Denemark v. Ed B. Mooney, Inc.

237 S.W.2d 41, 218 Ark. 944, 1951 Ark. LEXIS 450
CourtSupreme Court of Arkansas
DecidedApril 2, 1951
Docket4-9309
StatusPublished
Cited by2 cases

This text of 237 S.W.2d 41 (Denemark v. Ed B. Mooney, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Denemark v. Ed B. Mooney, Inc., 237 S.W.2d 41, 218 Ark. 944, 1951 Ark. LEXIS 450 (Ark. 1951).

Opinions

Robinson, J.

The appellants herein, Mr. and Mrs. Emil Denemark, are residents of Chicago, and are partners owning a string of horses and operating a racing stable.

In the fall of 1948, they decided to bnild a stable near the race-track at Hot Springs, Arkansas, and had plans and specifications prepared by an architect in Chicago. Denemark brought these plans and specifications to Hot Springs and consulted with Mr. Joe McRae, Secretary-Treasurer and, apparently, Manager of the appellee Ed B. Mooney, Incorporated.

McRae gave Denemark an estimate of the costs of building a stable according to the plans and specifications which Denemark exhibited to him. The parties disagree as to the amount McRae estimated it would cost to build the stable. The plans also provided for living quarters for the grooms in connection with the same building. But, be that as it may, it is agreed that whatever price McRae gave Denemark, it was more than Denemark wanted to spend on the structure.

Denemark then returned to Chicago where he had other plans and specifications prepared for a cheaper barn and a two-story frame residence. After another meeting with McRae at Hot Springs, it was agreed that appellee was to build the structures. The parties are in hopeless disagreement as to the estimate that McRae gave as the cost. McRae says it was $37,817 for the stable and $9,500 for the house. Denemark says the estimate on the barn and house together was $26,500.

In any event, it was agreed that appellee was to construct the buildings on a cost-plus arrangement, either cost plus ten per cent or a straight fee. Denemark returned to Chicago and had his secretary, Mr. Frank J. Kotnour, send appellee $10,000 as part payment.

On November 18th McRae wrote to Kotnour as follows:

“This will acknowledge receipt of the check No. 4632 in the amount of $10,000 which is to he applied upon the costs of the construction of the house and stable building now under construction by us for Mr. Denemark in Hot Springs, Arkansas.

“I am enclosing the daily report copies of the costs to date on the job, which has been set up on a strict actual cost basis plus 10%, with us to furnish all small tools (hand tools such as picks, shovels, mortar hoes, electric saws, vibrators and allied hand tools that would be used on the job), at no cost to the owner except for re-sharpening. This I discussed with Mr. Denemark when he was here, and he advised me to go ahead and we would agree on either this basis or a straight fee for my services, so I have set it up this way, and he and I will agree on the final figure at a later date when he is down here.

“On all purchases we will furnish you with the original copy of the purchase order with each report at the completion of the job, will furnish you with the invoices to cover same. In this way you will have a complete breakdown of the cost of the labor and material used in the construction of these building's.”

On the 27th of November, Denemark made another trip to Hot Springs at which time he authorized certain changes in the structures and the addition of a one-story bunk-house. McRae - was unable to obtain the metal roofing and Denemark, at the cost of about $4,000, obtained it in Chicago, and paid for it.

On December 12th McRae wrote to Kotnour, Denemark’s secretary, as follows:

“Enclosed please find the copies of the daily reports for the week ending December 10th together with the Estimate No. 4 and the cash statement to accompany same.

“I will try to give you an over-all picture of the progress of the job for the week as it stands today:

“Barn; all concrete block work 100% complete. Posts for stall framing all erected and cut to finished grade. Sills to carry loft floor are erected except circle corner at ends. Floor joists and loft floor 65% complete. Will complete Monday if we get a full day’s work without rain. Steel columns to carry roof section erected complete, all bolts set in walls and the concrete sill under window section ready for the steel. Steel for roof and roof materials will be delivered to the job complete on Tuesday of this week, steel workers all set to start Wednesday morning. Hardware for stall doors all in town, ready when needed.

“Big house: 80% completed; carpenters will finish installation of all sheet rock on walls and ceilings Monday, will start trim on windows and door frames sometime Monday; should start hanging doors in house by Wednesday and painter crew will start Monday to taping joints of sheet rock. Brick mason has the fireplace 70% complete — will complete Tuesday of this week. House will definitely be completed and ready before the 1st of January.

“Small house: Plumbing all roughed in, floor and foundation poured 100% complete, brick masons now laying' exterior tile walls. Should complete all the walls and partitions this week.

“On an over-all picture of the job, barring as much as 4 or 5 days’ rain between now and next Tuesday, one week from now, the entire project will be completed in time to use on the 1st of January, or shortly thereafter.

“One other thing that I imagine that Denemark is interested in will be the final anticipated cost of the entire project, which is of course impossible to guage accurately, but we are attempting to give your office a picture of the project as best we can.

“Project cost to date is................................................$16,533.03

Cost of steel framing & roof erected for

barn is .............................................................................. 12,500.00

Estimated costs to finish stalls & barn,

bunkhouse & big house complete ......... 10,000.00

Total ................................................................................................$39,033.03

“I do not think that the costs will vary more than 10% either way from the above estimate unless we get other changes that we do not know about at the present time. ’ ’

On December 18th Denemark made another trip to Hot Springs at which time he authorized the addition of a one-half bath in the two-story frame house, a second story to the bunkhouse consisting of one room and bath, and the construction of a four-car garage.

On December 31st appellee sent Denemark a statement showing the cost of the project as $38,984.87, which included appellee’s 10% commission. On January 5th appellee sent Denemark a statement showing the cost to be $54,737.05. When Denemark received this $54,737.05 statement, it was for more than he had anticipated. He immediately went to Hot Springs, arriving there on January 8th, and had a conference with McRae on the 9th, at the conclusion of which Denemark gave McRae a check for $19,737.05. Denemai'k states that he paid this under protest; that McRae assured him he would have an audit made of everything and if Denemark was entitled to a refund he would get it; that he was led to believe that he would get a refund.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
237 S.W.2d 41, 218 Ark. 944, 1951 Ark. LEXIS 450, Counsel Stack Legal Research, https://law.counselstack.com/opinion/denemark-v-ed-b-mooney-inc-ark-1951.