Power Engineering & Manufacturing, Ltd. v. Krug International

501 N.W.2d 490, 23 U.C.C. Rep. Serv. 2d (West) 382, 1993 Iowa Sup. LEXIS 157, 1993 WL 208816
CourtSupreme Court of Iowa
DecidedJune 16, 1993
Docket91-1737
StatusPublished
Cited by10 cases

This text of 501 N.W.2d 490 (Power Engineering & Manufacturing, Ltd. v. Krug International) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Power Engineering & Manufacturing, Ltd. v. Krug International, 501 N.W.2d 490, 23 U.C.C. Rep. Serv. 2d (West) 382, 1993 Iowa Sup. LEXIS 157, 1993 WL 208816 (iowa 1993).

Opinion

HARRIS, Justice.

An Iowa manufacturer contracted to design and supply special equipment for a corporation doing business in Ohio. Although the Iowa manufacturer was unaware of it, the equipment was to be sold to an entity in Iraq. As a result of hostilities between that nation and ours, an embargo was declared and enforced, prohibiting trade with the entity in Iraq. The question in this suit is which of the two corporations must bear the loss. The trial court determined that it is the responsibility of the corporation in Ohio, not the Iowa corporation. We agree.

The dispute is between Power Engineering & Manufacturing, Ltd. (Power Engineering) and Krug International (Krug). Power Engineering is an Iowa corporation engaged in the business of engineering and manufacturing heavy-duty gear boxes and transmissions. Its principal place of busi *492 ness is in Waterloo. Krug is a non-Iowa corporation that manufactures and supplies equipment. Its principal place of business is in Dayton, Ohio. Power Engineering brought this action against Krug for breach of contract, seeking money damages.

The contract arose from a commercial relationship between Tripod Laing, an international joint venture, and Iraqi Airways. Tripod Laing was to deliver to Iraqi Airways, in Iraq, an aeromedical equipment laboratory, one part of which was to be a human centrifuge, equipment used to train jet pilots. Tripod Laing contracted with Krug International (U.K.), Ltd., a subsidiary of Krug, to build the aeromedical equipment laboratory. The Krug subsidiary then contracted with Krug to build the centrifuge. Krug in turn contracted with Power Engineering to build a gear box to be used as a part of the centrifuge. Power Engineering did not know the identity of Krug’s buyer or the identity of the ultimate consumer until it received a stop work order in August of 1990.

The relationship between Krug and Power Engineering was established through both oral negotiation and an exchange of written forms: a meeting in early March 1990; Power Engineering’s “QUOTATION,” dated March 14; Krug’s “PURCHASE ORDER,” dated March 16; and Power Engineering's “PURCHASE ORDER ACKNOWLEDGMENT,” dated April 26. Power Engineering began manufacturing the gear box shortly after receiving the purchase order.

There never was a clear meeting of minds on whether the order was subject to cancellation. Throughout the transaction the parties somewhat casually communicated divergent positions on written forms. Power Engineering’s quotation stated “ONLY NON-CANCELLABLE ORDERS ACCEPTED.” Power Engineering’s purchase order acknowledgment contains similar language. Power Engineering nevertheless concedes:

There had been discussions, however, during a meeting between the parties in the first week of March, wherein Krug had expressed the desire to be able to cancel the order if necessary and pay for what work had been completed as of the cancellation date. Power Engineering had agreed to do so thus overriding the printed language of the form.

The purchase order states on its front, “KRUG has the right to cancel this order at any time and will pay for only work completed.” Power Engineering points out that this “language was consistent with the verbal understanding of the parties [concerning] the amount of damages to which Power Engineering would be entitled [upon cancellation or delivery deferral].”

So far, the parties and the language on the forms appear to be in agreement. But on the reverse side of Krug’s purchase order appears a “force majeure” clause. Power Engineering asserts it was neither discussed between the parties nor agreed upon. This clause — the central point of the dispute — provides as follows:

10. Contingencies. In the event of causes beyond the control of Purchaser, including but not limited to acts of God, fire, the elements, strikes or labor disputes, and accident or transportation difficulties which would make it unreasonable in Purchaser’s judgment to accept delivery hereunder, Purchaser shall have the option to terminate this purchase order or to delay the delivery or completion of all or part of the items, such termination or delay being without cost to Purchaser.

(Emphasis added.) Krug correctly asserts that Power Engineering never, either verbally or in the purchase order acknowledgment, discussed or objected to this clause.

It appears that Power Engineering initially received merely an oral purchase order and an electronic facsimile of only the front page of the written purchase order, and began production at that time. Power Engineering did not receive a copy of the complete purchase order until a month later, on April 16, 1990. Thus Power Engineering could not become aware that Krug had incorporated a “force majeure” clause on the reverse side of the purchase order until it received the complete copy. This *493 was after it had begun the manufacturing process.

During the initial manufacturing and assembly stages, Krug paid Power Engineering $75,000, just over one-half of the $149,-700 contract price. The gear box was completed in late July, and a minor adjustment requested by Krug was completed in early August. On August 7 Krug authorized Power Engineering to ship the gear box. It was not shipped immediately only because of some routine matters that already had been, or were soon, resolved.

Hostilities with Iraq, known as the Gulf War, began on or about August 6, 1990. The United Nations immediately implemented an embargo against all shipment of any materials to Iraq. Reacting to the embargo, on August 7 Tripod Laing directed Krug International (U.K.), Ltd., by letter to “carry out no more work and expend no more money until further notice.” In the letter Tripod Laing alleged “that due to the United Nations resolution ... we have been forced to suspend operations on the contract due to ‘force majeure’.” Krug received a copy of this letter on August 7 and immediately complied with its directive. Believing the gear box was in transit, however, Krug decided all equipment in transit would be accepted and paid for. On August 10 Krug learned that Power Engineering had not yet shipped the gear box and immediately orally directed Power Engineering not to ship it. On August 13 Power Engineering received a similar written directive from Krug. Krug purported to be operating in accordance with the force majeure clause. The gear box remains in storage because Krug has refused to have it shipped.

Power Engineering then brought this suit. The district court determined the force majeure clause is not part of the contract between the parties. The court found that Power Engineering had fully complied with the contract and Krug had breached it. Judgment was entered for Power Engineering against Krug for one-half the purchase price — plus interest and costs.

I. The case was tried to the court at law so our review is for correction of errors. Iowa R.App.P. 4. The findings of fact in jury-waived cases have the effect of a special verdict. Iowa R.App.P. 4. They are binding on appeal if supported by substantial evidence. Iowa R.App.P. 14(f)(1). We are not bound by the trial court’s application of legal principles or conclusions of law. Iowa Fuel & Minerals, Inc. v. Iowa State Bd. of Regents,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Revere Transducers, Inc. v. Deere & Co.
595 N.W.2d 751 (Supreme Court of Iowa, 1999)
L & L Builders Co. v. Mayer Associated Services, Inc.
46 F. Supp. 2d 875 (N.D. Iowa, 1999)
Johnson v. Land O' Lakes, Inc.
18 F. Supp. 2d 985 (N.D. Iowa, 1998)
Advance Elevator Co. v. Four State Supply Co.
572 N.W.2d 186 (Court of Appeals of Iowa, 1997)
DeJong v. City of Sioux Center
980 F. Supp. 1010 (N.D. Iowa, 1997)
Chicago Central & Pacific Railroad v. Union Pacific Railroad
558 N.W.2d 711 (Supreme Court of Iowa, 1997)
Howard v. Schildberg Const. Co., Inc.
528 N.W.2d 550 (Supreme Court of Iowa, 1995)
Jahnke v. Jahnke
526 N.W.2d 159 (Supreme Court of Iowa, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
501 N.W.2d 490, 23 U.C.C. Rep. Serv. 2d (West) 382, 1993 Iowa Sup. LEXIS 157, 1993 WL 208816, Counsel Stack Legal Research, https://law.counselstack.com/opinion/power-engineering-manufacturing-ltd-v-krug-international-iowa-1993.