Marvin Swan v. Robert Lee Jackson

CourtCourt of Appeals of Iowa
DecidedMay 12, 2021
Docket19-0116
StatusPublished

This text of Marvin Swan v. Robert Lee Jackson (Marvin Swan v. Robert Lee Jackson) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marvin Swan v. Robert Lee Jackson, (iowactapp 2021).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 19-0116 Filed May 12, 2021

MARVIN SWAN, Plaintiff-Appellee,

vs.

ROBERT LEE JACKSON, Defendant-Appellant. ________________________________________________________________

Appeal from the Iowa District Court for Wayne County, Patrick W.

Greenwood, Judge.

Robert Jackson appeals the district court’s order foreclosing a mechanic’s

lien in favor of Marvin Swan. AFFIRMED.

Bob Jackson, Promise City, self-represented appellant.

Verle W. Norris, Corydon, for appellee.

Considered by Vaitheswaran, P.J., Greer, J., and Scott, S.J.*

*Senior judge assigned by order pursuant to Iowa Code section 602.9206

(2021). 2

VAITHESWARAN, Presiding Judge.

Robert Jackson appeals a trial court order foreclosing a mechanic’s lien in

favor of Marvin Swan. Jackson contends the court (1) should not have excluded

certain exhibits, (2) acted inequitably in concluding Swan substantially performed

the contract, and (3) should not have awarded trial attorney fees.

I. Background Facts and Proceedings

Jackson was a farmer who owned property in Wayne County, Iowa.

Jackson signed a conservation program contract with the Natural Resources

Conservation Service (NRCS) of the United States Department of Agriculture

(USDA). He was to have two ponds constructed on his property as part of the

“Lower South Fork Chariton River Project.” The NRCS was to pay him $38,684

for his participation in the program.

Jackson hired Swan to construct the ponds, referred to as the large

structure and the small structure. After Swan completed the work, he submitted

two invoices: $31,855 for the large structure and $14,551 for the small structure.

At Jackson’s request, Swan later completed additional work, including the

construction of a fence crossing and a building site. Swan invoiced that work at

$4300. Jackson submitted a payment application to the USDA.

The USDA paid Jackson $26,417.22. Jackson, in turn, paid Swan $9500,

$5000, and a $1000 “cash payment,” leaving an outstanding balance of $35,201.

Swan attempted but failed to collect the balance. He filed a mechanic’s lien,

followed by a petition to foreclose the lien. The petition sought $46,135.97 and 3

reasonable attorney fees.1 Jackson filed an answer and counterclaim, alleging

Swan’s “construction of the pond was negligent.” After a bench trial, the district

court foreclosed the mechanic’s lien in the amount of $35,201 and ordered

Jackson to pay Swan trial attorney fees of $70,164.71. The court denied Jackson’s

posttrial motion. This appeal followed.

II. Exclusion of Evidence

Swan engaged in pretrial discovery. Jackson failed to cooperate, forcing

Swan to move for an order compelling compliance and for sanctions. Years

passed. Eventually, Jackson answered interrogatories and provided some

documents. On November 14, 2017, approximately two months after a scheduled

trial date and two months before a rescheduled trial date, Jackson gave Swan a

zip drive containing 2265 files and 49 folders. Swan moved to “exclude all exhibits

and discovery materials produced after” the originally scheduled trial date. On

December 12, 2017, the district court imposed discovery sanctions as follows:

[T]he discovery materials and/or proposed exhibits transmitted to [Swan] by [Jackson] on November 14, 2017, are excluded from use at trial due to the fact that they were not disclosed until well after the Court’s extended discovery deadline. Any documents or proposed exhibits transmitted to [Swan] by [Jackson] on or before August 29, 2017, are not excluded.

Swan subsequently filed two motions to exclude exhibits he alleged were in

violation of the December 12, 2017 order. The district court granted the motions.

Jackson contends the district court “incorrectly interpreted and incorrectly

applied [the December 12, 2017] order excluding documents throughout trial.” In

his view, the judge who signed the December 12, 2017 order was “misled” into

1 According to Swan, the larger amount did not reflect payments Jackson made on the outstanding balance after the mechanic’s lien was filed. 4

believing he violated a trial scheduling order, and the trial court selectively enforced

the December 12, 2017 order against him, resulting in “a decidedly unfair trial.” In

response, Swan exhorts us not to address the issue on the ground that “Jackson

has made no attempt to pinpoint any evidence, exhibit, or any objection to such

evidence or exhibit, the exclusion of such which was error.” We elect to bypass

Swan’s waiver concern and proceed to the merits. Our review of the December 12,

2017 order, as well as the trial court’s implementation of that order, is for an abuse

of discretion. See City of Des Moines v. Ogden, 909 N.W.2d 417, 422–23 (Iowa

2018) (“We ‘review decisions on sanctions for violation of discovery for an abuse

of discretion.’ Likewise, we review evidentiary rulings for an abuse of discretion.”

(citations omitted)).

Iowa Rule of Civil Procedure 1.517(3)(a) authorizes exclusion of documents not

disclosed in discovery “unless the failure was substantially justified or is harmless.”

Swan filed his petition in 2015 and served his first request for production of documents

within three months. Two and one-half years later, Swan was still attempting to obtain

compliance. One trial date came and went. Another was on the horizon. Jackson’s

only justification for his delayed production of documents in November 2017 was that

they were generated after Swan took his deposition in August 2017. He asserted Swan

had “more than adequate time to review the same” before the rescheduled trial date.

Swan countered that the new documents were unmarked and intermingled with old

ones and the sheer volume produced at that “late juncture” and “after the case ha[d]

previously been set for trial” rendered the production “highly prejudicial.”

Jackson’s noncompliance with discovery requests for a period of years supports

the district court’s exclusionary order. Additionally, Jackson’s belatedly-produced zip 5

drive failed to identify documents arguably responsive to his deposition testimony

versus documents generally responsive to prior requests for production. The district

court’s December 12, 2017 order staked out a middle ground, excluding only those

documents disclosed after the originally scheduled trial date while permitting those

disclosed before. We discern no abuse of discretion in the court’s order.

We turn to the trial court’s enforcement of the December 12, 2017 order.

Throughout the thirteen-day trial, the court afforded Jackson the chance to explain

why he believed certain documents should not be excluded. The following

comments are illustrative:

The Court’s difficulty is that the exhibits are so numerous and voluminous that it’s difficult to know, not having participated in the discovery process, what was timely provided and what was not. To the best of his ability, I believe [Swan’s counsel] has provided the matrix or spreadsheet to show what he asserts was not provided. That was prepared before the filings from two days ago. It’s my intent to exclude those unless you can establish that you indeed did comply with the prior discovery rulings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nepstad Custom Homes Co. v. Krull
527 N.W.2d 402 (Court of Appeals of Iowa, 1994)
Schaffer v. Frank Moyer Construction, Inc.
628 N.W.2d 11 (Supreme Court of Iowa, 2001)
McDonald v. Welch
176 N.W.2d 846 (Supreme Court of Iowa, 1970)
Flynn Builders, L.C. v. Matthew P. Lande and Chris Lande
814 N.W.2d 542 (Supreme Court of Iowa, 2012)
Benjamin Feld, Larry Feld, And Judith Feld Vs. Luke Borkowski
790 N.W.2d 72 (Supreme Court of Iowa, 2010)
City of Des Moines, Iowa v. Mark Ogden
909 N.W.2d 417 (Supreme Court of Iowa, 2018)
Winger Contracting Company v. Cargill, Incorporated
926 N.W.2d 526 (Supreme Court of Iowa, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Marvin Swan v. Robert Lee Jackson, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marvin-swan-v-robert-lee-jackson-iowactapp-2021.