Timmons v. Nelsen

66 N.W.2d 406, 159 Neb. 193, 1954 Neb. LEXIS 107
CourtNebraska Supreme Court
DecidedOctober 8, 1954
Docket33514
StatusPublished
Cited by3 cases

This text of 66 N.W.2d 406 (Timmons v. Nelsen) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Timmons v. Nelsen, 66 N.W.2d 406, 159 Neb. 193, 1954 Neb. LEXIS 107 (Neb. 1954).

Opinion

Carter, J.

This is a suit to foreclose a mechanic’s lien on a new house in the claimed amount of $8,231.17. The answer of the defendants alleges an oral contract between the parties by which plaintiff agreed to-build the house for $32,075.20. Defendants paid $33,500 to the plaintiff and they claim an over-payment of $1,424.80. Defendants also filed a counterclaim for damages in the amount of $4,000 for the failure of the plaintiff to construct a driveway into the garage in accordance with the agreement. The trial court found that plaintiff had established a valid mechanic’s lien in the amount of $4,315.64 and ordered a sale of the property to satisfy the lien if it was not paid within 20 days. The counterclaim was dismissed. The plaintiff appealed and the defendants have taken a cross-appeal.

For convenience, Andrew C. Nelsen will hereafter be referred to as the defendant where only one defendant is indicated.

The record discloses that plaintiff was a general contractor engaged in the building of new houses in the city of Omaha during the times herein mentioned. It appears that on or before June 1, 1950, plaintiff had constructed a house adjacent to his own, which, he had for sale. Defendant and his wife became interested in this house, inspected it several times, and talked with plaintiff about its sale price. It was subsequently sold to one DeMoss for $32,500. Thereafter the defendant talked with plaintiff about building him a new house similar *195 to the DeMoss house. Defendant purchased a lot and commenced negotiations with the plaintiff for the construction of a new house. Defendant testified that plaintiff told him that the DeMoss house cost him $26,932 exclusive of the cost of the lot, and that he could duplicate it at $29,000 or $29,500 on any lot that defendant might select. It is the contention of the defendant that they calculated the cost of the house by using the basic cost of the DeMoss house in the amount of $26,932, and adding thereto the cost of changes to be made in the amount of $2,500 and a 10 percent profit amounting to $2,943.20. From the total cost thus calculated, amounting to $32,375.20, defendant claims a deduction of $300 arising from an alleged saving of fhat amount in substituting concrete floors for wood floors. Defendant asserts that plaintiff agreed to build the house for $32,075.20.

It is the contention of the plaintiff that the house was to be built in accordance with the plans of the DeMoss house, with the changes agreed upon prior to the commencement of construction and any other changes requested by the defendant in the course of construction. The evidence shows that plaintiff prepared a written contract to this effect which the defendant did not execute. The defendant gave as his reason that he desired his attorney to go over it. It appears that for one reason or another the contract was not submitted to defendants* attorney. The work proceeded without any written agreement being made and upon the oral agreements of the parties.

The trial judge found from the evidence that plaintiff had failed to establish an agreement that the house was to be built at cost plus 10 percent. The trial judge also found that there was no fixed sum agreed upon for the construction of the house, as claimed by the defendants. The court then found that the mechanic’s lien was valid in the amount of $36,014.90, the amount found due for labor and materials, plus 5 percent thereof, or *196 $1,800.75, for services-of the plaintiff in supervising the construction of the house, making a total cost of $37,815.65. Payment of $33,500 of this amount was paid by defendants, leaving a balance düe of $4,315.65, which the court decreed to be a lien upon the property. Both parties filed motions for a new trial. Both motions were overruled and plaintiff appealed. The defendants cross-appealed.

The defendants contend that the description of the labor and materials used in the construction of the house was insufficient to create a lien. We shall not determine this issue on its merits. Defendants failed to set forth in their assignments of error on their cross-appeal any claim of error on the part of the trial court in ruling on this issue. Under such circumstances the error, if any existed, will be deemed to have been waived. Okuda v. Hampton, 154 Neb. 886, 50 N. W. 2d 108.

Defendants also claim that the proof was insufficient to establish that the mechanic’s lien was filed within 4 months of the date of performance as required by section 52-103, R. R. S. 1943. The notice of lien shows that a number of items were furnished in March 1951. Specific days of that month were not designated as the days on which the labor and materials were furnished. The mechanic’s lien was filed on June 5, 1951. Assuming that all items shown to have been furnished in March 1951 were furnished on the first day of that month, the filing of the notice of lien was well within the 4-month period required by the statute.

The contention of the defendant that an oral agreement was made to the effect that plaintiff was to build the house for $32,075.20 cannot be sustained in this court. It is true that defendant produced evidence to this effect. The evidence of the plaintiff was in direct conflict therewith. The rule in such instances is: Where, in a suit in equity on a trial de novo, the evidence is in irreconcilable conflict, this court will consider the fact *197 that the district court observed the conduct and demean- or of the witnesses and gave credence to the testimony of some rather than to the contradictory testimony of others. Hehnke v. Starr, 158 Neb. 575, 64 N. W. 2d 68; Lakey v. Gudgel, 158 Neb. 116, 62 N. W. 2d 525. The finding of the district court on this contention is affirmed.

The evidence shows that plaintiff commenced the construction of the house without a written agreement being executed. A written contract was prepared on a cost plus 10 percent basis. Defendant did not execute it because he desired his attorney to examine it. He' knew that plaintiff understood the agreement to be on a cost basis with a 10 percent profit. He does not appear to have objected, and permitted plaintiff to proceed with the work. Monthly statements for labor and materials were submitted, containing a 10 percent charge which was designated as profit. Defendant paid $5,000 per month thereon for 6 months. He knew, or should have known, all during this period that plaintiff was charging the cost plus 10 percent. He permitted plaintiff to continue with the construction on that basis. Defendant wanted the subcontracting of special work submitted for competitive bidding. He procured one or two bids for plaintiff, a clear indication that he. at that time understood that the work was proceeding on a cost plus basis. The original invoices were turned over to defendant each month and retained by him. This, also, is evidence supporting the contention of the plaintiff that the house was not' being constructed for a fixed amount. We think the evidence considered as a whole sustains plaintiff’s allegation that the house was being constructed on a cost plus 10 percent basis and that the trial court’s finding to the contrary is not supported by the evidence.

The defendant contends that plaintiff failed to hold the cost of the construction down by failing to consider bids by subcontractors that were less than those accepted by the plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brandt v. Mayer
246 N.W.2d 203 (Nebraska Supreme Court, 1976)
Jensen v. Manthe
95 N.W.2d 699 (Nebraska Supreme Court, 1959)
S. A. Sorensen Construction Co. v. Broyhill
85 N.W.2d 898 (Nebraska Supreme Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
66 N.W.2d 406, 159 Neb. 193, 1954 Neb. LEXIS 107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/timmons-v-nelsen-neb-1954.