Westinghouse Electric Corp. v. Mill & Elevator Co.

118 N.W.2d 528, 254 Iowa 874, 1962 Iowa Sup. LEXIS 738
CourtSupreme Court of Iowa
DecidedDecember 11, 1962
Docket50724
StatusPublished
Cited by13 cases

This text of 118 N.W.2d 528 (Westinghouse Electric Corp. v. Mill & Elevator Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westinghouse Electric Corp. v. Mill & Elevator Co., 118 N.W.2d 528, 254 Iowa 874, 1962 Iowa Sup. LEXIS 738 (iowa 1962).

Opinion

*876 Garfield, 0. J.

— The question presented is the liability of defendant surety on a construction bond to plaintiff-subcontractor from which defendant principal contractor purchased material in performing the contract. The answer depends on the proper construction of the contractor’s bond and the contract made part thereof. Following trial in equity, mainly on stipulated facts, judgment was entered for plaintiff against defendants’ contractor and its surety. These defendants and the owner appeal.

Plaintiff-subcontractor is Westinghouse Electric Corporation. Defendant principal contractor is Mill & Elevator Company. Surety on the contractor’s bond is Farmers Elevator Mutual Insurance Company. Farmers Cooperative Elevator is owner. Various mechanic’s lien claimants were also made defendants.

The owner made a written contract with the (principal) contractor under which the latter agreed to build in the town of Stanhope a feed mill and install necessary machinery, equipment and wiring therein. Total contract price was $177,475. The contract contains these pertinent provisions:

“6. The Contractor agrees to purchase all. materials and machinery, furnish all necessary labor and carry on the project in a workmanlike manner. * * *
“8. It is understood that the Contractor will subcontract-portions of this project, and that these subcontracts are a part of this total contract. * * *
“11. The Contractor agrees to * * * obtain a performance bond * * #.”

The owner was to and did pay the cost of the bond in addition to the contract price.

Attached to and forming part of the contract is a list of the machinery the contractor was to furnish.

The bond, headed “Contract Bond”, describes the contract and goes on to provide: “* * * which contract is hereby referred to and made a part hereof as fully and to the same extent as if copied at length herein. Now, therefore, the condition of the above obligation is such, That if the above bounden Principal *877 shall well and truly keep, do and perform, each and every, all and singular, the matters and things in said contract set forth and specified to be by the said Principal kept, done and performed at the time and in the manner in said contract specified, and shall pay over, make good and reimburse to the above named Obligee, all loss and damage which said Obligee may sustain by reason of failure or default on the part of said Principal, then this obligation shall be void; otherwise, to be and remain in full force and effect.”

The contractor defaulted in construction of the improvement and advised the surety it could go no further, was in effect insolvent, and no money was then due the contractor from the owner. The surety took over the assets of the contractor, “started running the job * * * and the contract was completed by the contractor with the exception of some minor” items. The surety paid holders of mechanic’s liens filed within 60 days after the last material or labor was furnished. Claims not so filed, including plaintiff’s, were not paid. Our question is whether the bond obligates the surety to pay them.

It was admitted at the trial the materials for which payment was claimed were sold and delivered to the contractor and used in the improvement for the owner. The amounts were also admitted. Plaintiff’s claim for $13,606.16 is much the largest. It was also established that the contractor made and delivered purchase orders to the suppliers before they delivered material to the contractor. It is agreed the contractor was obligated to pay the subcontractors for the materials so purchased and delivered.

I. It is now almost universally held that the undertaking of a paid surety engaged in that business for profit is in the nature of an insurance contract and is controlled by rules applicable thereto rather than by rules applied to a gratuitous surety who was a favorite of the law. Rowe v. Stufflebeam, 249 Iowa 985, 992, 89 N.W.2d 875, 878, 879, and citations; 9 Am. Jur., Building and Construction Contracts, section 89; 72 C. J. S., Principal and Surety, section 102.

“* * * in determining the right of a laborer or material-man to the benefit of a contractor’s bond, as against a compen *878 sated surety, the undertaking- will be most strongly construed in favor of such persons and against the surety. That is to say, where the bond is reasonably susceptible of two constructions, that one which is the more favorable to the claimant will be adopted.” Annotation, 77 A. L. R. 21, 42, 43, citing numerous precedents; supplemented in 118 A. L. R. 57, 62. To like effect are Clinton Bridge Works v. Kingsley, 188 Iowa 218, 224, 175 N.W. 976; Streator Clay Mfg. Co. v. Henning-Vineyard Co., 176 Iowa 297, 311, 155 N.W. 1001.

II. There is little if any dispute as to the law governing cases of this kind. The disagreement here is in the application of the law to the bond and contract before us.

It is clear the contract is part of the bond. As stated, the bond expressly so provides. Thus there can be no doubt terms of the contract as well as the bond should be considered in determining the surety’s liability under the bond. Bourrett v. W. M. Bride Constr. Co., 248 Iowa 1080, 1085, 84 N.W.2d 4, 7; Annotations, 77 A. L. R. 21, 46, 47; 118 A. L. R. 57, 62.

The fact only the owner is named as obligee of the bond is unimportant. “Although there are a few outside decisions to the contrary it is well settled in Iowa and is the weight of authority generally that laborers and materialmen may recover on a contractor’s bond conditioned that the contractor shall pay all claims for labor and material, or shall faithfully perform a contract providing for such payment, although the owner alone is named as obligee of the bond.” (Citations) Bourrett case, supra.

In the precedent last cited the main condition of the bond -was to “ ‘indemnify the Obligee against any loss or damage * * * by reason of the failure of the Principal to faithfully perform said contract * * *.’ ” It was not contended the obligee-owner sustained any loss or damage in a legal sense. That the bond was intended only to indemnify the owner was made doubly clear by the express condition in it “ ‘That no right of action shall accrue upon or by reason hereof, to or for the use or benefit of anyone other than the Obligee herein named; # * (Page 1086 of 248 Iowa, pages 7 and 8 of 84 N.W.2d)

Bourrett, a subcontractor, was held not entitled to recover on the bond then before us. (For an explanation of the decision *879 see Rowe v. Stufflebeam, supra, 249 Iowa 985, 993, 89 N.W.2d 875, 879.) However, the Bourrett opinion cites several Iowa decisions where laborers or materialmen have been allowed to recover on a contractor’s bond conditioned, in substance, that he will pay all claims for labor and material

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L & L Builders Co. v. Mayer Associated Services, Inc.
46 F. Supp. 2d 875 (N.D. Iowa, 1999)
Cretex Companies, Inc. v. Construction Leaders, Inc.
342 N.W.2d 135 (Supreme Court of Minnesota, 1984)
Wyoming MacHinery Co. v. United States Fidelity & Guaranty Co.
614 P.2d 716 (Wyoming Supreme Court, 1980)
Dealers Electrical Supply v. United States Fidelity & Guaranty Co.
258 N.W.2d 131 (Nebraska Supreme Court, 1977)
National Bank v. Equity Investors
546 P.2d 440 (Washington Supreme Court, 1976)
Amelco Window Corp. v. Fed. Ins. Co.
317 A.2d 398 (New Jersey Superior Court App Division, 1974)
Ferrer v. Alliance Co. of P.R., Inc.
93 P.R. 1 (Supreme Court of Puerto Rico, 1966)
Ore-Ida Potato Products, Inc. v. United Pacific Insurance
392 P.2d 191 (Idaho Supreme Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
118 N.W.2d 528, 254 Iowa 874, 1962 Iowa Sup. LEXIS 738, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westinghouse-electric-corp-v-mill-elevator-co-iowa-1962.