Brian Halstead v. Wayne A. Langel, Cathy M. Langel, and First State Bank

CourtCourt of Appeals of Iowa
DecidedOctober 29, 2014
Docket14-0237
StatusPublished

This text of Brian Halstead v. Wayne A. Langel, Cathy M. Langel, and First State Bank (Brian Halstead v. Wayne A. Langel, Cathy M. Langel, and First State Bank) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brian Halstead v. Wayne A. Langel, Cathy M. Langel, and First State Bank, (iowactapp 2014).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 14-0237 Filed October 29, 2014

BRIAN HALSTEAD, Plaintiff-Appellant,

vs.

WAYNE A. LANGEL, CATHY M. LANGEL, and FIRST STATE BANK, Defendants-Appellees. ________________________________________________________________

Appeal from the Iowa District Court for Fayette County, Kellyann M. Lekar,

Judge.

A contractor appeals the district court decision denying his petition

seeking a money judgment and enforcement of his mechanic’s lien, and granting

the defendants’ counterclaim for damages. AFFIRMED IN PART, REVERSED

IN PART, AND REMANDED.

James S. Updegraff, West Union, for appellant.

Patrick Dillon, Sumner, and David James Hanson of Hofmeyer & Hanson,

P.C., Fayette, for appellees.

Considered by Potterfield, P.J., and Tabor and Mullins, JJ. 2

MULLINS, J.

A contractor appeals the district court decision denying his petition

seeking a money judgment and enforcement of his mechanic’s lien, and granting

the defendants’ counterclaim for damages. We agree with the district court’s

determination the contractor cannot enforce his mechanic’s lien because he did

not show substantial performance of the contract. We conclude, however, the

contractor should be paid for the work he performed on the project and for which

he had not been paid, as adjusted by the cost of remedying defective work. We

affirm the denial of the mechanic’s lien, reverse the decision of the district court

on damages, and remand for a further hearing on the amount of damages.

I. Background Facts & Proceedings

Wayne and Cathy Langel own a building in Fayette, Iowa. Cathy

developed plans to operate a prom and bridal shop business there. She was

approved for a grant of $100,000 from Upper Iowa University in Fayette to make

improvements to the property and to help start the business. A condition of

obtaining the grant funding was that Cathy improve the appearance of the

building.

On July 20, 2012, Cathy entered into a written contract with Brian

Halstead to perform work to improve the appearance of the outside of the

building for a cost of between $15,000 to $20,000, depending upon the costs of

materials and hours needed to complete the work. The written contract did not

contain any provision concerning when the work needed to be completed. Cathy

stated Halstead orally agreed the work would be completed by Upper Iowa 3

University’s Homecoming Week, September 23 to 29, 2012; but Halstead denied

this was a provision of the contract. Halstead had a full-time job performing tuck-

point brick repair on older buildings for Technical Specialty Systems. He also

performed independent projects, such as his job for Cathy, and she was aware

he would be working on her project in his spare time.

Halstead began working on the project after the contract was signed. The

work primarily involved tuck-pointing the existing brick façade of the building.

Cathy paid Halstead $5000 near the beginning of the project. On September 22,

2012, Cathy discharged Halstead because she believed the project was not

being completed in a timely manner and she had concerns about the quality of

Halstead’s work. The parties agree the work was not completed at that time.

Cathy contacted Thomas Pattison to work on the project. Pattison mainly

engaged in new construction, but had employees that could do tuck-pointing. He

had some of his employees work on the exterior of the building for about two and

one-half days in September 2012, and charged Cathy $1968.49 for the work.

Pattison submitted an estimate that it would cost an additional $8950 “to

complete and fix problems.” Cathy did not have this additional work performed.

On September 28, 2012, Halstead submitted a bill to Cathy for $10,000,

representing labor and materials for the project for which he had not been paid.

He submitted an exhibit showing his time and materials for the project had

actually been $16,245, for which he had already been paid $5000, leaving a

balance of $11,245; but he decided to bill Cathy for only $10,000 of the 4

remainder. In October 2012, Upper Iowa University released the grant payment

of $100,000 to Cathy.

On December 28, 2012, Halstead filed a mechanic’s lien, pursuant to Iowa

Code chapter 572 (2011). Halstead filed a petition on March 12, 2013, seeking

to enforce the mechanic’s lien on the property because he had not been paid the

$10,000 he believed was due for his work on the project. The Langels filed a

counterclaim asserting Halstead should be required to pay $8950 for the cost of

repairing his work.

The district court entered a decision on January 15, 2014. The court

determined Halstead had not substantially completed the project, and therefore,

could not enforce his mechanic’s lien. In particular, the court found Halstead

failed to perform material portions of the contract by not completing it by

September 23, 2012. On the counterclaim, the court determined Halstead had

not completed the work in a good, workmanlike manner and should be

responsible to pay defendants the amount of $8950. Halstead appeals the

decision of the district court.

II. Standard of Review

An action to enforce a mechanic’s lien is heard in equity and we review

the district court’s decision de novo. Flynn Builders, L.C. v. Lande, 814 N.W.2d

542, 545 (Iowa 2012). We give weight to the district court’s findings of fact, but

are not bound by them. Id. In cases involving a mechanic’s lien, “involving as

they do numerous charges and counter charges which depend entirely on the 5

credibility of the parties, we have frequently held the trial court is in a more

advantageous position than we to put credence where it belongs.” Id.

III. Mechanic’s Lien

In general, in order to enforce a mechanic’s lien a contractor must show

substantial performance of the contract. Id. at 546. Substantial performance

means there are only omissions or deviations from a contract that are inadvertent

or unintentional, not the result of bad faith; do not impair the structure as a whole;

are remedial without doing substantial damage to the other portions of the

building; and may be compensated through deductions in the contract price. Id.

In an action to foreclose a mechanic’s lien, “a technical, exact and perfect

performance is not necessary.” Id.

There is an exception to the requirement for substantial performance if the

contractor’s inability to complete the project is due to obstruction, hindrance, or

delay by the homeowner. Sheer Constr., Inc. v. W. Hodgman & Sons, Inc., 326

N.W.2d 328, 332 (Iowa 1982). “[T]he rule is well-settled that one party to a

contract may not hamper the efforts of the other in performance according to its

terms.” Hardin v. Eska Co., 127 N.W.2d 595, 598 (Iowa 1964). “[I]f one party to

a contract prevents the other from performing a condition or fails to cooperate to

allow the condition to be satisfied, the other party is excused from showing

compliance with the condition.” Employee Benefits Plus, Inc. v. Des Moines

Gen. Hosp., 535 N.W.2d 149, 155 (Iowa Ct. App. 1995).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moore's Builder & Contractor, Inc. v. Hoffman
409 N.W.2d 191 (Court of Appeals of Iowa, 1987)
Nepstad Custom Homes Co. v. Krull
527 N.W.2d 402 (Court of Appeals of Iowa, 1994)
Sheer Construction, Inc. v. W. Hodgman & Sons, Inc.
326 N.W.2d 328 (Supreme Court of Iowa, 1982)
Bidwell v. Midwest Solariums, Inc.
543 N.W.2d 293 (Court of Appeals of Iowa, 1995)
McDonald v. Welch
176 N.W.2d 846 (Supreme Court of Iowa, 1970)
I. G. L. Racquet Club v. Midstates Builders, Inc.
323 N.W.2d 214 (Supreme Court of Iowa, 1982)
First Interstate Equipment Leasing of Iowa, Inc. v. Fielder
449 N.W.2d 100 (Court of Appeals of Iowa, 1989)
Hardin v. Eska Company
127 N.W.2d 595 (Supreme Court of Iowa, 1964)
Employee Benefits Plus, Inc. v. Des Moines General Hospital
535 N.W.2d 149 (Court of Appeals of Iowa, 1995)
Flynn Builders, L.C. v. Matthew P. Lande and Chris Lande
814 N.W.2d 542 (Supreme Court of Iowa, 2012)
Lewis Electric Co. Vs. Ronald E. Miller And Kathleen F. Miller
791 N.W.2d 691 (Supreme Court of Iowa, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Brian Halstead v. Wayne A. Langel, Cathy M. Langel, and First State Bank, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brian-halstead-v-wayne-a-langel-cathy-m-langel-and-iowactapp-2014.