Bidwell v. Midwest Solariums, Inc.

543 N.W.2d 293, 1995 Iowa App. LEXIS 143, 1995 WL 790832
CourtCourt of Appeals of Iowa
DecidedNovember 27, 1995
Docket94-1932
StatusPublished
Cited by4 cases

This text of 543 N.W.2d 293 (Bidwell v. Midwest Solariums, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bidwell v. Midwest Solariums, Inc., 543 N.W.2d 293, 1995 Iowa App. LEXIS 143, 1995 WL 790832 (iowactapp 1995).

Opinion

HABHAB, Judge.

Plaintiff Fern Bidwell (Bidwell) contracted with defendant Midwest Solariums, Inc. for the construction of a sunroom onto her house *295 for $18,948. According to the terms of the contract, Bidwell was to pay ten percent of the contract price upon acceptance of the proposal ($1894.80), forty percent within ten days of acceptance ($7579.20), thirty percent upon delivery of the unit ($5684.40), fifteen percent upon completion ($2842.20), and five percent upon completion of electrical ($947.40). After the construction started, Bidwell complained the walls of the sunroom were too high, leaving insufficient window area. She claimed the constructed sunroom was not the four-season sunroom she agreed to have Midwest build.

After the sunroom was completed, Bidwell claimed the sunroom was too cold to use in the winter. Midwest claims this problem could be corrected by baseboard heating and a booster fan for a cost of $400. Bidwell claims her use of space heaters was not adequate to heat the sunroom. Bidwell introduced evidence the heating problem could be corrected by the replacement of the metal windows with wooden-frame windows at a cost of $4050. Midwest contends there was no foundation for this evidence.

Bidwell paid all but $3790.20. Midwest filed a mechanic’s lien. Bidwell brought this suit. 1 Midwest counterclaimed seeking foreclosure of its mechanic’s lien.

The case proceeded to trial. On September 22, 1994, the district court granted Bid-well damages for breach of contract. The court determined the measure of damages should be the cost of replacing the window’s metal frames with wooden frames which would not conduct the cold. The court determined the replacement cost to be $4050 and awarded this amount. In this respect, the court in its findings stated:

Plaintiffs testimony establishes new windows could be placed in the sunroom at a cost of $4050. Plaintiffs witnesses testified that the windows should be replaced with wooden-frame windows which do not conduct the cold like metal-frame windows. The district court refused to foreclose on

Midwest’s mechanic’s lien on the basis Midwest did not establish it substantially performed the contractual terms. It dismissed Midwest’s counterclaim.

Midwest appeals. Bidwell cross-appeals.

I. Mechanic’s Lien. Midwest contends the district court erred in denying its counterclaim for foreclosure of its mechanic’s lien. An action to enforce a mechanic’s lien is in equity and our review is de novo. Iowa Code § 572.26 (1993); Sulzberger Excavating, Inc. v. Glass, 351 N.W.2d 188, 191 (Iowa App.1984). Weight will be given to the findings of fact and credibility determinations of the district court, especially in mechanic’s lien eases. Giese Constr. Co. v. Randa, 524 N.W.2d 427 (Iowa App.1994).

In order to successfully enforce a mechanic’s lien, substantial performance of the contract is required. See Moore’s Builder & Contractor, Inc. v. Hoffman, 409 N.W.2d 191, 193 (Iowa App.1987); 53 Am. Jur.2d Mechanics’ Liens § 51, at 563 (1970) (“A contractor cannot successfully assert a mechanic’s lien upon the property where there has been only part performance or a lack of substantial performance of the contract.”).

Substantial performance allows only the omissions or deviations from the contract that are inadvertent or unintentional, not the result of bad faith, do not impair the structure as a whole, are remedial without doing material damages to other portions of the building, and may be compensated for through deductions from the contract price.

Moore’s Builder, 409 N.W.2d at 193.

In deciding the mechanic’s lien could not be enforced in the counterclaim, the district court stated there was not substantial performance due to the breach of the contract and the breach of the implied warranty of fitness for a particular purpose. Specifically, the court found the four-season sun-room as constructed by Midwest was too cold to be used in the winter.

*296 Upon our de novo review of the evidence, we find the district court’s characterization of the performance by Midwest to be incorrect. We do not believe the breach relied upon by the district court rises to the level of the omissions or deviations defined in Moore’s Builder. We find there was substantial performance, 2 and the omission or deviation is one which was not the result of bad faith. In addition, the defect is of the type that can be compensated for, either through a reduction in the contract price or the awarding of a judgment (as the trial court did) to enable Bidwell to correct the defect.

Under the circumstances here, the balance due Midwest on its contract must be accounted for. As explained under division II, Bid-well is entitled to judgment of $4050. With the awarding of that amount, Bidwell is made whole and, subject to the reduction explained later, Midwest is entitled to judgment against Bidwell for the balance due on the contract of $3790.

II. Damages. We turn next to Bid-well’s claim of damages. Even though there is substantial performance on the part of Midwest, this is not a complete discharge of Midwest’s promissory duty. In Moore’s Builder, we approved the following from Cor-bin on Contracts:

When we use the term “substantial performance of a promissory duty,” we always mean something less than full and exact performance of that duty. As so used, therefore, substantial performance is not a complete discharge of duty. It is not a defense in a suit against the building contractor for damages. Judgment will not be prevented from going against him in such a suit by his averring and proving that he performed almost in full, that his deviations have been small, that the owner can live comfortably in the house, or that the value to the owner is very nearly as great as it would have been had exact performance been rendered. [Emphasis supplied.]

Moore’s Builder, 409 N.W.2d at 195 (quoting A.L. Corbin, 3A Corbin on Contracts § 702 (2d ed. 1960)). Thus, Bidwell is still entitled to seek damages and, as set forth above, judgment will not be prevented by mere proof on the part of Midwest that it “performed almost in full.”

Midwest contends the district court erred in calculating the damages awarded to Bidwell. We review for corrections of errors of law. Iowa R.App.P. 4; R.E.T. Corp. v. Frank Paxton Co., 329 N.W.2d 416, 418-19 (Iowa 1983).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
543 N.W.2d 293, 1995 Iowa App. LEXIS 143, 1995 WL 790832, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bidwell-v-midwest-solariums-inc-iowactapp-1995.