Brian Halstead v. Wayne A. Langel, Cathy M. Langel, and First State Bank

Court of Appeals of Iowa·Decided October 29, 2014·No. 14-0237·Published

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 14-0237

Filed October 29, 2014

BRIAN HALSTEAD, Plaintiff-Appellant,

vs.

WAYNE A. LANGEL, CATHY M. LANGEL, and FIRST STATE BANK, Defendants-Appellees.

Appeal from the Iowa District Court for Fayette County, Kellyann M. Lekar, Judge.

A contractor appeals the district court decision denying his petition seeking a money judgment and enforcement of his mechanic’s lien, and granting the defendants’ counterclaim for damages. AFFIRMED IN PART, REVERSED IN PART, AND REMANDED.

James S. Updegraff, West Union, for appellant.

Patrick Dillon, Sumner, and David James Hanson of Hofmeyer & Hanson, P.C., Fayette, for appellees.

Considered by Potterfield, P.J., and Tabor and Mullins, JJ.

MULLINS, J.

A contractor appeals the district court decision denying his petition seeking a money judgment and enforcement of his mechanic’s lien, and granting the defendants’ counterclaim for damages. We agree with the district court’s determination the contractor cannot enforce his mechanic’s lien because he did not show substantial performance of the contract. We conclude, however, the contractor should be paid for the work he performed on the project and for which he had not been paid, as adjusted by the cost of remedying defective work. We affirm the denial of the mechanic’s lien, reverse the decision of the district court on damages, and remand for a further hearing on the amount of damages.

I. Background Facts & Proceedings Wayne and Cathy Langel own a building in Fayette, Iowa. Cathy developed plans to operate a prom and bridal shop business there. She was approved for a grant of $100,000 from Upper Iowa University in Fayette to make improvements to the property and to help start the business. A condition of obtaining the grant funding was that Cathy improve the appearance of the building.

On July 20, 2012, Cathy entered into a written contract with Brian Halstead to perform work to improve the appearance of the outside of the building for a cost of between $15,000 to $20,000, depending upon the costs of materials and hours needed to complete the work. The written contract did not contain any provision concerning when the work needed to be completed. Cathy stated Halstead orally agreed the work would be completed by Upper Iowa

University’s Homecoming Week, September 23 to 29, 2012; but Halstead denied this was a provision of the contract. Halstead had a full-time job performing tuck- point brick repair on older buildings for Technical Specialty Systems. He also performed independent projects, such as his job for Cathy, and she was aware he would be working on her project in his spare time.

Halstead began working on the project after the contract was signed. The work primarily involved tuck-pointing the existing brick façade of the building. Cathy paid Halstead $5000 near the beginning of the project. On September 22, 2012, Cathy discharged Halstead because she believed the project was not being completed in a timely manner and she had concerns about the quality of Halstead’s work. The parties agree the work was not completed at that time.

Cathy contacted Thomas Pattison to work on the project. Pattison mainly engaged in new construction, but had employees that could do tuck-pointing. He had some of his employees work on the exterior of the building for about two and one-half days in September 2012, and charged Cathy $1968.49 for the work. Pattison submitted an estimate that it would cost an additional $8950 “to complete and fix problems.” Cathy did not have this additional work performed.

On September 28, 2012, Halstead submitted a bill to Cathy for $10,000, representing labor and materials for the project for which he had not been paid. He submitted an exhibit showing his time and materials for the project had actually been $16,245, for which he had already been paid $5000, leaving a balance of $11,245; but he decided to bill Cathy for only $10,000 of the

remainder. In October 2012, Upper Iowa University released the grant payment of $100,000 to Cathy.

On December 28, 2012, Halstead filed a mechanic’s lien, pursuant to Iowa Code chapter 572 (2011). Halstead filed a petition on March 12, 2013, seeking to enforce the mechanic’s lien on the property because he had not been paid the $10,000 he believed was due for his work on the project. The Langels filed a counterclaim asserting Halstead should be required to pay $8950 for the cost of repairing his work.

The district court entered a decision on January 15, 2014. The court determined Halstead had not substantially completed the project, and therefore, could not enforce his mechanic’s lien. In particular, the court found Halstead failed to perform material portions of the contract by not completing it by September 23, 2012. On the counterclaim, the court determined Halstead had not completed the work in a good, workmanlike manner and should be responsible to pay defendants the amount of $8950. Halstead appeals the decision of the district court.

II. Standard of Review An action to enforce a mechanic’s lien is heard in equity and we review the district court’s decision de novo. Flynn Builders, L.C. v. Lande, 814 N.W.2d 542, 545 (Iowa 2012). We give weight to the district court’s findings of fact, but are not bound by them. Id. In cases involving a mechanic’s lien, “involving as they do numerous charges and counter charges which depend entirely on the

credibility of the parties, we have frequently held the trial court is in a more advantageous position than we to put credence where it belongs.” Id.

III. Mechanic’s Lien In general, in order to enforce a mechanic’s lien a contractor must show substantial performance of the contract. Id. at 546. Substantial performance means there are only omissions or deviations from a contract that are inadvertent or unintentional, not the result of bad faith; do not impair the structure as a whole; are remedial without doing substantial damage to the other portions of the building; and may be compensated through deductions in the contract price. Id. In an action to foreclose a mechanic’s lien, “a technical, exact and perfect performance is not necessary.” Id.

There is an exception to the requirement for substantial performance if the contractor’s inability to complete the project is due to obstruction, hindrance, or delay by the homeowner. Sheer Constr., Inc. v. W. Hodgman & Sons, Inc., 326 N.W.2d 328, 332 (Iowa 1982). “[T]he rule is well-settled that one party to a contract may not hamper the efforts of the other in performance according to its terms.” Hardin v. Eska Co., 127 N.W.2d 595, 598 (Iowa 1964). “[I]f one party to a contract prevents the other from performing a condition or fails to cooperate to allow the condition to be satisfied, the other party is excused from showing compliance with the condition.” Employee Benefits Plus, Inc. v. Des Moines Gen. Hosp., 535 N.W.2d 149, 155 (Iowa Ct. App. 1995).

Halstead contends his failure to complete the project was due to the fact he was discharged by Cathy on September 22, 2012. Halstead disputes the

assertion he had agreed to complete the project by homecoming for Upper Iowa University, which was during the week of September 23 to 29, 2012. He stated he told Cathy he could have the job done by the end of the season, which depended upon the weather and temperature. Halstead testified, “If there would have been any pressure on the time figure, I probably would not have done this job, because this was my part-time job.” On the other hand, Cathy testified that having the work completed by homecoming was a condition of the contract, and Halstead told her he could get the job done within that timeframe. Wayne testified, “he said that he could get it done by the end of the season. But our deadline was to get the east and south side had to be done by homecoming, is what we went for.” Wayne stated Halstead was informed of this requirement, and he did not object.

Free access — add to your briefcase to read the full text and ask questions with AI

Brian Halstead v. Wayne A. Langel, Cathy M. Langel, and First State Bank, (iowactapp 2014).

Brian Halstead v. Wayne A. Langel, Cathy M. Langel, and First State Bank (Brian Halstead v. Wayne A. Langel, Cathy M. Langel, and First State Bank) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Moore's Builder & Contractor, Inc. v. Hoffman
409 N.W.2d 191 (Court of Appeals of Iowa, 1987)
Nepstad Custom Homes Co. v. Krull
527 N.W.2d 402 (Court of Appeals of Iowa, 1994)
Sheer Construction, Inc. v. W. Hodgman & Sons, Inc.
326 N.W.2d 328 (Supreme Court of Iowa, 1982)
Bidwell v. Midwest Solariums, Inc.
543 N.W.2d 293 (Court of Appeals of Iowa, 1995)
McDonald v. Welch
176 N.W.2d 846 (Supreme Court of Iowa, 1970)
I. G. L. Racquet Club v. Midstates Builders, Inc.
323 N.W.2d 214 (Supreme Court of Iowa, 1982)
First Interstate Equipment Leasing of Iowa, Inc. v. Fielder
449 N.W.2d 100 (Court of Appeals of Iowa, 1989)
Hardin v. Eska Company
127 N.W.2d 595 (Supreme Court of Iowa, 1964)
Employee Benefits Plus, Inc. v. Des Moines General Hospital
535 N.W.2d 149 (Court of Appeals of Iowa, 1995)
Flynn Builders, L.C. v. Matthew P. Lande and Chris Lande
814 N.W.2d 542 (Supreme Court of Iowa, 2012)
Lewis Electric Co. Vs. Ronald E. Miller And Kathleen F. Miller
791 N.W.2d 691 (Supreme Court of Iowa, 2010)