L & L Builders Co. v. Mayer Associated Services, Inc.

46 F. Supp. 2d 875, 1999 U.S. Dist. LEXIS 4490, 1999 WL 190230
District Court, N.D. Iowa·Decided April 5, 1999·No. C 97-4034-MWB·Published·Cited by 7 cases

Opinion

MEMORANDUM OPINION AND ORDER REGARDING CROSS-MOTIONS FOR SUMMARY JUDGMENT

BENNETT, District Judge.

TABLE OF CONTENTS

I. INTRODUCTION.877

A. Factual Background.877

B. Procedural Background.878

II. LEGAL ANALYSIS.880

A. Standards For Summarg Judgment.880

B. Which State’s Law Applies? .881

1. The appropriate test.881

2. Application of the test... 882

C. Cummins South’s Coverage Under The Surety Bond.883

1. Rules of contract construction and interpretation .884

2. Ambiguity.886

3. Consideration.887

D. Estoppel.888

1. Elements of equitable estoppel.888

2. Genuine issues of material fact.889

E. Waiver.891
III.CONCLUSION.892

Anyone who is foolish enough to think that life is fair should consider the plight of the parties in this litigation. The plaintiff general contractor asserts that it’s just not fair that it should be called upon to pay a materialman for certain equipment, when it has already paid a subcontractor once for that same equipment, and before doing so, received what it took to be assurances that the materialman had already been paid. The materialman counters that it’s just not fair that it has never been paid in full by anyone for the equipment it supplied to the subcontractor, even though it received what it took to be assurances that it would have coverage under the general contractor’s surety bond before shipping the equipment to the subcontractor. The materialman and general contractor seem to agree that it’s not fair that the subcontractor received payment specifically earmarked for the equipment in question, but the money was never passed on to the materialman. However, these disappointed parties disagree on who should now bear the cost of the subcontractor’s defalcation, and they present that question to the court on cross-motions for summary judgment.

I. INTRODUCTION
A. Factual Background

Although this matter is before the court on cross-motions for summary judgment, the court will not attempt here an exhaustive recitation of undisputed and disputed facts. Rather, the court will provide here *878 only a survey of the facts and factual disputes necessary to frame the discussion to follow. In its legal analysis, the court will, where necessary, consider which pertinent facts are undisputed and which are genuinely in dispute.

Plaintiff L & L Builders Company was the general contractor for a construction project on' land owned by the Winnebago Tribe near Sloan, Iowa. The project was known as the Winnavegas Casino Expansion, Phase I Bingo Hall. Defendant Mayer Associated Services, Inc., was a subcontractor for that project, employed to perform electrical work and to install certain equipment, including a diesel generator. Defendant Cummins South, Inc., was a materialman that supplied the diesel generator and an automatic transfer switch to Mayer for installation on the project.

Cummins South contends that it only agreed to provide Mayer with the diesel generator and automatic transfer switch without payment in advance after receiving assurances that it was covered by L & L’s payment and performance bond for the project. When Mayer sought payment from L & L to cover its payment to Cum-mins South, Mayer agreed to provide L & L with a lien waiver from Cummins South as soon as Mayer received payment from L & L. L & L contends that it is the custom and practice in the industry to give lien waivers only after payment is received, and that it relied upon this custom and practice in making payment to Mayer. Therefore, on January 14, 1997, L & L sent Mayer a check for $197,406, which was to cover payment due Cummins South. It was L & L’s understanding of the agreement with Mayer that if L & L did not receive a lien waiver from Cummins South by the next day, it would stop payment on the check. L & L then received by facsimile a lien waiver from Cummins South dated January 15, 1997. However, Mayer apparently deposited the funds from L & L, and has never paid Cummins South in full. Cummins South subsequently filed an “Affidavit of Non-Payment,” and demanded payment from United Fire & Casualty Company, L & L’s surety for the construction project. United Fire in turn made demand on L & L for exoneration.

The following chart may be of assistance in understanding the facts just described:

[[Image here]]

B. Procedural Background

Two separate lawsuits have their genesis in the question of who should pay Cum-mins South the outstanding amount due for the equipment it supplied to Mayer. On April 7, 1997, Cummins South brought an action in the Iowa District Court for Linn County against Mayer and United *879 Fire seeking payment either from Mayer or against the bond for the project. Cum-mins South did not name L & L in its lawsuit. Approximately two weeks later, on April 18, 1997, L & L brought the present action against Mayer and Cum-mins South in this federal court for inter-pleader and declaratory judgment. In the present lawsuit, L & L seeks declarations that neither of the defendants is entitled to recover from L & L any sums due Cum-mins South; that Cummins South’s sole recourse is against Mayer as to sums that may be due Cummins South from Mayer and that Cummins South has no recourse against L & L or any bond posted by L & L; that if L & L is indebted to Cummins South or Cummins South has any rights under the bond posted by L & L, L & L is entitled to judgment against Mayer, not dischargeable under 11 U.S.C. § 523, for the amount due Cummins South plus costs and attorney’s fees; and that if L & L is indebted to Cummins South or Cummins South has any rights under the bond posted by L & L, L & L should be authorized to pay Cummins South directly any sums L & L owes Mayer.

Free access — add to your briefcase to read the full text and ask questions with AI

L & L Builders Co. v. Mayer Associated Services, Inc., 46 F. Supp. 2d 875, 1999 U.S. Dist. LEXIS 4490, 1999 WL 190230 (N.D. Iowa 1999).

46 F. Supp. 2d 875 (L & L Builders Co. v. Mayer Associated Services, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Stults v. Symrise, Inc.
989 F. Supp. 2d 735 (N.D. Iowa, 2013)
ESTATE OF PIGORSCH v. York College
734 F. Supp. 2d 704 (N.D. Iowa, 2010)
Johnson v. American Leather Specialties Corp.
578 F. Supp. 2d 1154 (N.D. Iowa, 2008)
Jones Ex Rel. Jones v. Winnebago Industries, Inc.
460 F. Supp. 2d 953 (N.D. Iowa, 2006)
Sioux Biochemical, Inc. v. Cargill, Inc.
410 F. Supp. 2d 785 (N.D. Iowa, 2005)
Webster Industries, Inc. v. Northwood Doors, Inc.
320 F. Supp. 2d 821 (N.D. Iowa, 2004)
Helm Financial Corp. v. Iowa Northern Railway Co.
214 F. Supp. 2d 934 (N.D. Iowa, 2002)