Olmstead Construction, Inc. v. Otter Creek Investments, LLC

CourtCourt of Appeals of Iowa
DecidedSeptember 25, 2019
Docket18-1186
StatusPublished

This text of Olmstead Construction, Inc. v. Otter Creek Investments, LLC (Olmstead Construction, Inc. v. Otter Creek Investments, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Olmstead Construction, Inc. v. Otter Creek Investments, LLC, (iowactapp 2019).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 18-1186 Filed September 25, 2019

OLMSTEAD CONSTRUCTION, INC., Plaintiff-Appellee/Cross-Appellant,

vs.

OTTER CREEK INVESTMENTS, LLC, Defendant-Appellant/Cross-Appellee. ________________________________________________________________

Appeal from the Iowa District Court for Linn County, Kevin McKeever,

Judge.

Olmstead Construction, Inc. and Otter Creek Investments, L.L.C. both

appeal following resolution of their contract dispute. AFFIRMED IN PART AND

REVERSED IN PART ON APPEAL; CONDITIONALLY AFFIRMED ON CROSS-

APPEAL; AND REMANDED.

Dana L. Oxley and Kevin J. Caster of Shuttleworth & Ingersoll, P.L.C.,

Cedar Rapids, for appellant Otter Creek Investments, LLC.

Jeffrey A. Stone and Chad D. Brakhahn of Simmons Perrine Moyer

Bergman PLC, Cedar Rapids, for appellee Olmstead Construction, Inc.

Heard by Doyle, P.J., Blane, S.J.* and Lloyd, S.J.*

*Senior judges assigned by order pursuant to Iowa Code section 602.9206 (2019). 2

DOYLE, Presiding Judge.

The parties to a dispute over a construction contract ask us to review the

district court’s determination of various contract terms that affect the damages,

attorney fees, and interest awarded in a breach-of-contract claim. We must also

determine whether the district court erred by refusing to foreclose on a mechanic’s

lien.

We affirm the judgment entered in favor of Olmstead Construction, Inc.

(Olmstead Construction) on its breach-of-contract claim but reverse the awards of

$48,150 in damages for electrical costs and $47,787.73 in attorney fees. We

conditionally affirm the denial of Olmstead Construction’s petition to foreclose on

its mechanic’s lien and affirm the district court in all other respects. We remand

the case for further proceedings in conformance with this opinion.

I. Background Facts and Proceedings.

Brothers Don and Joe Burd decided to open a convenience store and gas

station in Robins and formed Otter Creek Investments, LLC (Otter Creek) for that

purpose. Otter Creek hired Olmstead Construction to build the store. In May 2014,

the parties entered a cost-plus contract, which requires the owner to pay the

contractor for construction costs plus a percentage markup. Otter Creek agreed

to reimburse Olmstead Construction for its construction costs and pay a seven-

percent markup on those costs. The contract also required Olmstead Construction

to act as the project manager, which entailed obtaining subcontractor bids,

supervising their subcontractor work, and processing and paying subcontractor

invoices. Olmstead Construction would then bill Otter Creek for the subcontractor

costs plus the seven-percent markup on those costs. 3

In July 2014, Olmstead Construction provided Otter Creek an initial estimate

of the total cost of construction, which it projected to be $1,204,774. Construction

began. During 2014, Olmstead Construction billed Otter Creek for work totaling

$81,093.16. Otter Creek paid Olmstead Construction this amount in December

2014.

By the end of the year, Otter Creek realized it needed to scale back the cost

of the project due to financing issues. As a result, it redesigned the construction

plans between December 2014 and May 2015 with Olmstead Construction’s help.

Based on Otter Creek’s changes to the plans, Olmstead Construction submitted a

revised estimate of the total cost of construction on April 5, 2015, which it projected

to be $962,535. Two days later, Olmstead Construction submitted a new estimate,

this time projecting a total cost of $948,132.

One way in which Otter Creek tried to reduce the cost of the project was to

contract directly with some subcontractors, eliminating the seven-percent markup

Olmstead Construction would otherwise receive for that subcontracted work. One

subcontractor Otter Creek opted to contract with directly was Streff Electric, the

electrical subcontractor. The parties agreed that Otter Creek would pay Streff

Electric directly for the portion of the electrical work running to the gas pumps while

Olmstead Construction would oversee the work Streff Electric performed inside the

store. Olmstead Construction’s revised estimates reflect this change.1

Olmstead Construction received invoices from the subcontractors it

supervised, while those contracting directly with Otter Creek submitted invoices to

1 The revised estimates include a line for electrical work but list it as “Electrical (No electrical at Gas Pumps).” 4

Don Burd. Daniel Olmstead, the owner and president of Olmstead Construction,

testified, “We pay strictly off whatever invoices are sent to us.” So when Olmstead

Construction received invoices from Streff Electric for work on the gas pumps,

Daniel Olmstead assumed Otter Creek was adding that expense back into their

contract despite Otter Creek’s silence on the matter. Because it received the

invoice, Olmstead Construction paid Streff Electric for that work and added the

expense to its invoice to Otter Creek. Unbeknown to Olmstead Construction, Otter

Creek also paid Streff Electric for the electrical work on the gas pumps.

During 2015, Olmstead Construction billed Otter Creek for work totaling

$778,432.84 in 2015. Don Burd noted some items listed as completed in an

October 2015 invoice were for work that had not yet begun and asked for

documentation of the costs. He never received the requested documentation.

When Olmstead Construction sent a new invoice in December without

documentation, Don Burd again asked for documents to verify the costs. Although

Olmstead Construction never provided documentation, Otter Creek paid the total

amount due in December 2015.

In February 2016, Olmstead Construction sent Otter Creek three invoices

listing different amounts owed. An invoice dated February 9 shows a total project

cost of $999,850 and an amount due of $102,930.84. An invoice dated February

12 shows a total project cost of $962,535 and an amount due of $102,928. Another

invoice dated February 12 also shows a total project cost of $962,535 but an

amount due of $35,483.16. When Otter Creek asked about the invoices, Olmstead

Construction stated it had revised the invoices and would invoice for “extras” later. 5

Olmstead Construction sent a final invoice to Otter Creek on March 22,

2016. That invoice shows a total project cost of $1,058,869.82 and an amount due

of $199,343.82. Confused about what the additional charges were for, Don Burd

decided to wait to pay it until Olmstead Construction provided explanation or

documentation of the costs. Olmstead Construction informed Otter Creek that it

would file a mechanic’s lien if Otter Creek failed to pay the invoice within thirty

days. Olmstead Construction filed a mechanic’s lien on April 12, 2016.

In June 2016, Olmstead Construction petitioned to foreclose the mechanic’s

lien for the remaining $199,343.82. Otter Creek counterclaimed for breach of

contract and defective construction. Olmstead Construction amended its petition

to add a claim for breach of contract, seeking prejudgment interest and attorney

fees.

Following a bench trial, the district court found Olmstead Construction

proved its breach-of-contract claim. It entered a $217,121.19 judgment for

Olmstead Construction, which included $48,150 in damages attributable to work

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sherwood Distilling Co. v. Ryan, Director
190 F.2d 314 (Emergency Court of Appeals, 1951)
Arc Electric Co. v. Esslinger-Lefler, Inc.
591 P.2d 989 (Court of Appeals of Arizona, 1979)
Brenton National Bank of Des Moines v. Ross
492 N.W.2d 441 (Court of Appeals of Iowa, 1992)
Westhoff v. American Interinsurance Exchange
250 N.W.2d 404 (Supreme Court of Iowa, 1977)
Olberding Const. Co., Inc. v. Ruden
243 N.W.2d 872 (Supreme Court of Iowa, 1976)
Freeman & Co. v. Bolt
968 P.2d 247 (Idaho Court of Appeals, 1998)
Hosteng Concrete & Gravel, Inc. v. Tullar
524 N.W.2d 445 (Court of Appeals of Iowa, 1994)
Bidwell v. Midwest Solariums, Inc.
543 N.W.2d 293 (Court of Appeals of Iowa, 1995)
M. Carbine Restoration, Ltd. v. Sutherlin
544 So. 2d 455 (Louisiana Court of Appeal, 1989)
Capitol City Drywall Corp. v. C. G. Smith Construction Co.
270 N.W.2d 608 (Supreme Court of Iowa, 1978)
Joe Bonura, Inc. v. Hiern
419 So. 2d 25 (Louisiana Court of Appeal, 1982)
Tindell v. Apple Lines, Inc.
478 N.W.2d 428 (Court of Appeals of Iowa, 1991)
Shaw v. Bula Cannon Shops, Inc.
38 So. 2d 916 (Mississippi Supreme Court, 1949)
Iowa Arboretum, Inc. v. Iowa 4-H Foundation
886 N.W.2d 695 (Supreme Court of Iowa, 2016)
Michelle Postell v. American Family Mutual Insurance Co.
823 N.W.2d 35 (Supreme Court of Iowa, 2012)
Flynn Builders, L.C. v. Matthew P. Lande and Chris Lande
814 N.W.2d 542 (Supreme Court of Iowa, 2012)
Winger Contracting Company v. Cargill, Incorporated
926 N.W.2d 526 (Supreme Court of Iowa, 2019)
Hitt v. Smallwood
133 S.E. 503 (Court of Appeals of Virginia, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
Olmstead Construction, Inc. v. Otter Creek Investments, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/olmstead-construction-inc-v-otter-creek-investments-llc-iowactapp-2019.