Suvada v. Muller

983 N.W.2d 548, 2022 S.D. 75
South Dakota Supreme Court·Decided December 14, 2022·No. 29684·Published·Cited by 3 cases

Opinion

#29684-a-SPM 2022 S.D. 75

IN THE SUPREME COURT

OF THE

STATE OF SOUTH DAKOTA

****

ED SUVADA, Plaintiff and Appellant, v.

GEORGE JOHN MULLER, II and CHRISTINE MULLER, Defendants and Appellees.

****

APPEAL FROM THE CIRCUIT COURT OF THE FOURTH JUDICIAL CIRCUIT LAWRENCE COUNTY, SOUTH DAKOTA

****

THE HONORABLE ERIC J. STRAWN Judge

****

DAVE L. CLAGGETT of Claggett & Dill, Prof. LLC Spearfish, South Dakota Attorneys for plaintiff and appellant.

ROBERT J. GALBRAITH of Nooney & Solay, LLP Rapid City, South Dakota Attorneys for defendants and appellees.

****

CONSIDERED ON BRIEFS

FEBRUARY 14, 2022

OPINION FILED 12/14/22

MYREN, Justice [¶1.] Ed Suvada commenced this action to foreclose a materialmen’s lien to recover for material and labor he expended in renovating a cabin for George (Jack) and Christine Muller. Suvada also sought damages for breach of contract. The Mullers counterclaimed for breach of contract and fraud. The jury found in favor of Suvada on his materialmen’s lien, awarding him damages. The jury also found in favor of the Mullers on both of their claims but only awarded damages on the breach of contract claim. Suvada appeals, raising multiple issues. We affirm.

Facts and Procedural History [¶2.] Suvada is a carpenter with nearly 50 years of experience. In August 2016, Suvada signed a written contract with the Mullers for an addition and remodeling project on their cabin near Deadwood. The contract covered labor and materials and included a clause stating that the work 1 would be “substantially completed on or before the 31st day of May, 2017.” The Mullers agreed to pay Suvada $131,600.00 plus tax for the material and labor performed, subject to any authorized change orders. The contract stated, “[a]ll change orders shall be in writing and signed by both the Owner and the Contractor.” 2 The contract also included a payment schedule. [¶3.] The Mullers made timely payments until the end of May 2017, leaving approximately $5,000.00 to pay under the payment schedule. Ultimately, the

1. The contract included a page itemizing the work to be completed.

2. It is undisputed that the parties only entered into one written change order (involving concrete).

Mullers withheld $2,690.00, claiming that items within the contract remained incomplete. Suvada claimed that the Mullers had him complete work beyond what was called for in the contract (“extras”) between August 2016 and January 2018, preventing him from completing the contract on time. He asserted that the Mullers gave him over 60 additional “extras,” which were not part of the written contract, including installing different siding and soffit. [¶4.] On January 10, 2018, approximately eight months after the contract’s expected completion date, Suvada and Jack Muller spoke over the phone. Both parties acknowledged that the phone call was “heated”; however, they disagreed about the call’s contents. Jack Muller claimed that he asked Suvada to complete the contractual work and that they would “figure out the extras after the contractual work had been completed.” Suvada contended that Jack Muller told him to stop working. Following the phone call, the Mullers sent Suvada an email requesting that he bill them for the “extras” and complete the contract work by March 1, 2018. 3 [¶5.] Suvada did not return to the worksite, and the project remained incomplete. In February 2018, the Mullers sent Suvada a termination letter. In March 2018, Suvada served the Mullers with his notice of intent to claim a

3. Over the course of the project, Suvada billed the Mullers for numerous “extras,” which the Mullers paid in addition to the contract amounts. As the project came to its conclusion, Suvada billed the Mullers for “extras” in December 2017 and February 2018. The Mullers initially wrote Suvada checks for the December invoices but later cancelled the checks before Suvada deposited them.

materialmen’s lien4 on the property. Suvada then filed his lien statement with the register of deeds in Lawrence County, alleging that the Mullers owed him $16,389.35 for labor and materials. 5 Shortly after, the Mullers demanded that Suvada commence suit to enforce the lien under SDCL 44-9-26. Suvada commenced this action to foreclose the lien and also alleged breach of contract. He requested the lien sum, costs, and attorney fees. Suvada simultaneously filed a notice of lis pendens, including a bill of particulars with itemized invoices. [¶6.] The Mullers filed their answer, denying Suvada’s causes of action and asserting several affirmative defenses. The Mullers also counterclaimed, alleging breach of contract, construction defects/negligence, fraudulent misrepresentations, and seeking declaratory judgment. They demanded a jury trial on all issues triable to a jury. The Mullers also sought $38,310.55 for the amount they expended to hire All Star Construction (All Star) to finish the work Suvada allegedly failed to complete under the contract. [¶7.] Suvada filed a motion to dismiss and a reply to the Mullers’ counterclaims. Discovery ensued. In September 2020, Suvada filed a motion for a scheduling order to establish dates to set a pretrial hearing and trial. The parties agreed to a two-day jury trial starting on March 24, 2021.

4. A mechanic’s and materialmen’s lien grants a person, who “at the request of the owner . . . furnish[ed] skill, labor, services, including light, power, or water, equipment, or materials for the improvement, development, or operation of property” to have a lien thereon. SDCL 44-9-1.

5. The materialmen’s lien did not relate to anything owed under the contract;

instead, it related only to the “extras” completed by Suvada at the Mullers’

request.

Free access — add to your briefcase to read the full text and ask questions with AI

Suvada v. Muller, 983 N.W.2d 548, 2022 S.D. 75 (S.D. 2022).

983 N.W.2d 548 (Suvada v. Muller) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sleep v. Steele
South Dakota Supreme Court, 2026
Shevling v. Major
South Dakota Supreme Court, 2026
State v. Spry
South Dakota Supreme Court, 2026
Nelson v. Tinkcom
2025 S.D. 42 (South Dakota Supreme Court, 2025)
Smith Masonry v. Wipi Group Inc.
2025 S.D. 26 (South Dakota Supreme Court, 2025)
Acuity Insurance v. a Maxon and Weatherspoon
2024 S.D. 53 (South Dakota Supreme Court, 2024)