Lytle, Campbell & Co. v. Somers, Fitler & Todd Co.

120 A. 409, 276 Pa. 409, 27 A.L.R. 41, 1923 Pa. LEXIS 606
CourtSupreme Court of Pennsylvania
DecidedJanuary 3, 1923
DocketAppeals, Nos. 133 and 145
StatusPublished
Cited by43 cases

This text of 120 A. 409 (Lytle, Campbell & Co. v. Somers, Fitler & Todd Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lytle, Campbell & Co. v. Somers, Fitler & Todd Co., 120 A. 409, 276 Pa. 409, 27 A.L.R. 41, 1923 Pa. LEXIS 606 (Pa. 1923).

Opinion

Opinion by

Mr. Justice Kephart,

This is an action of assumpsit. Defendant, desiring to remodel'certain buildings, entered into a contract with plaintiff, Lytle, Campbell & Company, Inc., to do the work [412]*412“on a time and material basis, with ten per cent profit as compensation to the contractor, the records of the cost to be kept at all times in such a manner as to be checked and audited by the owners.” The controversy in these appeals arises from the construction to be given the words just quoted. Itemized statements were sent each week of the amounts paid the various workmen, and the cost of materials used. At the foot of each statement was a charge “10% overhead.” Payments were made on account, from' time to time, without reference to any specific statement. After the work was completed, a dispute arose over the “10% overhead.” Defendant contended all plaintiff was entitled to receive was the various amounts paid out for the time of laborers and the cost of materials, $64,183, plus ten per cent, $6,-418.32, with the same profit on materials furnished by defendant, $306.88, in all $70,908.20, and it had assumed that the “ten per cent overhead,” added to the weekly statements, was the profit allowed under the terms of the contract. Plaintiff, as we have seen, added to these items an overhead charge, arbitrarily fixed by it at ten per cent, plus a like profit on it. It also claimed an additional sum because of a mistake in the charges for mill-work, of which we shall speak later.

Defendant paid $70,908.20, leaving in dispute, first, the claim for “overhead,” and, second, the additional charge for millwork. The first question the court below decided adversely to plaintiff, and, on the second, gave judgment for $3,768.99. Both sides have appealed, and, as the case was tried without a jury, we will dispose of it finally in this opinion.

Plaintiff was a general contractor, principally engaged in repairing, remodeling and altering buildings, with its main office in the City of Pittsburgh, where this work was done. It had other contract's, in addition to the one before us, and supervised all its engagements from its central office. Under the charge of “overhead” it endeavored to collect “for the use of [these] offices [413]*413where the books of account were kept, and the clerks and bookkeepers to keep the books of account' from which the records of cost of the operation were, kept......The personal supervision of its officers......liability insurance,” rent, heat, light, telephones for the buildings in which their business was conducted, and for the use of building equipment. Also a charge for one of its officers as an architect. As we have said, to cover these items it fixed an arbitrary charge of ten per cent of the gross cost of the time and materials furnished to the operation under defendant’s contract.

If the charge of “overhead” is not brought within the terms of the agreement, it must fail; and to determine this we must ascertain the intention of the parties from the contract, as we are not aided by extraneous matters. In discussing the factors of costs and charges ordinarily included by the words “time and material basis” “for the work to be done,” without any other indication to broaden the scope, it is necessary to consider the general division and proper classification of costs and charges incurred by a business concern such as plaintiff’s and to ascertain from such classification what charges are generally accepted in the business world as coming under that designation; and the distinction there made should be borne in mind in construing “cost plus” contracts.

Overhead, or general expenses, as applied to a business concern, producing a utility possessing the quality of value or wealth, as generally understood, include all administrative or executive costs incident to the management, supervision or conduct of the capital outlay or its business. They are to be distinguished from operating charges, or those items inseparably connected with the productive end. The latter charges contain all elements of labor and materials, which directly produce a definite end, measured by cost or value. Overhead charges are generally of a nonproductive nature, in that they do not of themselves directly create a definite util[414]*414ity, and, while they are essential to the life of a business concern, yet in determining the value and the selling price of the utility, they must not be confused with those charges which actually produce a definite end, and upon which an organization depends for its continued existence. Moreover, they are charges usually for the greater part solely within the knowledge of the executive officials. As Ruskin says, in one of his essays on the laws of political economy, “A gain is unjust in a most fatal way which depends on keeping the exchangers ignorant of the exchange value of the articles.” On the other hand, operating charges are those which may be seen as the work progresses and are the subject of knowledge from observation. ■ The really essential line of distinction, as we view it, is that the one is a producing cost, capable of being ascertained by those dealing with the company, and the other is a nonproductive, or indirect, charge, difficult of ascertainment, and not ordinarily within the outsider’s knowledge. . The latter utilizes the earnings produced from the operating end, as the stockholders must, from the earnings of the productive end, pay the charges incident to the management of their capital invested, depreciation, interest and the risk of the venture. When “overhead” is disproportionate to capital and earnings, it usually spells disaster for the concern. There is a necessary correlation between the two, for it is true the one can scarcely exist without the other; but the fundamental difference must be observed, at least in contracts like the one before us. Suppose Lyt'le was sole owner and general contractor, would a “cost plus” contract permit him to charge for his services as manager, supervising and directing the administration of his own capital invested, and for a part of that supervision which he employs others to perform? Yet that is what is here asked under “overhead.” Or if, at the time, this was plaintiff’s only contract, and its contention be correct, why should not the entire executive or administrative salary-roll, with rents and other charges, be in-[415]*415eluded as part of the operating cost, and if not, upon what theory of allocation would plaintiff proceed? It seems necessary only to mention the possibilities that might arise to answer the suggestion. It is difficult to announce any rule of interpretation that will lay down a strict line of demarcation between the two charges, for there are many uncertain items fluctuating between the administrative and operative ends, partaking somewhat of both, which can be properly classified solely from a knowledge of the work done or the charge thereunder. This charge must be determined as each case presents its own peculiar circumstances. We deal with the facts before us on this appeal, applying, as far as we are able, the general rule above stated.

The term “overhead,” — including the salaries of executive or administrative officials, interest charges for floating bonds, carrying charges, depreciation, taxes and the general office expenses as here claimed, — cannot be allowed as an operating charge in “cost plus” contracts. To do so would open the doors to a flood of obligations not intended by the innocent words used in a contract such as the one before us. The term “time and material basis” was intended to include the necessary cost of operation

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glenn, L. v. Smith, A. v. Glenn, B.
Superior Court of Pennsylvania, 2018
Citibank v. Hull
26 Pa. D. & C.5th 188 (Clinton County Court of Common Pleas, 2012)
Ford v. Culp Custom Homes, Inc.
731 N.E.2d 468 (Indiana Court of Appeals, 2000)
Kubela v. Schuessler Lumber Co.
492 S.W.2d 92 (Court of Appeals of Texas, 1973)
Herre Bros. v. Rhoads
222 A.2d 486 (Superior Court of Pennsylvania, 1966)
Domineck v. Tuskan
193 A.2d 626 (Superior Court of Pennsylvania, 1963)
Ballinger v. Howell Manufacturing Co.
180 A.2d 555 (Supreme Court of Pennsylvania, 1962)
Conditioned Air Corp. v. Rock Island Motor Transit Co.
114 N.W.2d 304 (Supreme Court of Iowa, 1962)
Harris & Harris Construction Co. v. Crain & Denbo, Inc.
123 S.E.2d 590 (Supreme Court of North Carolina, 1962)
Carrico v. City & County of San Francisco
177 Cal. App. 2d 97 (California Court of Appeal, 1960)
Jensen v. Manthe
95 N.W.2d 699 (Nebraska Supreme Court, 1959)
Clearfield Development Corp. v. Devonian Gas & Oil Co.
122 A.2d 718 (Supreme Court of Pennsylvania, 1956)
Dunn v. Hammon Drug Co.
284 P.2d 468 (Arizona Supreme Court, 1955)
Nolop v. Spettel
64 N.W.2d 859 (Wisconsin Supreme Court, 1954)
Pioneer Constructors v. Symes
267 P.2d 740 (Arizona Supreme Court, 1954)
Hotpoint Inc. v. United States
117 F. Supp. 572 (Court of Claims, 1954)
Washington Construction Co., Inc. v. Spinella
84 A.2d 617 (Supreme Court of New Jersey, 1951)
Denemark v. Ed B. Mooney, Inc.
237 S.W.2d 41 (Supreme Court of Arkansas, 1951)
Mann v. Schnarr
95 N.E.2d 138 (Indiana Supreme Court, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
120 A. 409, 276 Pa. 409, 27 A.L.R. 41, 1923 Pa. LEXIS 606, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lytle-campbell-co-v-somers-fitler-todd-co-pa-1923.