Moore's Builder & Contractor, Inc. v. Hoffman

409 N.W.2d 191, 1987 Iowa App. LEXIS 1573
CourtCourt of Appeals of Iowa
DecidedMay 28, 1987
Docket85-1685
StatusPublished
Cited by7 cases

This text of 409 N.W.2d 191 (Moore's Builder & Contractor, Inc. v. Hoffman) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moore's Builder & Contractor, Inc. v. Hoffman, 409 N.W.2d 191, 1987 Iowa App. LEXIS 1573 (iowactapp 1987).

Opinion

*193 HAYDEN, Judge.

Plaintiff, Moore’s Builder and Contractor, Inc., contracted with defendant, Elizabeth Hoffman, to perform extensive remodeling on her home in Oelwein, Iowa. The written contract provided for a total price of $41,840, to be paid as follows: $2,000 when the contract was signed; $7,500 when the doors and windows arrived; $9,000 when construction began; $16,000 when the roof was finished on the addition; $5,000 when the addition was drywalled, and the balance upon completion. Plaintiff's president, Dennis F. Moore, began work on defendant’s house in July of 1982. During the initial stages of construction defendant remained in Oelwein and monitored the construction. In the middle of August she left for California to prepare for her move to Iowa. Defendant made the first four payments, totalling $34,500, but did not make the fifth scheduled payment. Mr. Moore drywalled the addition in the first part of September; as provided by the written contract he requested defendant make her fifth payment of $5,000. Payment was not received, but Mr. Moore was notified by defendant that she would be returning to Iowa at the end of the month. Upon her return defendant inspected the house with Mr. Moore and made clear her numerous complaints. Mr. Moore told her no further work would be completed until the amount due was paid and proceeded to walk off the job. On October 8,1982, Mr. Moore, acting as plaintiff’s representative, filed a mechanic’s lien against defendant.

On October 26, 1982, plaintiff commenced an action to foreclose on its mechanic’s lien. Defendant answered on November 19, 1982, and amended her answer on October 28,1983, therein adding a counterclaim. A month later defendant filed a jury demand. Both parties conducted extensive discovery involving interrogatories, depositions, and the production of various documents. Finally, on July 26, 1985, this matter proceeded to trial. In this proceeding the mechanic’s lien was submitted to the court sitting in equity and the counterclaim was tried to the jury. The jury returned a verdict in favor of Moore’s Builder and Contractor, Inc., and on August 23, 1985, the trial court entered an order foreclosing the mechanic’s lien against defendant. From this judgment defendant has appealed.

Defendant contends the district court erred by concluding substantial compliance would entitle the builder to the entire balance of the contract price. Defendant also contends the court erred by instructing the jury that substantial compliance by the builder would bar counterclaims based upon breach of express warranties or implied warranties of fitness. Finally, defendant contends the district court abused its discretion by refusing to let her take a deposition to perpetuate the testimony of a potential witness who had moved out of state.

I.

Defendant argues the court did not correctly apply the law and as a result the plaintiff was only entitled to the contract price, minus any deductions for any defects in performance.

An action to enforce a mechanic’s lien is an equitable proceeding. Iowa Code § 672.26 (1985). Our review of the equity portion of this proceeding is de novo. Iowa R.App,P. 4. While we give weight to the findings of the trial court, especially where credibility of witnesses is involved, we are not bound by them. Iowa R,App.P. 14(f)(7).

Initially defendant makes a brief argument that there was not substantial compliance by plaintiff to the provisions of the original contract. Substantial performance allows only the omissions or deviations from the contract that are inadvertent or unintentional, not the result of bad faith, do not impair the structure as a whole, are remedial without doing material damages to other portions of the building, and may be compensated for through deductions from the contract price. Littell v. Webster County, 152 Iowa 206, 215, 131 N.W. 691, 694 (1911). From the evidence presented in the record, we find that any omission plaintiff made was minor, and plaintiff did sub *194 stantially comply with the original construction contract.

Defendant next contends the trial court applied the wrong legal principle in making its equitable decision. Both parties agree upon the rule, “when the contractor has substantially complied with his contract he is entitled to recover the contract price with deductions for any defects or incompletions.” S. Hanson Lumber Company v. DeMoss, 253 Iowa 204, 208, 111 N.W.2d 681, 684 (1961) (citing Farrington v. Freeman, 251 Iowa 18, 23, 99 N.W.2d 388, 391 (1959)). We also note the burden of proof regarding the performance of the contract rested on the plaintiff. Farring-ton, 251 Iowa at 24, 111 N.W.2d at 391. Although the burden of proof regarding the showing of substantial performance rests with plaintiff-contractor, the defendant-homeowner has the burden of showing any defects or incompletions. A.L. Corbin, 3A Corbin on Contracts § 710 (2d ed. I960); S. Williston, 6 Williston on Contracts, § 842 (3d. ed. 1962). Defendant contends the court allowed payment for work that was defective and incomplete. We disagree.

As already mentioned, plaintiff substantially complied with the construction contract. Therefore we need only consider whether the trial court made deductions from the contract for any defective or incomplete work, and what deductions were, in fact, needed. In its judgment on the mechanic’s lien the trial court awarded plaintiff the sum of $8,109.71. The court arrived at this amount by taking the remainder due on the contract price, plus the extras provided, and subtracting the unfinished work. The trial court accepted and used the figures provided by the plaintiff regarding both the extra work done and the work not completed. After a careful and thorough review of the record, we find the trial court’s reliance upon these figures reasonable and accept them ourselves. Defendant signed a construction contract in which she promised to pay plaintiff $41,840 for the completion of the project. Defendant approved the plans for the addition and remodeling. Plaintiff did the extra work which defendant requested; this work totaled $1,410.82. Plaintiff admitted to the court that on September 27, 1982, certain work was not completed. This work involved the installation of bathroom plumbing, a heating register, and a light fixture. Plaintiff valued the work needed to be completed at $645.11. Defendant contends the court did not correctly deduct from its judgment the defective work performed by plaintiff. Plaintiff substantially performed the contract. Regarding the mechanic’s lien, defendant failed her burden of showing any defects beyond those found by the court. Defendant obviously had some complaints about the work done and, although the work may not have met her satisfaction, it doesn’t make it legally defective.

II.

Defendant contends the trial court incorrectly instructed the jury. Specifically she contends the court erred in the instruction that substantial performance by the contractor bars her from recovery on either an implied warranty of fitness or breach of express warranty.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
409 N.W.2d 191, 1987 Iowa App. LEXIS 1573, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moores-builder-contractor-inc-v-hoffman-iowactapp-1987.