McLaughlin Electric Supply v. American Empire Insurance Co.

269 N.W.2d 766, 1978 S.D. LEXIS 200
CourtSouth Dakota Supreme Court
DecidedAugust 24, 1978
Docket12016, 12030, 12031 and 12042
StatusPublished
Cited by26 cases

This text of 269 N.W.2d 766 (McLaughlin Electric Supply v. American Empire Insurance Co.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McLaughlin Electric Supply v. American Empire Insurance Co., 269 N.W.2d 766, 1978 S.D. LEXIS 200 (S.D. 1978).

Opinion

DUNN, Chief Justice.

This case arises as a result of an alleged failure of Black Hawk Industrial Services, Inc. (Black Hawk), to adequately construct a trailer campground for the Bachmeiers. The issues raised involve mechanics’ liens and the liability of American Empire Insurance Company (American), the bonding company. We affirm in part and reverse and remand in part.

The Bachmeiers decided to construct a campground in the Black Hills in 1973. They hired one contractor who could not secure a performance bond, so in May of 1973, they hired Amos Lane, sole owner and stockholder of Black Hawk, to do the job. Mr. Lane and the Bachmeiers agreed on a price of $62,000. An “agreement in principal” was drawn up on June 2, 1973.

Mr. Lane contacted Tony Meier of Kluthe and Lane Insurance Agency about getting a performance bond and left a copy of the June 2nd proposal. Mr. Meier knew it was a rough draft and assumed the attorneys for the various parties would fill in the details as instructed by their clients. The June 2nd document contained no completion date or liquidated damages clause. The process of drafting the final contract was delayed by errors in the drafts and circumstances aLthe work place. A final contract was signed on July 23, 1973, but backdated with the permission of Mr. Meier to June 29, 1973, the date the bond was issued by *768 American. Mr. Meier did not request a copy of the final contract before agreeing to backdate the document.

Mr. Lane originally told the Bachmeiers that the job would be done by July 4, 1973, for the tourist season. When it became apparent that it would be much later than that, discussion of a liquidated damages' clause took place. Prior to July 23, 1973, Mr. Lane was informed by state and local health officials that all the trailer beds had to at least have a water hookup. This required a change in the water tank size and more dirt work to place the tank. Both parties agreed to raise the price to $66,000 to cover the new plans and the $66,000 figure was the one that appeared on the final contract and the bond. The Bachmei-ers made it clear that they could spend no more than that amount.

A final contract contained an August 6, 1973 completion date, a $300 per day liquidated damages clause, and a change in the number of trailer beds as set out later in this opinion. The work was not completed on time, and the work that was done was of a very poor quality.

McLaughlin Electric Supply, one of the holders of a mechanic’s lien, sued the Ba-chmeiers, Black Hawk, the bank holding the mortgage, and American. The Bachmeiers cross claimed against Black Hawk and American. The following mechanic’s lien claimants were joined in the action: Birdsall Sand & Gravel, Black Hills Masonry, Hills Red-E-Mix, Knecht Industries, Pete Lien & Sons, Inc. (Lien), Northwest Pipe Fittings and Wesley Scholl, d/b/a Scholl Construction Company (Scholl). Trial was had before the Circuit Court, Seventh Judicial Circuit, commencing on October 1, 1974, without a jury, and judgment was entered July 1, 1976.

The trial court concluded that Black Hawk had breached its contract and awarded the Bachmeiers $56,882.91 plus $18,000 in liquidated damages for delay in completion. The $18,000 was not allowed to be collected against the bond, and the court also set off $12,993.80 for “extra dirt work” that the contractor had done pursuant to a “separate, oral agreement” according to the court. A further $20,849.66, which was the amount the Bachmeiers still owed Black Hawk on the contract, was set off from the Bachmeiers’ award. Lien and Scholl, as well as several other lien claimants, were found to have filed defective mechanic’s liens but were allowed to recover against the bond money as unpaid materialmen on the theory of unjust enrichment. They were not allowed attorney fees, however. American appealed the decision, the Ba-chmeiers cross-appealed, and, finally, Lien and Scholl cross-appealed from that part of the judgment which was adverse to them.

The trial court placed a $66,000 maximum on the total recovery against American, so the issues raised involve a dispute among all the appellants as to how to divide the money. Further factual details are given in the discussion of the various issues raised on appeal.

We must first determine whether the changes between the contract signed on July 23, 1973, and backdated to June 29, 1973, and the “agreement in principal” were so material that American should be relieved of liability on its bond. This court has stated that:

“ ‘ * * * The rule seems to be thoroughly well established that where alterations and changes are made pursuant to such agreement they are binding upon the surety unless they are so extensive and material as to amount to a departure from the original contract rather than a permissible modification of its details.’ ” Independent School District No. 41 v. Sloan, 1929, 54 S.D. 646, 649, 224 N.W. 182, 183.

A paid surety must show prejudice or damage as a result of the change, and if the prejudicial aspect of the change can be easily measured and excised, the surety remains liable on the original contract. Restatement of the Law, Security, § 128(b); Zuni Construction Co. v. Great American Ins. Co., 1970, 86 Nev. 364, 468 P.2d 980; Pacific Cty. v. Sherwood Pacific, Inc., 1977, 17 Wash.App. 790, 567 P.2d 642; United Bond. Ins. Co. v. Atlantic Roofing & Sh. Met. Co., *769 1969, Fla.App., 221 So.2d 461; Ferguson Contract. Co. v. Charles E. Story Const. Co., 1967, Ky., 417 S.W.2d 228; Development Corp. of America v. United Bonding Ins. Co., 1969, 5 Cir., 413 F.2d 823.

The major changes between the two agreements were the liquidated damages clause, a completion date, and a change in the number of camper pads from 115, including 75 with no utility hookups, to 108, including 68 pads with water-only hookups. The change in the number of pads did not increase the risk in any way and is the kind of change expected to result as a project develops, so the bonding company should not escape liability on that basis. The completion date and the liquidated damages clause definitely increased the risk and for that reason were excised by the trial court. The Bachmeiers contend that American’s agent knew of the damages clause before agreeing to the contract, but the evidence on this point was contradictory. The trial court refused a proposed finding to that effect and concluded that American was not liable for the liquidated damages. Since there was evidence in the record to support this decision by the trial court, we will not disturb that finding by the trial court. SDCL 15-6-52(a); City of Rapid City v. Hoogterp, 1970, 85 S.D. 176,

Related

DAKOTA CRAFT, INC. v. Severson
2009 SD 56 (South Dakota Supreme Court, 2009)
Carstensen Contracting, Inc. v. Mid-Dakota Rural Water System, Inc.
2002 SD 136 (South Dakota Supreme Court, 2002)
Muhlenkort v. Union County Land Trust
530 N.W.2d 658 (South Dakota Supreme Court, 1995)
Cordell v. Codington County
526 N.W.2d 115 (South Dakota Supreme Court, 1994)
FGS Constructors, Inc. v. Carlow
823 F. Supp. 1508 (D. South Dakota, 1993)
Mash v. Cutler
488 N.W.2d 642 (South Dakota Supreme Court, 1992)
R & L Supply, Ltd. v. Evangelical Lutheran Good Samaritan Society
462 N.W.2d 515 (South Dakota Supreme Court, 1990)
Gebrueder Heidemann, KG v. AMR Corp.
746 P.2d 579 (Idaho Court of Appeals, 1987)
First Bank of South Dakota v. Haberer Dairy & Farm Equipment, Inc.
412 N.W.2d 866 (South Dakota Supreme Court, 1987)
Pankratz v. Miller
401 N.W.2d 543 (South Dakota Supreme Court, 1987)
Gross v. Connecticut Mutual Life Insurance Co.
361 N.W.2d 259 (South Dakota Supreme Court, 1985)
Matter of DH
354 N.W.2d 185 (South Dakota Supreme Court, 1984)
In re the Termination of Parental Rights over D.H.
354 N.W.2d 185 (South Dakota Supreme Court, 1984)
Larson Concrete Co. v. Stroschein
353 N.W.2d 354 (South Dakota Supreme Court, 1984)
Wefel v. Harold J. Westin & Associates, Inc.
329 N.W.2d 624 (South Dakota Supreme Court, 1983)
Lanning Construction, Inc. v. Rozell
320 N.W.2d 522 (South Dakota Supreme Court, 1982)
Sherman v. Meyer
312 N.W.2d 373 (South Dakota Supreme Court, 1981)
Gee v. Eberle
420 A.2d 1050 (Superior Court of Pennsylvania, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
269 N.W.2d 766, 1978 S.D. LEXIS 200, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mclaughlin-electric-supply-v-american-empire-insurance-co-sd-1978.