Freeman & Co. v. Bolt

968 P.2d 247, 132 Idaho 152, 1998 Ida. App. LEXIS 87
CourtIdaho Court of Appeals
DecidedAugust 11, 1998
Docket23938
StatusPublished
Cited by3 cases

This text of 968 P.2d 247 (Freeman & Co. v. Bolt) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Freeman & Co. v. Bolt, 968 P.2d 247, 132 Idaho 152, 1998 Ida. App. LEXIS 87 (Idaho Ct. App. 1998).

Opinion

SCHWARTZMAN, Judge.

Bolt Construction Company (Bolt) appeals from the district court’s decision on a bench trial regarding disputes over a residence which Bolt built for Jack and Jennifer Kulm. The parties disagreed over how to properly calculate and prove “cost” for a “cost plus” contract and whether the charges levied for certain “extra” and “additional” work were correct. Each party prevailed on some of their respective claims, but the district court concluded that the Kulms were the overall prevailing party and awarded them a significant percentage of their attorney fees.

We affirm the decision of the district court, with one minor exception regarding a concession made by the Kulms.

I. FACTUAL BACKGROUND

In March of 1994, A1 Bolt (dba Bolt) entered into a written contract with Jack and Jennifer Kulm for the construction of a residence in rural Jerome County. The contract provided, in relevant part:

Bolt Construction hereby agrees to furnish all the material and perform all the labor necessary for the completion of:
[Home as per plans provided by the Kulms]
All material is guaranteed to be as specified, and the above work to be performed in accordance with the drawings and specifications submitted for above work and completed in a substantial workmanlike manner for the sum of:
Two Hundred Twenty Five Thousand Dollars ($225,000.00)
Any additional work required by owner shall be at cost plus 10% unless other arrangements are made prior to the start of such work. Any alteration or deviation from above specifications required by owner involving extra costs will become an extra charge over and above the estimate at the rate of cost plus 15%. Owner to carry fire, tornado, wind, storm and other necessary insurance upon above work. Workmen’s compensation and public liability insurance on above work to be taken out by Bolt Construction.

The residence was built, but many problems arose. The Kulms claimed that Bolt did not fulfill the terms of the contract: specifically, that Bolt did not properly perform some of the work, that problems were not cured, and that materials were improperly used.

Furthermore, the contract specified that “additional” work would be billed to the Kulms at “cost” plus 10 percent, and “extra” work would be billed at “cost” plus 15 percent. Nowhere in the contract are the terms “additional,” “éxtra,” and “cost” defined, and the parties never held any pre-contract discussion to define or clarify the meaning of these terms. The primary disagreement focused on how to define “cost,” that is, which items are properly chargeable by a general contractor in computing its “cost” for a “cost plus” contract.

There was also a claim regarding Freeman & Company, Inc., one of Bolt’s subcontractors who installed the dryvit system on the Kulms’ house. The Kulms allege that Bolt never fully paid Freeman, and that the Kulms are entitled to reimbursement from Bolt for money they paid to Freeman in settlement of the claim.

*155 Bolt, on the other hand, disputes many of the district court’s determinations regarding monetary compensation for specific jobs and alleges that the court erred in its disposition of Bolt’s claims regarding these numerous projects. Bolt also argues that the court erred in awarding the Kulms damages for various construction items on their counterclaim.

II. PROCEDURE

The case began with a complaint filed by Freeman, who brought an action for payment against both Bolt and Kulm as well as a hen against the Kulm property; the Kulms then filed a cross-claim against Bolt alleging that Bolt was responsible for holding them harmless for any damages resulting from Freeman’s mechanic’s lien. The Kulms withheld money from the contract price with Bolt based on credits to which the Kulms claimed they were entitled. Bolt then filed suit against the Kulms, and the Kulms counterclaimed. The Kulms further sought an offset for alleged defects in Bolt’s performance of the contract. Ultimately, the Freeman claim was settled and he was dropped from the case by agreement of the parties.

The trial was conducted in two phases. 1 The first phase of trial (which concerned mostly Bolt’s claims) began on June 27, 1996, and lasted two days. The district court then filed its “Order on Court Trial.” In response to the parties’ subsequent motions, the district court also issued an “Order on Motion to Reconsider and Amend Findings of Fact.”

The second phase of the trial began on December 11,1996, and also lasted two days. The court then filed an “Order on Second Phase of Court Trial: Findings of Fact, Conclusions of Law.” Again, in response to motions by the parties, the court issued an “Order on Motions for Reconsideration; Amend Findings of Fact, Conclusions of Law; and Amend Judgment on Phase II of Court Trial.” In all, the district court prepared four separate decisions, comprising 162 pages, each meticulously detailed, containing an exhaustive item by item analysis. The net result of this marathon litigation, after offsets and credits, left the Kulms with a $9,856.85 judgment, together with costs and 75 percent of their attorneys fees.

Bolt appealed and the Kulms filed a notice of cross-appeal.

III. DISCUSSION

A. The District Court Properly Determined Which Items Should Be Included In Calculating “Cost” Under A “Cost Plus” Contract

According to the terms of the contract, Bolt was entitled to charge the Kulms his “cost” plus 10 percent for “additional” work and “cost” plus 15 percent for “extra” work. Bolt computed an hourly rate to charge for any work done in accordance with these “cost plus” provisions. Bolt provided an itemized breakdown of direct and indirect costs which were all included in calculating how much to charge for each hour per worker as Bolt’s “cost.” For every hour worked by a laborer, foreman or welder, Bolt charged the following items to arrive at his “cost.” 2

Percentage Of Salary Charged As “Cost” Laborer

Wages - $10.00

1) Work. Comp. 26.41% $2.64

2) Liability Ins. 2.42% .42

3) Health Ins. 4.60% .46

*156 Percentage Of Salaiy Charged As “Cost” Laborer

4) PICA 6.20% .62

5) MEDICARE 1.45% .15

6) State Empl. Ins. 2.00% .20

7) FUTA .80% .20

8) Trucks 10.00% $1.00

9) Equipment 10.00% $1.00

10) General Operating 15.00% $1.50

11) Tools 5.00% .50

12) Repairs 5.00% .50

IS) Replacement_ 5.00% .50

Total 93.88% $19.39

Therefore, with regard to “additional” or “extra” work done by a laborer who was paid an hourly wage of $10.00, Bolt billed the Kulms $19.39 an hour, plus 10 percent or 15 percent, respectively.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Electrical Wholesale Supply Co. v. Nielson
41 P.3d 242 (Idaho Supreme Court, 2001)
Arthur v. Shoshone County
993 P.2d 617 (Idaho Court of Appeals, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
968 P.2d 247, 132 Idaho 152, 1998 Ida. App. LEXIS 87, Counsel Stack Legal Research, https://law.counselstack.com/opinion/freeman-co-v-bolt-idahoctapp-1998.