Standard Water Control Systems, Inc., plaintiff-appellees/counterclaim-defendants v. Michael D. Jones and Cori Jones, defendants-appellants/counterclaim-plaintiffs.

888 N.W.2d 673, 2016 WL 7478610
CourtCourt of Appeals of Iowa
DecidedAugust 31, 2016
Docket15-0458
StatusPublished
Cited by9 cases

This text of 888 N.W.2d 673 (Standard Water Control Systems, Inc., plaintiff-appellees/counterclaim-defendants v. Michael D. Jones and Cori Jones, defendants-appellants/counterclaim-plaintiffs.) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Water Control Systems, Inc., plaintiff-appellees/counterclaim-defendants v. Michael D. Jones and Cori Jones, defendants-appellants/counterclaim-plaintiffs., 888 N.W.2d 673, 2016 WL 7478610 (iowactapp 2016).

Opinion

MCDONALD, Judge.

Mike and Cori Jones contracted with Standard Water Control Systems to waterproof the basement of their residence: Standard Water started work on July 15, 2013. While working in the basement, one of Standard Water’s employees struck a water line and a sewer line with a jackhammer. The water and sewer lines were encased within the concrete floor and the footings. The placement of the lines was unusual and not foreseeable. The ruptured water and sewer lines caused damage to the'Joneses’ property.

Standard Water continued to work on the basement on the day of July 15 but did not complete the job. Several witnesses testified the job was ninety-five percent complete at the end of the day. The Joneses would not allow Standard Water back on the property the next day or any day thereafter to finish the remainder of the work. Standard Water tendered a bill to the Joneses for $5,400, which represent *675 ed the balance owed on the project. The Joneses stated they would not pay the bill because the work was incomplete and because Standard Water had damaged the property. The Joneses incurred costs to assess and repair the damage to their property.

Sixteen days after its first and last day of work at the Joneses’ residence, Standard Water filed a notice of commencement of work and mechanic’s lien. In October 2013, the Joneses sent Standard Water a letter demanding foreclosure of the mechanic’s lien pursuant to Iowa Code section 572.28 (2013). Standard Water filed an action to foreclose the lien and for breach of contract, and the Joneses filed an answer and counterclaims. The district court found the Joneses were in breach of contract and entered judgment in personam against the defendants for $5400 plus interest at twelve percent and attorney fees in the amount of $43,835.25. The district court concluded Standard Water was entitled to in rem judgment against the property for the same amount and entitled to foreclose the mechanic’s lien. The Joneses timely filed this appeal, challenging the validity of the hen, the validity of the parties’ contract, and the amount of the fee award.

I.

The Joneses argue Standard Water’s mechanic’s lien was invalid due to Standard Water’s purported failure to comply with statutory filing and notice requirements. Actions to enforce mechanic’s liens are equitable proceedings. See Flynn Builders, L.C. v. Lande, 814 N.W.2d 542, 545 (Iowa 2012). Normally, appeals from actions brought in equity are reviewed de novo. See Iowa R. App. P. 6.907. However, this dispute raises issues of statutory interpretation and construction. Our review of issues of statutory interpretation and construction is for the correction of legal error. See Bank of Am., N.A. v. Schulte, 843 N.W.2d 876, 880 (Iowa 2014).

We look no further than thé language of the statute when it is unambiguous. Estate of Ryan v. Heritage Trails Assocs., Inc., 745 N.W.2d 724, 730 (Iowa 2008). If a statute is ambiguous, we turn'to principles of statutory interpretation. In re Estate of Bockwoldt, 814 N.W.2d 215, 223 (Iowa 2012). A statute is ambiguous if reasonable people can disagree about its meaning. Id. When interpreting statutes, we seek the legislature’s intent. Schaefer v. Putnam, 841 N.W.2d 68, 75 (Iowa 2013). Rather than analyzing words or phrases in isolation, we assess the entire statute. Hardin Cty. Drainage Dist. 55 v. Union Pac. R.R. Co., 826 N.W.2d 507, 512 (Iowa 2013). We consider a statute’s legislative history, including prior versions of the statute. State v. Romer, 832 N.W.2d 169, 176 (Iowa 2013). Under the pretext of construction, we may not extend a statute, expand a statute, or change its meaning. Id.

At issue is Iowa Code section 572.13A(1) — a matter of first impression for this court, as section 572.13A was only enacted in 2013. That subsection provides, in pertinent part:

A general contractor or' owner-builder who has contracted or will contract with a subcontractor to provide labor or furnish material for the property shall post a notice of commencement of work to the mechanics’ notice and lien registry [MNLR] internet' website within ten days of commencement of work on the property. A notice of commencement of work is effective only as to any labor, service, equipment, or material furnished to the property subsequent to the posting of the notice of commencement of work. .

Iowa Code § 572.13A(1). The terms “general contractor,” “owner-builder,” and *676 “subcontractor” are all defined by statute. See Iowa Code § 572.1.

The parties have different interpretations of the statute. The Joneses argue the doctrine of the last antecedent means the clause “who has- contracted or will contract” modifies only the term “owner-builder.” The Joneses thus contend the statute applies to (a) all general contractors and (b) those owner-builders who have contracted or will contract with a subcontractor to provide labor or furnish material to the property. Standard Water, as a covered general contractor, did not post a notice of commencement of wdrk within ten days of first furnishing materials or furnishing labor. As a result, the Joneses claim, Standard Water was prohibited from filing and enforcing its mechanic’s lien. Standard Water, contends the last-antecedent rule is inapplicable here and the phrase “who has contracted or will contract” modifies both “general contractor” and “owner-builder.” Standard Water did not contract with a subcontractor. Standard Water thus concludes it did hot have to file a notice of commencement of work on the MNLR within ten days of commencing work as a prerequisite to filing and enforcing its mechanic’s lien.

We conclude the challenged phrase could reasonably bear both interpretations and is thus ambiguous. See Bockwoldt, 814 N.W.2d at 223. Under the circumstances, the last-antecedent rule is not dispositive, and we turn to other interpretive aids. See Fjords N., Inc. v. Hahn, 710 N.W.2d 731, 738 (Iowa 2006) (“[T]he last-antecedent rule is not.inflexible, and it does not.apply where the entire act reveals that the qualifying sentence applies to several preceding subjects. Ultimately, we look to. the intent of our legislature”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
888 N.W.2d 673, 2016 WL 7478610, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-water-control-systems-inc-iowactapp-2016.