Carrico v. City & County of San Francisco

177 Cal. App. 2d 97, 2 Cal. Rptr. 87, 1960 Cal. App. LEXIS 2434
CourtCalifornia Court of Appeal
DecidedJanuary 13, 1960
DocketCiv. No. 18415
StatusPublished

This text of 177 Cal. App. 2d 97 (Carrico v. City & County of San Francisco) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carrico v. City & County of San Francisco, 177 Cal. App. 2d 97, 2 Cal. Rptr. 87, 1960 Cal. App. LEXIS 2434 (Cal. Ct. App. 1960).

Opinion

TOBRINER, J.

Appellant general contractors predicate this appeal on the lack of substantial evidence in the record to support three portions of the findings and judgment in favor of respondent city and county of San Francisco: (1) appellants improperly constructed certain roofs to respondent’s damage in the sum of $17,923.64; (2) respondent properly delayed acceptance of, and final payment for, the buildings because of appellants’ contractual failures; and (3) con[99]*99tract modification number 23, providing for installation of the skylights, entitled appellants only to payment for labor and materials, excluding both shop overhead incurred by the subcontractor and also overhead and profit of the general contractors. As we shall explain, we have found the judgment properly supported by the evidence in all respects except that the general contractors should recover the entire amount billed them by the subcontractor, inclusive of the subcontractor’s shop overhead.

The instant dispute is the deformed issue of a contract for the construction of four identical recreation centers in San Francisco: Potrero Hill, Ocean View, St. Mary’s and Sunset. On October 24, 1949, appellants contracted to construct these centers, the work to be “entirely completed” within 365 days. Respondent in turn agreed to make progress payments equal to 90 per cent of the work done, the balance to be paid after the Recreation Department’s engineer had found that the work had been “fully and satisfactorily completed” and the Recreation “Commission ha[d], by resolution, accepted the work.” The contract imposed upon appellants the duty of protecting and safeguarding the work, “from any” cause, until acceptance by respondent. The contract also provided that the respondent city and county could take “possession of” the recreation centers and “open [them] for public use” without such "constituting acceptance of the work or any part thereof.” Appellants commenced work in October or November of 1949, and by December, 1950, had completed 95 per cent of the work and received progress payments accordingly.

The skylights, which had been installed pursuant to the plans and specifications, leaked. On January 26, 1951, the parties modified the contract to provide for a complete reworking of the skylights, such work, according to modification number 23, to be done on a “time and material” basis. Appellants completed the reconstruction of the skylights, which differed from the original plans, ‘‘[s]ometime during the month of February or early March, 1951. ...”

By May 25, 1951, the city took possession of the recreation centers for its “custodial care.” In January, 1952, the city finally accepted the buildings, respondent making the retention payment of $85,000 to appellants on February 29, 1952. The parties left for future settlement the payment pertaining to modification number 23.

After a trial without jury the court rendered the following findings, among others: (1) that throughout “the year 1951, [100]*100and until January 24,1952, ’ ’ the refusal of respondent to make final payment to appellants and formally to accept the work done under the contract “was due to non-compliance by [appellants] . . . with the ‘check list’ or ‘punch list’ demands” of respondent, which lists contained demands by respondent that appellants correct work not done in conformity with the contract, and failure to supply respondent with proper specifications in the bill for work under contract modification number 23; (2) that contract modification number 23, entitling appellants to their cost for “time and material,” did not include provision for overhead and profit but only for cost of labor and material, which amounted to $4,801.81; and (3) that appellants defectively constructed the “fieldhouse roof on each recreation center,” causing respondent damage in the amount of $4,231 with respect to each roof. The court entered judgment on September 17, 1957, which: (1) awarded appellants $4,801.81, (2) awarded respondent $17,923.60, and (3) denied appellants’ other claims against respondent.

Appellants attack the sufficiency of the evidence to support the findings and judgment. We turn to an examination of the evidence for support of the findings.

First, was appellants’ failure to properly construct the field-house roofs sufficiently established?

The plans and drawings for the construction of the fieldhouse roofs call for a pitch of one-eighth inch per foot which was to be achieved by use of light weight concrete fill. This fill was to be placed on top of the structural concrete slab. City Assistant Engineer Downey, a graduate civil engineer, testified that he inspected the roofs on the fieldhouses at each of the centers, and “that where these roofs are flat roofs they have not pitched them by the installation of this light weight aggregate to carry the respective drains. [E]very place where we have a level roof they [appellants] haven’t done the work which would drain, the water off to the various drains, and that’s what we call by the filler or installing the light weight aggregate that would create the slope . . . and that’s what the architect intended. ...” Downey also stated that in “pouring this construction slab you . . . get highs and lows. ...” Moreover, the architect who prepared the plans and drawings testified if the one-eighth inch per foot were uniform, such uniformity would be sufficient for drainage purposes under ordinary circumstances. Finally, respondent’s Exhibit Six, prepared by Mr. Corollo, one of its inspectors, contained a showing of the pitch for the fieldhouse roofs at [101]*101numerous points, per plans, and appellants’ deviations therefrom at the Ocean View and Sunset Recreation Centers.

While appellants’ expert witness, structural engineer Robinson, testified that the plastic flow of concrete in the roofs in question could be up to one-half inch, Corollo in turn stated that 50 per cent of this plastic flow takes place within the first two and one-half months. Furthermore, Robinson admitted that “if you screeded your fill material to an accurate grade after your forms had been stripped for quite a while [from the concrete slab] . . . you would definitely improve the accuracy of your surface by using a fill material. ’ ’

As to the cost of conforming the roof construction to the plans, General Manager Collins of C. J. Collins, general contractor, after reviewing the plans and specifications, estimated that this would be $16,924 the figure being based on the cost of removing the asphalt and gravel from the roofs and installing the light weight aggregate.

In light of the foregoing testimony appellants’ claim that the evidence is insufficient to support the judgment cannot stand. Creager’s testimony that appellants installed the required pitch in the concrete slab is refuted by the specific measurements of the Ocean View and Sunset roofs. Lastly, the trial court’s rejection of appellants’ contention that they were given permission to place the pitch in the concrete slab is supported both by Harman’s testimony and the contract itself.

While the evidence as to the defective roofs of Potrero Hill and St. Mary’s is not as explicit as that regarding the roofs at Ocean View and Sunset, the court could properly conclude that appellants’ attempt to place the pitch in the concrete slab did not afford respondent the protection for which it had contracted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vowels v. Witt
308 P.2d 415 (California Court of Appeal, 1957)
Fox-Woodsum Lumber Co. v. Fidelity & Deposit Co.
188 P. 70 (California Court of Appeal, 1920)
George Parks & Co. v. Howard Hotel Realty Co.
203 N.W. 247 (Supreme Court of Iowa, 1925)
Dougherty v. Iredale
108 N.E.2d 754 (Ohio Court of Appeals, 1952)
Thoroughbred Motor Court, Inc. v. Allen Co.
296 S.W.2d 690 (Court of Appeals of Kentucky, 1956)
Hamilton v. Coogan
28 N.Y.S. 21 (New York Court of Common Pleas, 1894)
Advance Auto Body Works, Inc. v. Asbury Transportation Co.
52 P.2d 958 (California Court of Appeal, 1935)
Lytle, Campbell & Co. v. Somers, Fitler & Todd Co.
120 A. 409 (Supreme Court of Pennsylvania, 1923)
Ford v. St. L., K. & N. W. R.
7 N.W. 126 (Supreme Court of Iowa, 1880)
Grafton Hotel Co. v. Walsh
228 F. 5 (Fourth Circuit, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
177 Cal. App. 2d 97, 2 Cal. Rptr. 87, 1960 Cal. App. LEXIS 2434, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carrico-v-city-county-of-san-francisco-calctapp-1960.