Glenn, L. v. Smith, A. v. Glenn, B.

Superior Court of Pennsylvania·Decided June 25, 2018·No. 578 MDA 2017·Unpublished

Opinion

J-A04042-18

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

LARRY GLENN, D/B/A LARRY GLENN : IN THE SUPERIOR COURT OF CONSTRUCTION : PENNSYLVANIA : Appellant : : : v. : : : No. 578 MDA 2017 ANDREA H. SMITH : : : v. : : : BRIDGET GLENN D/B/A LARRY : GLENN CONSTRUCTION :

Appeal from the Judgment Entered March 17, 2017 In the Court of Common Pleas of Clinton County Civil Division at No(s): 126-14

LARRY GLENN, D/B/A LARRY GLENN : IN THE SUPERIOR COURT OF CONSTRUCTION : PENNSYLVANIA : : v. : : : ANDREA H. SMITH : : No. 659 MDA 2017 Appellant : : : : : v. : : : BRIDGET GLENN D/B/A LARRY : GLENN CONSTRUCTION : J-A04042-18

Appeal from the Judgment Entered March 17, 2017 In the Court of Common Pleas of Clinton County Civil Division at No(s): 126-14

BEFORE: STABILE, J., NICHOLS, J., and RANSOM*, J.

MEMORANDUM BY RANSOM, J.: FILED JUNE 25, 2018

Larry Glenn d/b/a Larry Glenn Construction (“Contractor”) and

Andrea H. Smith (“Homeowner”) both appeal from the judgment entered on

March 17, 2017. We affirm Contractor’s liability to Homeowner, that Bridget

Glenn (“Bridget”) has no liability to Homeowner, and that Homeowner has no

liability to Contractor, but we vacate the judgment and remand for a new

hearing limited to the issue of damages.

In early 2012, Homeowner approached Contractor about building a

home. In April 2012, Contractor and Homeowner signed a document entitled

“Contractor Agreement – LARRY GLENN CONSTRUCTION” (“Contract”).

According to the terms of the Contract, Contractor would charge Homeowner

for “time, materials and 10% profit.”

Contractor started construction in June 2012 and completed it in

October 2012. Contractor provided invoices to Homeowner throughout the

construction, each one noting the hours of labor as follows: June – 556 hours;

July - 1,065.5 hours; August – 660.5 hours; September – 673 hours; and

October – 242 hours. Pl.’s Ex. 3 (collectively).

Contractor also performed landscaping pursuant to a subsequent oral

____________________________________ * Retired Senior Judge assigned to the Superior Court.

-2- J-A04042-18

agreement. Prior to the completion of the home, Homeowner requested

additions of a finished basement and an outside deck. These embellishments

were not included in the Contract.

Upon moving into the home in November 2012, Homeowner discovered

that the roof leaked. Trial Court Opinion (TCO), 10/5/16, at 2, 5. Upon further

investigation, she learned that the gutters also leaked at the seams, were not

pitched properly, and did not drain and that the trim at the garage doors was

water-damaged and loose. After uncovering these problems, Homeowner

refused to pay the balance under the Contract.

In February 2014, Contractor filed a complaint against Homeowner for

breach of contract and unjust enrichment, in order to collect the unpaid

balance. In March 2014, Homeowner filed an answer and counterclaim for

breach of contract, unjust enrichment, and violations of the Unfair Trade

Practices and Consumer Protection Law (“UTPCPL”). For her breach of

contract claim, Homeowner alleged that Contractor’s performance was not “in

a good and workmanlike manner” and was not in compliance with the

Contract. Answer with New Matter & Countercl., 3/3/14, at ¶¶ 64, 84. For

the UPTCPL claim, Homeowner contended that Contractor engaged in unfair

or deceptive acts or practices by “represent[ing] that services are of a

particular standard, quality or grade [when] they [were] of another” and

engaging in other “fraudulent or deceptive conduct and thereby creating the

likelihood of confusion or misunderstanding,” specifically by “greatly inflating

the costs under the [C]ontract.” Id. at ¶¶ 95-96, 105 (citing 73 P.S. § 201-

-3- J-A04042-18

2(4)(vii), (xxi)). Homeowner simultaneously filed a complaint to join

additional defendant, Bridget, raising the same three counts.

In March 2014, Contractor filed preliminary objections to Homeowner’s

counterclaim. In his preliminary objections, Contractor contended that

Homeowner’s counterclaim under the UTPCPL was precluded by the “gist of

the action” doctrine.1 The trial court agreed with Contractor, stating that

“[t]he UTPCPL is clearly a social policy determination by the legislature

imposing sanctions for fraud or, since recent amendments [in 1996],

‘deceptive’ conduct.” Order, 5/16/14, at 3. In May 2014, the trial court thus

sustained the Contractor’s preliminary objection and dismissed “all references

in [Homeowner]’s pleading to the UTPCPL[.]” Id. at 5. In June 2014,

Homeowner filed an amended new matter and counterclaim, in which she

stated: “Upon information and belief, [Contractor] greatly inflated the costs

under the [Contract] by misrepresenting the rate being paid to employees and

by charging a 10% profit on this inflated rate and on materials purchased by

____________________________________________

1 The gist of the action doctrine bars a plaintiff from re-casting ordinary breach of contract claims into tort claims. . . .

Although they derive from a common origin, distinct differences between civil actions for tort and contract breach have developed at common law. Tort actions lie for breaches of duties imposed by law as a matter of social policy, while contract actions lie only for breaches of duties imposed by mutual consensus agreements between particular individuals.

Knight v. Springfield Hyundai, 81 A.3d 940, 950 (Pa. Super. 2013) (internal citations and quotation marks omitted) (some formatting).

-4- J-A04042-18

[Homeowner] for her own home.” Am. New Matter & Countercl., 6/3/14, at

¶ 61.

In July and November 2014, some repairs were completed on the home.

TCO, 10/5/16, at 4. These repairs included caulking around windows and

exterior sealing. The total cost of these repairs was $1,876.30.

During a bench trial, Homeowner presented the report and expert

testimony of a building inspector, Kevin R. Crane. Ex. Smith-21 (Crane’s

expert report; HouseMaster Report ID: CEIKC7900); Notes of Testimony

(N.T.), 7/27/16, at 15-49. Crane testified about problems with various

components of Homeowner’s house. He explained the ratings system that he

and other inspectors use, including that any element of a building rated as

“poor” “requires immediate attention.” Id. at 12.

Crane began by testifying that the gutters installed by Contractor

leaked, were not set to the proper pitch to allow gravity to drain the water

downwards, and were installed with non-copper screws at the seams, which

are likely to corrode. Id. at 17-19. He explained that the “water is standing

in the gutter and it’s not draining” and that “it has to be changed.” In his

opinion, the gutters rated as “poor” and “needed to be addressed.” Id.; see

also Ex. Smith-21 at 6, 20 ¶ 1.3 (rating gutters as “poor”; “[g]utters will

require repairs to function properly”).

Next, Crane testified that the entry doors had “a poor fit and finish.”

N.T., 7/27/16, at 22-23. Although he rated them as “fair” instead of “poor,”

he explained that, here “[f]air means that the element was functional, but

-5- J-A04042-18

there are certain things about it that may require or will require repair.” His

report recommended that a “qualified contractor should be consulted to

determine remedial action[.]” Ex. Smith-21 at 8.

He continued that the stone of the front stoop was crumbling. N.T.,

Free access — add to your briefcase to read the full text and ask questions with AI

Glenn, L. v. Smith, A. v. Glenn, B., (Pa. Ct. App. 2018).

Glenn, L. v. Smith, A. v. Glenn, B. (Glenn, L. v. Smith, A. v. Glenn, B.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kiser v. Schulte
648 A.2d 1 (Supreme Court of Pennsylvania, 1994)
Troncatti v. Smereczniak
235 A.2d 345 (Supreme Court of Pennsylvania, 1967)
Stilp v. Hafer
718 A.2d 290 (Supreme Court of Pennsylvania, 1998)
Flank v. Walker
157 A.2d 163 (Supreme Court of Pennsylvania, 1960)
Schott v. Westinghouse Electric Corp.
259 A.2d 443 (Supreme Court of Pennsylvania, 1969)
Connolly v. Philadelphia Transportation Co.
216 A.2d 60 (Supreme Court of Pennsylvania, 1966)
Lambert v. PBI INDUSTRIES
366 A.2d 944 (Superior Court of Pennsylvania, 1976)
Kraner v. Kraner
841 A.2d 141 (Superior Court of Pennsylvania, 2004)
Strong v. Option One Mortgage Corp.
356 B.R. 121 (E.D. Pennsylvania, 2004)
In Re Estate of Leitham
726 A.2d 1116 (Commonwealth Court of Pennsylvania, 1999)
Kravinsky v. Glover
396 A.2d 1349 (Superior Court of Pennsylvania, 1979)
Wiggins v. Synthes (U.S.A.)
29 A.3d 9 (Superior Court of Pennsylvania, 2011)
McKniff v. Wilson
172 A.2d 801 (Supreme Court of Pennsylvania, 1961)
Messer v. Beighley
187 A.2d 168 (Supreme Court of Pennsylvania, 1963)
Wolfe v. PICKELL
205 A.2d 634 (Superior Court of Pennsylvania, 1964)
Ely, M. v. Susquehanna Aquacultures, Inc.
130 A.3d 6 (Superior Court of Pennsylvania, 2015)
Huey v. Blue Ridge Transportation Co.
39 A.2d 602 (Supreme Court of Pennsylvania, 1944)
Donahue v. Philadelphia
41 A.2d 879 (Superior Court of Pennsylvania, 1944)
Fix's Estate
12 A.2d 826 (Superior Court of Pennsylvania, 1940)
Robbins v. Weinstein
17 A.2d 629 (Superior Court of Pennsylvania, 1940)