Lytle v. Morgan

270 N.W.2d 359, 1978 S.D. LEXIS 216
South Dakota Supreme Court·Decided September 21, 1978·No. 12060·Published·Cited by 94 cases

Opinion

PER CURIAM.

This action was brought by plaintiff Ly-tle for materials furnished and labor supplied to defendant Morgan. A jury verdict was rendered for defendant and the lower court entered judgment dismissing plaintiff’s complaint and discharging plaintiff’s mechanic’s lien. We affirm.

Since December of 1974, defendant has been the owner and operator of a public campground which is located approximately four miles west of Custer, South Dakota. Plaintiff is a plumbing contractor who had begun construction of additional campground facilities at defendant’s campground prior to December of 1974. In the spring of 1975, the parties met with each other and discussed completion of the project. An informal, unwritten agreement was reached whereby the plaintiff was to complete the installation of additional facilities.

Plaintiff commenced work on the project on . approximately June 24, 1975, and worked sporadically through August of 1975. On August 31, 1975, plaintiff billed defendant for work done and materials furnished in the amount of $5,233.00. Defendant subsequently paid $3,300.00 and informed plaintiff that he was not going to pay the balance of the bill until the project was completed satisfactorily.

Plaintiff then filed a mechanic’s lien in the general amount of the balance of the bill remaining unpaid. Defendant made a formal demand that suit be filed 1 and plaintiff brought this action for foreclosure on the lien and sale of defendant’s property or, in the alternative, for judgment on the amount of the bill unpaid. Defendant answered and counterclaimed for damages for breach of contract. The actions came to trial before a jury on June 29, 1976. The trial court directed a verdict against defendant on the counterclaim and denied plaintiff’s motion for directed verdict on the complaint. The jury verdict was rendered for defendant on the issues remaining. The trial court also denied plaintiff’s motion for judgment notwithstanding the verdict.

On appeal, plaintiff raises the following issues:

1. the trial court erred in not granting plaintiff’s motion for directed verdict on the complaint or motion for judgment n. o. v. because plaintiff was entitled to foreclosure on the mechanic’s lien as a matter of law;
2. the trial court erred in failing to advise the jury that plaintiff’s motion for directed verdict on defendant’s counterclaim was granted; and
3. the trial court erred in failing to use plaintiff’s mechanic’s lien instructions.

With regard to the first issue, it is well established that trial court rulings and decisions are presumed to be correct and this court will not seek reasons to reverse. Shaffer v. Honeywell, Inc., 1976, S.D., 249 N.W.2d 251; Custer County Bd. of Ed. v. State Com’n on E. & S. Ed., 1972, 86 S.D. *361 215, 193 N.W.2d 586. In our review of the trial court’s denial of the plaintiff’s motions for directed verdict and judgment n. o. v., we must keep in mind that the trial court must consider the evidence in the light most favorable to the non-moving party and give the non-moving party the benefit of every reasonable inference in his favor. If there is substantial evidence that would allow reasonable minds to reach differing conclusions, it is proper to deny the motion for directed verdict and to submit the case to the jury and the verdict should not be disturbed on a motion for judgment notwithstanding the verdict. Heiser v. Rodway, 1976, S.D., 247 N.W.2d 65; Beck v. Wessel, 1976, S.D., 237 N.W.2d 905; Ehlers v. Chrysler Motor Corp., 1975, 88 S.D. 612, 226 N.W.2d 157; Ricketts v. Tusa, 1974, 87 S.D. 702, 214 N.W.2d 77; and Corey v. Kocer, 1972, 86 S.D. 221, 193 N.W.2d 589.

We have examined the record in the light most favorable to defendant and we find that there was substantial evidence upon which reasonable minds could differ. We are convinced that the trial court was correct in denying both of plaintiff’s motions. The record reveals that the parties had conversations regarding the necessity for completion of the project at the earliest date possible. There is evidence that plaintiff stated he could not be done with the project by July 4th but that “he would do the best he could” and that “he should be able to finish by the middle of July”. At the time plaintiff presented the bill to defendant, the project was not completed in that the shower house and laundry building were totally inoperable, pipes were sticking out of the ground, ditches were open and there were no water connections in the tent area. The water pipes leaked when the water system was pressurized and sewer pipe under the road was buried only one foot deep and was plugged. A state plumbing inspector found that the plumbing installation was inadequate, incomplete, and improper based upon the state plumbing code. There is testimony that some of the materials that plaintiff billed defendant for were in fact supplied by defendant himself.

Free access — add to your briefcase to read the full text and ask questions with AI

Lytle v. Morgan, 270 N.W.2d 359, 1978 S.D. LEXIS 216 (S.D. 1978).

270 N.W.2d 359 (Lytle v. Morgan) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Suvada v. Muller
983 N.W.2d 548 (South Dakota Supreme Court, 2022)
J. Clancy, Inc. v. Khan Comfort, LLC
955 N.W.2d 382 (South Dakota Supreme Court, 2021)
Magner v. Brinkman
2016 SD 50 (South Dakota Supreme Court, 2016)
Wald, Inc. v. Stanley
2005 SD 112 (South Dakota Supreme Court, 2005)
Veeder v. Kennedy
1999 SD 23 (South Dakota Supreme Court, 1999)
Kuper v. Lincoln-Union Electric Co.
1996 SD 145 (South Dakota Supreme Court, 1996)
High Plains Genetics Research, Inc. v. J K Mill-Iron Ranch
535 N.W.2d 839 (South Dakota Supreme Court, 1995)
Weiszhaar Farms, Inc. v. Tobin
522 N.W.2d 484 (South Dakota Supreme Court, 1994)
Maybee v. Jacobs Motor Co., Inc.
519 N.W.2d 341 (South Dakota Supreme Court, 1994)
Treib v. Kern
513 N.W.2d 908 (South Dakota Supreme Court, 1994)
Nelson v. Nelson Cattle Co.
513 N.W.2d 900 (South Dakota Supreme Court, 1994)
Haberer v. Rice
511 N.W.2d 279 (South Dakota Supreme Court, 1994)
Lien v. McGladrey & Pullen
509 N.W.2d 421 (South Dakota Supreme Court, 1993)
Baltodano v. North Central Health Services, Inc.
508 N.W.2d 892 (South Dakota Supreme Court, 1993)
Shippen v. Parrott
506 N.W.2d 82 (South Dakota Supreme Court, 1993)
Craig v. Swann (In Re Swann)
141 B.R. 678 (D. South Dakota, 1992)
Chambers v. Dakotah Charter, Inc.
488 N.W.2d 63 (South Dakota Supreme Court, 1992)
Time Out, Inc. v. Karras
469 N.W.2d 380 (South Dakota Supreme Court, 1991)
Schelske v. South Dakota Poultry Cooperative, Inc.
465 N.W.2d 187 (South Dakota Supreme Court, 1991)