Nepstad Custom Homes Co. v. Krull

527 N.W.2d 402, 1994 Iowa App. LEXIS 146, 1994 WL 750710
CourtCourt of Appeals of Iowa
DecidedNovember 28, 1994
Docket93-266
StatusPublished
Cited by21 cases

This text of 527 N.W.2d 402 (Nepstad Custom Homes Co. v. Krull) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nepstad Custom Homes Co. v. Krull, 527 N.W.2d 402, 1994 Iowa App. LEXIS 146, 1994 WL 750710 (iowactapp 1994).

Opinion

HUITINK, Judge.

Nepstad Custom Homes Company brought this mechanic’s lien foreclosure action against Curtis and Chris Krull for amounts due for *404 the construction of a home. First Interstate Bank provided the financing and now holds a mortgage on the home. The defendants counterclaimed for fraudulent misrepresentation and breach of contract, eventually dismissing the misrepresentation claim. The matter proceeded to a bench trial.

The Krulls entered into a contract with Nepstad for the construction of a home in West Des Moines. At the time the parties entered into the contract, Nepstad and its president, Gregory Nepstad, utilized Curtis Krull for legal representation. Curtis Krull represented Nepstad in a separate mechanic’s lien foreclosure action and Gregory Nep-stad in a dissolution action.

Prior to signing the contract, Nepstad provided the Krulls with a budget sheet and description of materials. The parties eventually agreed upon a price of $190,000 and this was the figure First Interstate utilized to set the construction loan amount.

Nepstad began construction of the house in August 1990. However, a dispute arose over the proper elevation of the foundation. After Nepstad built the foundation and began framing the home, the Krulls insisted that the foundation be lowered in order to reduce the slope of the driveway and front yard. This necessitated tearing out the old foundation and the framing which had been done. Nepstad then built the foundation as the Krulls requested.

On December 4, 1990, the parties entered into a contract for the apportionment of the costs associated with redoing the foundation. The second budget sheet reflected a new price of $195,045.50. Nepstad claims both it and the Krulls agreed to contribute $5,000. The Krulls claim Nepstad agreed to contribute $5,000 and cover the remainder of the replacement costs by reducing its profit.

After the completion of the second foundation, more disputes arose between the parties. Before, the framing was completed, the Krulls fired one carpenter for being too slow. The Krulls also claim they were unable to contact Gregory Nepstad during construction. Eventually construction was sufficiently completed to allow the Krulls to move into the home. The Krulls claim that at the time they moved in the home was eighty to eight-two percent complete. Nepstad claims the home was ninety-five percent complete.

The Krulls then learned the cost of the home had gone over the second budget price of $195,045.50. A dispute arose concerning who should be responsible for the cost overruns. The Krulls refused to make final payments to Nepstad, and Nepstad refused to complete the home until payment was made. The Krulls finished the construction themselves.

Nepstad then filed a mechanics lien and a subsequent foreclosure action against the Krulls. Nepstad also claimed First Interstate’s mortgage was junior to its lien interest. The defendants filed a counterclaim asserting breach of contract based on defects in the construction of the house. They claimed Nepstad failed to perform in a reasonably good and workmanlike manner. Several of the subcontractors also filed mechanic’s lien foreclosures. The Krulls settled with these subcontractors prior to trial.

The trial court dismissed Nepstad’s petition for foreclosure. Nepstad claimed the parties had entered into a cost-plus contract, which is a contract for the cost of the materials and labor plus a given percentage, here five percent. The court determined that Nepstad and the Krulls had entered into a fixed-price contract and not a cost-plus contract. The court held for the Krulls on their claim of breach of contract due to defects in construction. Nepstad was ordered to pay the cost oveiTuns during construction, which were $12,645.59. It was also ordered to pay the costs of repairing defects in the home, which were $6,535. Thus, in total the Krulls were awarded damages of $19,180.59. Nep-stad appeals.

I. An action to enforce a mechanic’s lien is in equity. Sulzberger Excavating, Inc. v. Glass, 351 N.W.2d 188, 191 (Iowa App.1984). Consequently, review is de novo. Iowa R.App.P. 4. In mechanic’s lien eases, involving as they do numerous charges and counter charges which depend entirely on the credibility of the parties, we have frequently held the trial court is in a more advantageous position than we to put credence where it *405 belongs. McDonald v. Welch, 176 N.W.2d 846, 849 (Iowa 1970).

We note that in Sulzberger, the defendant raised a counterclaim based on failure to perform work in a workmanlike manner, which is similar to the counterclaim raised in the present case. Sulzberger, 351 N.W.2d at 191. We there reviewed the entire case de novo on appeal. Id. However, in another mechanic’s lien case, Moore’s Builder & Contractor, Inc. v. Hoffman, a counterclaim of breach of warranty was separately tried as a law action by the trial court, and our review of the counterclaim was on assigned error of law. Moore’s Builder, 409 N.W.2d 191, 194 (Iowa App.1987).

Our scope of review is determined by the nature of the trial proceedings. Iowa Fuel & Minerals, Inc. v. Iowa State Bd. of Regents, 471 N.W.2d 859, 862 (Iowa 1991). Here, all issues were tried together before the court. We conclude the entire case was tried in equity and our review of this action, including the issues on the counterclaim, should be reviewed de novo.

II. Nepstad contends the construction contract for building the house was a cost-plus contract, not a fixed-price contract. As part of this argument, it claims the contract should be interpreted so that any dispute should be resolved in its favor because there was a confidential and fiduciary relationship between Curtis Krull and Nepstad Custom Homes. Curtis Krull is an attorney. At the time the present contract was entered into, Curtis Krull was representing plaintiff in another action and was representing Gregory Nepstad personally.

Nepstad admits the district court did not address this issue. Issues must ordinarily be presented to and passed upon by the trial court before they can be raised and decided on appeal. Johnston Equip. Corp. v. Industrial Indemnity, 489 N.W.2d 13, 16 (Iowa 1992) (citing State Farm Mut. Ins. Co. v. Pflibsen, 350 N.W.2d 202, 207 (Iowa 1984)). A rule 179(b) motion to enlarge or amend is necessary for preservation of error when a trial court fails to resolve a matter properly submitted. Id. at 17. Nepstad did not file a rule 179(b) motion seeking to obtain a ruling from the district court on its claim of a confidential and fiduciary relationship.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marvin Swan v. Robert Lee Jackson
Court of Appeals of Iowa, 2021
Flynn Builders, L.C. v. Matthew P. Lande and Chris Lande
814 N.W.2d 542 (Supreme Court of Iowa, 2012)
Baker v. Catlin Specialty Insurance
769 F. Supp. 2d 1157 (N.D. Iowa, 2011)
Schmidt v. Fortis Insurance
349 F. Supp. 2d 1171 (N.D. Iowa, 2005)
In Re Hassel
600 N.W.2d 335 (Court of Appeals of Iowa, 1999)
L & L Builders Co. v. Mayer Associated Services, Inc.
46 F. Supp. 2d 875 (N.D. Iowa, 1999)
Advance Elevator Co. v. Four State Supply Co.
572 N.W.2d 186 (Court of Appeals of Iowa, 1997)
Coulter v. Cigna Property & Casualty Companies
934 F. Supp. 1101 (N.D. Iowa, 1996)
Service Unlimited, Inc. v. Elder
542 N.W.2d 855 (Court of Appeals of Iowa, 1995)
Utica Mutual Insurance v. Stockdale Agency
892 F. Supp. 1179 (N.D. Iowa, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
527 N.W.2d 402, 1994 Iowa App. LEXIS 146, 1994 WL 750710, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nepstad-custom-homes-co-v-krull-iowactapp-1994.