LDL Cattle Co., Inc. v. Guetter

1996 SD 22, 544 N.W.2d 523, 1996 S.D. 22, 1996 S.D. LEXIS 22
CourtSouth Dakota Supreme Court
DecidedMarch 6, 1996
DocketNone
StatusPublished
Cited by47 cases

This text of 1996 SD 22 (LDL Cattle Co., Inc. v. Guetter) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LDL Cattle Co., Inc. v. Guetter, 1996 SD 22, 544 N.W.2d 523, 1996 S.D. 22, 1996 S.D. LEXIS 22 (S.D. 1996).

Opinion

LEE D. ANDERSON, Circuit Judge.

[¶ 1] LDL Cattle Company Inc. (LDL) brought suit against Northern States Elevator Construction (NSE) claiming that NSE was negligent in causing a fire which destroyed LDL’s property. Following a two day trial, an Edmunds County jury returned a verdict in favor of NSE. The trial court ordered a new trial on the basis that the evidence did not support the jury’s verdict. NSE appealed the order granting a new trial and LDL filed a notice of review concerning other issues. We reverse the granting of a new trial and affirm the trial court on the other issues.

FACTS

[¶ 2] LDL is a large custom cattle-feeding operation located near the town of Ipswich in rural Edmunds County, South Dakota. NSE is in the business of constructing and selling grain and feed-handling structures and equipment. Its principal place of business is Lucan, Minnesota, but it commonly undertakes construction projects in South Dakota, North Dakota, Montana and Nebraska. William Guetter and Roger Guetter are partners and the owners of NSE.

[¶ 3] In 1991, LDL hired NSE to build a 22 foot I-beam steel “superstructure” which would hold two 1600 bushel overhead tanks or bins. The superstructure was being constructed directly west of and adjacent to four large silos and directly within and above the existing feed mill building on LDL’s property-

[¶ 4] By October 8,1991, the I-beam superstructure had been installed and bolted into the cement pad on the floor of the feed mill building. On October 8, 1991, NSE employees were welding with electrical arc welders to secure beams that had been previously tacked together. Conflicting testimony was presented at the trial as to whether NSE employees had also been welding with an acetylene cutting torch on that day. Immediately below where the welding and construction was occurring was a roller mill and a three foot deep pit. In the pit was an accumulation of corn, chaff, grain dust, and other debris, all of which are combustible.

[¶ 5] The welding of the superstructure was discontinued between 4:30 and 5:00 p.m. on the 8th because it was too windy to risk placing the bins onto the I-beam superstructure. NSE employees then swept up the area under the superstructure and proceeded to continue painting the bins which were *526 located in LDL’s machine shed directly northeast of the feed mill. Prior to completing their workday at approximately 7:30 p.m., NSE employees walked through the feed mill and inspected the area under and around the I-beam superstructure. Nothing out of the ordinary was detected during the inspection.

[¶ 6] At some time during the night of October 8, 1991, or the early morning hours of October 9,1991, a fire broke out in LDL’s feed mill. The fire was discovered between 5:30 and 6:00 a.m. on October 9th, 1991, by LDL employees, who called the Ipswich fire department to the scene. In subsequent investigations, it was discovered that the clock in the feed mill building had stopped at 4:56 a.m. Very little of the feed mill was left standing after the ensuing fire. LDL suffered damages of $647,099.

[¶ 7] The State Fire Marshal’s Office was called in to investigate whether or not the fire was intentionally set. The fire marshals were unable to determine with certainty where the fire had originated, what the actual ignition source of the fire was, or whether the welding had in any way contributed to the fire. The fire marshals were able to conclude the fire was not intentionally set. At trial the fire marshals testified it was not likely that any remnants of welding, which had ceased at 5:00 p.m. on October 8th, could smolder undetected for nine to twelve hours before it would erupt into a blaze.

[¶ 8] Three private fire investigators were subsequently called in by LDL to investigate the cause of the fire. One of these investigators determined the fire was not caused by lightning nor was it electrical in nature. LDL’s other two investigators testified to their opinion that NSE’s welding was the cause of the fire.

[¶ 9] In its suit against NSE, LDL alleged that it sustained damages as result of a fire which was the proximate result of the negligence of NSE. The negligence was alleged to be due to: 1) the use of a cutting torch and welder by NSE employees in an area of combustible materials and the failure to take proper precautions to prevent the fire; and 2) the failure of NSE employees to take proper precautions in the detection and ex-tinguishment of the fire.

[¶ 10] An Edmunds County jury returned a verdict in favor of NSE on January 11, 1995. On January 12,1995, the trial court on its own initiative placed the parties on notice that it would grant a motion for a new trial on the grounds the verdict was inconsistent with the evidence presented at trial pursuant to SDCL 15-6-59(a)(6).

[¶ 11] Thereafter, LDL moved the court for a new trial under SDCL 15-6-59(a)(l), (3), (6) and (7). On January 25, 1995, the trial court ordered “the judgment be vacated, the jury verdict for the defendants be set aside and a new trial be granted pursuant to SDCL 15 — 6—59(a)(6).”

ISSUES

I.Whether the trial court abused its discretion in granting a new trial?

II.Whether the trial court erred by excluding evidence that both parties had insurance?

III."Whether the trial court erred in giving jury instructions number 22 and 23 on circumstantial evidence?

STANDARD OF REVIEW

[¶ 12] A trial court may order a new trial on its own initiative pursuant to SDCL 15 — 6—59(d), for any reason which it may have granted a new trial based upon a motion by a party. Case v. Murdock, 488 N.W.2d 885, 888 (S.D.1992). However, before a trial court exercises its inherent power to grant a new trial for reasons not advanced by the parties, it must be “satisfied there has been a mistrial, or a clear miscarriage of justice, growing out of a failure of the court itself to discharge the duties of its office .... ” Junge v. Jerzak, 519 N.W.2d 29, 32 (S.D.1994) (quoting Larsen v. Johnson, 43 S.D. 223, 178 N.W. 876, 877 (1920)).

[¶ 13] It is a well-established rule in South Dakota that a trial court has broad discretion to grant a new trial on the ground of insufficient evidence. Lewis v. Storms, 290 N.W.2d 494, 497 (S.D.1980). Nevertheless, a jury’s verdict should not be set aside “except in extreme cases where it is the result of passion or prejudice or the jury has *527 palpably mistaken the rules of law....” Stoltz v. Stonecypher, 336 N.W.2d 654, 657 (S.D.1983)(citing Simons v. Kidd, 73 S.D. 306,

Related

Suvada v. Muller
983 N.W.2d 548 (South Dakota Supreme Court, 2022)
Lundstrom, Jr. v. Homolka, P.A.
D. South Dakota, 2022
Wright v. Temple
2021 S.D. 15 (South Dakota Supreme Court, 2021)
Isg, Corp. v. Ple, Inc.
2018 SD 64 (South Dakota Supreme Court, 2018)
State v. Bausch
2017 SD 1 (South Dakota Supreme Court, 2017)
Lewis v. Sanford Medical Center
2013 SD 80 (South Dakota Supreme Court, 2013)
Baldridge v. Weber
2008 SD 14 (South Dakota Supreme Court, 2008)
State v. Motzko
2006 SD 13 (South Dakota Supreme Court, 2006)
Johnson v. Armfield
2003 SD 134 (South Dakota Supreme Court, 2003)
Schoon v. Looby
2003 SD 123 (South Dakota Supreme Court, 2003)
Fritzmeier v. Krause Gentle Corp.
2003 SD 112 (South Dakota Supreme Court, 2003)
State v. Moran
2003 SD 14 (South Dakota Supreme Court, 2003)
C & W Enterprises, Inc. v. City of Sioux Falls
2001 SD 132 (South Dakota Supreme Court, 2001)
Biegler v. American Family Mutual Insurance Co.
2001 SD 13 (South Dakota Supreme Court, 2001)
Carpenter v. City of Belle Fourche
2000 SD 55 (South Dakota Supreme Court, 2000)
Rogen v. Monson
2000 SD 51 (South Dakota Supreme Court, 2000)
Artz v. Meyers
1999 SD 156 (South Dakota Supreme Court, 1999)
Morrison v. Mineral Palace Ltd. Partnership
1999 SD 145 (South Dakota Supreme Court, 1999)
Atkins v. Stratmeyer
1999 SD 131 (South Dakota Supreme Court, 1999)
Veeder v. Kennedy
1999 SD 23 (South Dakota Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
1996 SD 22, 544 N.W.2d 523, 1996 S.D. 22, 1996 S.D. LEXIS 22, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ldl-cattle-co-inc-v-guetter-sd-1996.