Suvada v. Muller

983 N.W.2d 548, 2022 S.D. 75
CourtSouth Dakota Supreme Court
DecidedDecember 14, 2022
Docket29684
StatusPublished
Cited by3 cases

This text of 983 N.W.2d 548 (Suvada v. Muller) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Suvada v. Muller, 983 N.W.2d 548, 2022 S.D. 75 (S.D. 2022).

Opinion

#29684-a-SPM 2022 S.D. 75

IN THE SUPREME COURT OF THE STATE OF SOUTH DAKOTA

****

ED SUVADA, Plaintiff and Appellant,

v.

GEORGE JOHN MULLER, II and CHRISTINE MULLER, Defendants and Appellees.

APPEAL FROM THE CIRCUIT COURT OF THE FOURTH JUDICIAL CIRCUIT LAWRENCE COUNTY, SOUTH DAKOTA

THE HONORABLE ERIC J. STRAWN Judge

DAVE L. CLAGGETT of Claggett & Dill, Prof. LLC Spearfish, South Dakota Attorneys for plaintiff and appellant.

ROBERT J. GALBRAITH of Nooney & Solay, LLP Rapid City, South Dakota Attorneys for defendants and appellees.

CONSIDERED ON BRIEFS FEBRUARY 14, 2022 OPINION FILED 12/14/22 #29684

MYREN, Justice

[¶1.] Ed Suvada commenced this action to foreclose a materialmen’s lien to

recover for material and labor he expended in renovating a cabin for George (Jack)

and Christine Muller. Suvada also sought damages for breach of contract. The

Mullers counterclaimed for breach of contract and fraud. The jury found in favor of

Suvada on his materialmen’s lien, awarding him damages. The jury also found in

favor of the Mullers on both of their claims but only awarded damages on the

breach of contract claim. Suvada appeals, raising multiple issues. We affirm.

Facts and Procedural History

[¶2.] Suvada is a carpenter with nearly 50 years of experience. In August

2016, Suvada signed a written contract with the Mullers for an addition and

remodeling project on their cabin near Deadwood. The contract covered labor and

materials and included a clause stating that the work 1 would be “substantially

completed on or before the 31st day of May, 2017.” The Mullers agreed to pay

Suvada $131,600.00 plus tax for the material and labor performed, subject to any

authorized change orders. The contract stated, “[a]ll change orders shall be in

writing and signed by both the Owner and the Contractor.” 2 The contract also

included a payment schedule.

[¶3.] The Mullers made timely payments until the end of May 2017, leaving

approximately $5,000.00 to pay under the payment schedule. Ultimately, the

1. The contract included a page itemizing the work to be completed.

2. It is undisputed that the parties only entered into one written change order (involving concrete).

-1- #29684

Mullers withheld $2,690.00, claiming that items within the contract remained

incomplete. Suvada claimed that the Mullers had him complete work beyond what

was called for in the contract (“extras”) between August 2016 and January 2018,

preventing him from completing the contract on time. He asserted that the Mullers

gave him over 60 additional “extras,” which were not part of the written contract,

including installing different siding and soffit.

[¶4.] On January 10, 2018, approximately eight months after the contract’s

expected completion date, Suvada and Jack Muller spoke over the phone. Both

parties acknowledged that the phone call was “heated”; however, they disagreed

about the call’s contents. Jack Muller claimed that he asked Suvada to complete

the contractual work and that they would “figure out the extras after the

contractual work had been completed.” Suvada contended that Jack Muller told

him to stop working. Following the phone call, the Mullers sent Suvada an email

requesting that he bill them for the “extras” and complete the contract work by

March 1, 2018. 3

[¶5.] Suvada did not return to the worksite, and the project remained

incomplete. In February 2018, the Mullers sent Suvada a termination letter. In

March 2018, Suvada served the Mullers with his notice of intent to claim a

3. Over the course of the project, Suvada billed the Mullers for numerous “extras,” which the Mullers paid in addition to the contract amounts. As the project came to its conclusion, Suvada billed the Mullers for “extras” in December 2017 and February 2018. The Mullers initially wrote Suvada checks for the December invoices but later cancelled the checks before Suvada deposited them.

-2- #29684

materialmen’s lien4 on the property. Suvada then filed his lien statement with the

register of deeds in Lawrence County, alleging that the Mullers owed him

$16,389.35 for labor and materials. 5 Shortly after, the Mullers demanded that

Suvada commence suit to enforce the lien under SDCL 44-9-26. Suvada commenced

this action to foreclose the lien and also alleged breach of contract. He requested

the lien sum, costs, and attorney fees. Suvada simultaneously filed a notice of lis

pendens, including a bill of particulars with itemized invoices.

[¶6.] The Mullers filed their answer, denying Suvada’s causes of action and

asserting several affirmative defenses. The Mullers also counterclaimed, alleging

breach of contract, construction defects/negligence, fraudulent misrepresentations,

and seeking declaratory judgment. They demanded a jury trial on all issues triable

to a jury. The Mullers also sought $38,310.55 for the amount they expended to hire

All Star Construction (All Star) to finish the work Suvada allegedly failed to

complete under the contract.

[¶7.] Suvada filed a motion to dismiss and a reply to the Mullers’

counterclaims. Discovery ensued. In September 2020, Suvada filed a motion for a

scheduling order to establish dates to set a pretrial hearing and trial. The parties

agreed to a two-day jury trial starting on March 24, 2021.

4. A mechanic’s and materialmen’s lien grants a person, who “at the request of the owner . . . furnish[ed] skill, labor, services, including light, power, or water, equipment, or materials for the improvement, development, or operation of property” to have a lien thereon. SDCL 44-9-1.

5. The materialmen’s lien did not relate to anything owed under the contract; instead, it related only to the “extras” completed by Suvada at the Mullers’ request.

-3- #29684

[¶8.] On March 9, 2021, Suvada filed an objection to the Mullers’ demand

for a jury trial, arguing that a foreclosure of a materialmen’s lien operates like a

mortgage foreclosure and that foreclosures do not allow for a trial by jury. See First

Nat’l Bank of Phillip v. Temple, 2002 S.D. 36, ¶ 12, 642 N.W.2d 197, 202 (noting

that foreclosure of a mortgage is an equitable action); SDCL 44-9-23 (stating that a

materialmen’s “lien . . . action shall be begun and conducted in the same manner as

actions for the foreclosure of mortgages upon real estate”). He also argued that the

Mullers’ fraud claim and request for punitive damages do not entitle them to a jury

trial. In his view, his “mechanic’s lien is the heart of this litigation,” and “[a]ll other

claims are, at best, pendant [sic]” because “[t]he lien is based on the construction

contract between the parties, the change orders, and payment.”

[¶9.] In response to Suvada’s objection to a jury trial, the Mullers argued

that the parties had agreed to the jury trial in their scheduling order and noted that

Suvada’s complaint included a breach of contract claim, which they asserted was

appropriate for a jury trial. Similarly, they argued that their counterclaims for

breach of contract and fraud were both appropriate for a jury trial. The circuit court

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nelson v. Tinkcom
2025 S.D. 42 (South Dakota Supreme Court, 2025)
Smith Masonry v. Wipi Group Inc.
2025 S.D. 26 (South Dakota Supreme Court, 2025)
Acuity Insurance v. a Maxon and Weatherspoon
2024 S.D. 53 (South Dakota Supreme Court, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
983 N.W.2d 548, 2022 S.D. 75, Counsel Stack Legal Research, https://law.counselstack.com/opinion/suvada-v-muller-sd-2022.