Bradshaw Renovations, LLC v. Barry Graham and Jacklynn Graham

CourtSupreme Court of Iowa
DecidedMay 2, 2025
Docket22-1721
StatusPublished

This text of Bradshaw Renovations, LLC v. Barry Graham and Jacklynn Graham (Bradshaw Renovations, LLC v. Barry Graham and Jacklynn Graham) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bradshaw Renovations, LLC v. Barry Graham and Jacklynn Graham, (iowa 2025).

Opinion

In the Iowa Supreme Court

No. 22–1721

Submitted March 27, 2025—Filed May 2, 2025

Bradshaw Renovations, LLC,

Appellant,

vs.

Barry Graham and Jacklynn Graham,

Appellees.

On review from the Iowa Court of Appeals.

Appeal from the Iowa District Court for Polk County, Sarah Crane, judge.

A construction contractor seeks further review of the court of appeals

decision affirming an adverse jury verdict on consumer fraud claims and the

district court’s judgment on its unjust enrichment and quantum meruit claims.

Decision of Court of Appeals Vacated; District Court Judgment Affirmed in

Part, Reversed in Part, and Case Remanded.

Christensen, C.J., delivered the opinion of the court, in which all justices

joined.

Matthew J. Hemphill (argued) of Bergkamp, Hemphill & McClure, P.C.,

Adel, for appellant.

Zachary J. Hermsen (argued) and Anna E. Mallen of Whitfield & Eddy,

P.L.C., Des Moines, for appellees. 2

Christensen, Chief Justice.

“Where’s the beef?”1 While a contract dispute between homeowners and

their hired contractor led a jury to find that the contractor committed consumer

fraud, we are left questioning the substance of this verdict on appeal. Upon our

review of the record, we can only include that there was, in fact, no beef. The

homeowners’ evidence of consumer fraud did not meet the statutory definition

of a “prohibited practice” under Iowa Code section 714H.3(1) (2020). The

contractor may be guilty of sloppy billing practices, but the evidence presented

at trial fails to demonstrate that he improperly billed the homeowners with the

intent that they would rely on it to do business with him. Consequently, we

reverse the district court ruling on this issue and remand for the entry of

judgment consistent with this opinion.

I. Background Facts and Proceedings.

Barry and Jacklynn Graham began conversations with Bradshaw

Renovations, LLC (Bradshaw) about renovating their Urbandale home in the

summer of 2019. They spent the summer emailing back and forth about the

budget and plans, and Bradshaw provided the Grahams with a five-page

itemization of labor and materials that was described as “the current estimate”

of the project totaling $136,168.16. This estimate contained a description of each

stage of the construction with a corresponding lump sum total charge for that

1Marc Berman, ‘Where’s the Beef’? The Iconic Clara Peller Spot for Wendy’s Turns 40, Forbes (Jan. 10, 2024, 10:31 AM), https://www.forbes.com/sites/marcberman1/2024/01/10/ wheres-the-beef-the-iconic-clara-peller-spot-for-wendys-turns-40/ [https://perma.cc/R8E4- EWHP] (“Flashback to January 9, 1984. Clara Peller, the diminutive 81 year-old angrily asked, ‘Where’s the beef?’ in her first television appearance as a spokesperson for Wendy’s. Peller, as you might recall, was featured with two other ladies in that 1984 spot while being served a huge hamburger bun containing a miniscule hamburger patty. Those three words became a cultural phenomenon. . . . [It] even had a political connection, making it into the 1984 campaign for the then Democratic Presidential nomination when Walter F. Mondale used it to suggest a lack of substance in proposals advanced by his chief rival, Gary Hart.” (emphasis omitted)) 3

stage. It did not establish a specific labor rate or represent that Bradshaw was

excluding a profit margin on the labor and materials.

Bradshaw incorporated this five-page itemization into the written contract,

which the parties entered into on August 1. The first page of the contract states

that Bradshaw “will revise the estimate as we go to keep us up to date as things

change for allowance and scope of work through out the project,” and describes

the estimate as “an offer to you from Bradshaw Renovations, LLC, for the services

and cost detailed herein.” Moreover, the contract provides that the Grahams’

“signature below constitutes acceptance of the offer and a binding contract” and

sets a payment schedule. Under this schedule, the Grahams would pay $1,000

“upon acceptance,” 33% of the estimate “upon foundation work completion,”

another 33% “upon completion of drywall,” and the balance upon the

renovation’s completion. Additionally, the contract required Bradshaw to email

any changes to the scope of services to the Grahams, who must “immediately

inform Bradshaw Renovations, LLC in writing and via email if the changes

detailed are inaccurate. Failure by customer to respond in writing and via email

within three (3) days from receipt of any said email constitutes acceptance by

customer of the proposed changes.”

Bradshaw began work on the Grahams’ home shortly thereafter. On

September 3, Bradshaw emailed the Grahams a revised estimate that increased

the cost by $3,000 for a new total of $139,168.16 for additional required concrete

work. The Grahams emailed their approval of the change the same day. This was

the only revised estimate that Bradshaw sent the Grahams during the project,

but it periodically sent them invoices for the work performed that detailed

specific labor and material expenses—some of which varied from the estimate—

and discussed changes in person. For example, the invoice that Bradshaw

emailed Jacklynn on November 6 noted, “The foundation company needed to add 4

some supports and a little more wall than expected so there was an up-charge

on those items.” The Grahams promptly made payments on the invoices but

gradually became concerned about Bradshaw’s communications and billing

practices.

In a November 16 email to Bradshaw, the Grahams sought to ensure that

the parties were “communicating with one another each step of the way to avoid

any potential issues from forming” because “[a] lot has changed in terms of

weather, what people did incorrectly, and what you’ve decided to change because

of the weather.” They asked “to see this in written form so that we can approve

of things, as per the terms of our written agreement.” Bradshaw declined the

Grahams’ request to see these changes in writing three days later, claiming it

was only concerned with one line item for which there was an allowance.

Bradshaw indicated that it would address this item after it knew what the

expense incurred was. It also maintained that it had not changed the Grahams’

budget “since we have not made any cost changing decisions to this point.”

Bradshaw sent additional invoices in January and February 2020, which

the Grahams paid in full. The payment of these invoices brought the Grahams’

total payment on the project to $112,098.79. In March 2020, Bradshaw sent the

Grahams a fifth invoice, writing, “we are almost done” in the cover email. This

invoice brought the total billed on the project to $139,472.88—about $300 over

Bradshaw’s last estimate. The Grahams paid the “nice even number” of $28,000,

bringing their total paid to $140,098.79.

In May, Bradshaw emailed the Grahams a “[f]inal bill” of $18,779.15,

bringing the total billed to the Grahams for the project to $158,252.03. The

Grahams quickly responded with concerns that the invoice was “exceptionally

higher than what we talked about.” They sent another email later that day

expressing that they had begun reviewing line items and were troubled that 5

Bradshaw had billed almost $20,000 more than its last estimate even though

the Grahams purchased their own flooring.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nepstad Custom Homes Co. v. Krull
527 N.W.2d 402 (Court of Appeals of Iowa, 1994)
State v. Keding
553 N.W.2d 305 (Supreme Court of Iowa, 1996)
Johnson v. Dodgen
451 N.W.2d 168 (Supreme Court of Iowa, 1990)
Iowa Waste Systems, Inc. v. Buchanan County
617 N.W.2d 23 (Court of Appeals of Iowa, 2000)
City of Eagle Grove v. Cahalan Investments, LLC
904 N.W.2d 552 (Supreme Court of Iowa, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Bradshaw Renovations, LLC v. Barry Graham and Jacklynn Graham, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bradshaw-renovations-llc-v-barry-graham-and-jacklynn-graham-iowa-2025.