan
851 F. Supp. 327 (N.D. Illinois, 1994)
Parkhurst v. Armstrong Steel Erectors, Inc.
901 F.2d 796 (Ninth Circuit, 1990)
Bruce Parkhurst v. Armstrong Steel Erectors, Inc.
901 F.2d 796 (Ninth Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
519 F.2d 331, 89 L.R.R.M. (BNA) 3113, 1975 U.S. App. LEXIS 13428, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-order-of-american-bricklayers-and-stone-masons-union-no-21-v-ca7-1975.