Nolop v. Spettel

64 N.W.2d 859, 267 Wis. 245, 1954 Wisc. LEXIS 280
CourtWisconsin Supreme Court
DecidedJune 8, 1954
StatusPublished
Cited by22 cases

This text of 64 N.W.2d 859 (Nolop v. Spettel) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nolop v. Spettel, 64 N.W.2d 859, 267 Wis. 245, 1954 Wisc. LEXIS 280 (Wis. 1954).

Opinion

Fairchild, C. J.

Although there was never a written contract between the parties to this action, it is stipulated that they agreed to be bound by a written contract that had existed between the respondent and one Doctor Hulick, the pertinent portions of which contract follow:

“2. The owner agrees and covenants with the contractor to pay or cause to be paid to the contractor for the work performed, and the materials furnished by the contractor as follows:
“The actual net cost to the contractor of the materials actually furnished and labor and cartage actually performed by him hereunder on and for said building, plus a profit of 10 per cent.
*248 “The term actual net cost shall include the following:
“(a) The cost of all labor furnished;
“(b) The actual net cost of all materials purchased as shown by the original invoices;
“(c) The expense incurred by the contractor for cartage of all supplies and other expenses incidental to the erection of the building;
“(d) The cost of rental of any equipment which the contractor deems necessary or beneficial in the erection of the building;-
“(e) The cost of insurance including workmen’s compensation expended by the contractor in the erection of the building, except subcontracts.
“3. The owner is to make payments to the contractor . . . to be based upon a detailed itemized statement supported by invoices showing the net cost of materials delivered to the building site, materials actually installed in the building, the cost of cartage, the expenditure of labor, . . .
“4. The contractor agrees to keep accurate records and books of account showing the cost of the work performed and materials furnished . . .
“5. The contractor agrees that in consideration of the services performed by him that the sum hereinbefore agreed to be paid to him as contractor shall be full and complete compensation for the services to be performed by the contractor, it being the understanding between the parties that the contractor shall receive 10 per cent of the total cost of the erection of the building as compensation for his services.”

During the progress of the construction of the buildings statements showing various charges for labor at an hourly rate were submitted to appellant. The evidence shows that appellant was under the impression that all of the charges made by respondent for labor were the amounts actually paid in wages at the rates claimed; and that appellant continued to make payments without objection until the residence was substantially completed, at which time he learned from one of the painters that the rate per hour charged for his services to appellant was higher than the rate actually paid him by *249 respondent. Appellant, then unwilling to pay the balance claimed by respondent, insisted that an accounting be had. An action was begun, and an adverse examination of respondent was had in May, 1953. Then for the first time appellant learned what respondent had in fact paid his employees. The items claimed by respondent were reviewed in detail before a referee, and some of the items were disallowed. The referee made his findings of fact and concluded that appellant was indebted to respondent in the sum of $756.82, with interest from April 28, 1952. The circuit court confirmed the referee’s report and ordered judgment accordingly.

The first contention of the respondent, that appellant, by his actions in failing to complain to the contractor and in making payments on the contract and ordering new work to be done, waived any objections to any alleged overcharges or methods of computations, cannot be sustained. The great weight and clear preponderance of evidence does not permit of a finding that appellant, at the time he made those payments, was apprised that the rates per hour and the totals for labor set forth in statements presented to him by respondent included overcharges to cover an excess of incidentals or overhead. He did not learn that he was being so charged until the building was substantially completed. “A waiver is the intentional relinquishment of a known right.” Swedish American Nat. Bank v. Koebernick, 136 Wis. 473, 479, 117 N. W. 1020. “Since an intention to relinquish an existing right or advantage is generally regarded as an essential of a waiver, it follows that it must be shown by the party claiming a waiver that the person against whom the waiver is asserted had at the time knowledge, actual or constructive, of the existence of his rights or of the facts upon which they depended. Ignorance of a material fact negatives a waiver. Waiver cannot be established by a consent given under a mistake of fact.” 56 Am. Jur., Waiver, p. 114, *250 sec. 14. At no time did the respondent inform appellant as to what he in fact was paying his men; appellant had no knowledge of the overcharge at the time he paid the bills presented to him; therefore no waiver existed.

Respondent’s second contention, that labor includes items other than wages, is an unwarranted interpretation of the contract. He has taken the provision under subparagraph (c) of the contract allowing him “other expenses incidental to the erection of the building” and treated it as if it were part of (a) which refers to “the cost of all labor furnished;” then he has insisted that it be included as overhead. Using this method of computation, respondent has billed appellant for labor an amount per laborer greater than the actual amount paid out per laborer in wages.

The contract in question is a cost-plus contract. It provides separately for a profit of 10 per cent to be realized by the contractor on the cost of the erection of the building. The term “actual cost” governs the entire contract and applies to each of the subitems, i. e., labor, material, cartage, incidental expenses, rental equipment, and insurance and work-, men’s compensation. Further, payment by appellant for all of these separate items is subject to their being actually furnished or actually performed on and for said building, as stipulated in the second paragraph of the Dr. Hulick contract.

A review of available cases on cost-plus contracts and analogous cases requires the recognition of the general rules which are to be applied to the instant case. In one of the leading cases on this subject, it is said: “The term ‘overhead,’ — including the salaries of executive or administrative officials, interest charges for floating bonds, carrying charges, depreciation, taxes, and the general office expenses as here claimed, — cannot be allowed as an operating charge in ‘cost-plus’ contracts. - To do so would open the doors to a flood of obligations' not intended by the innocent words used in a contract such as the one before us. The term ‘time and ma *251 terial basis’ was intended to include the necessary cost of operation affecting the particular undertaking, — the cost of labor and materials that went into and became part of the finished product;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Freeman & Co. v. Bolt
968 P.2d 247 (Idaho Court of Appeals, 1998)
Milas v. Labor Ass'n of Wisconsin, Inc.
571 N.W.2d 656 (Wisconsin Supreme Court, 1997)
Reckner v. Reckner
314 N.W.2d 159 (Court of Appeals of Wisconsin, 1981)
Mansfield v. Smith
277 N.W.2d 740 (Wisconsin Supreme Court, 1979)
Walberg v. State
243 N.W.2d 190 (Wisconsin Supreme Court, 1976)
Harris Bros. Construction Co. v. Crider
497 S.W.2d 731 (Court of Appeals of Kentucky, 1973)
Ryder v. State Farm Mutual Automobile Insurance
187 N.W.2d 176 (Wisconsin Supreme Court, 1971)
La Velle v. De Luca
180 N.W.2d 710 (Wisconsin Supreme Court, 1970)
Employers Insurance of Wausau v. Sheedy
166 N.W.2d 220 (Wisconsin Supreme Court, 1969)
Tobler & Oliver Construction Co. v. Board of Trustees
442 P.2d 904 (Nevada Supreme Court, 1968)
Attoe v. State Farm Mutual Automobile Insurance
153 N.W.2d 575 (Wisconsin Supreme Court, 1967)
Bade v. Badger Mutual Insurance
142 N.W.2d 218 (Wisconsin Supreme Court, 1966)
Hanz Trucking, Inc. v. Harris Brothers Co.
138 N.W.2d 238 (Wisconsin Supreme Court, 1965)
Cordes v. Hoffman
120 N.W.2d 137 (Wisconsin Supreme Court, 1963)
Conditioned Air Corp. v. Rock Island Motor Transit Co.
114 N.W.2d 304 (Supreme Court of Iowa, 1962)
Strong v. Shawano Canning Co.
109 N.W.2d 355 (Wisconsin Supreme Court, 1961)
Davies v. J. D. Wilson Co.
85 N.W.2d 459 (Wisconsin Supreme Court, 1957)
Muth v. J. W. Speaker Corp.
151 F. Supp. 188 (E.D. Wisconsin, 1957)
Berger v. Alan Realty Co.
78 N.W.2d 747 (Wisconsin Supreme Court, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
64 N.W.2d 859, 267 Wis. 245, 1954 Wisc. LEXIS 280, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nolop-v-spettel-wis-1954.