Olberding Const. Co., Inc. v. Ruden

243 N.W.2d 872, 1976 Iowa Sup. LEXIS 955
CourtSupreme Court of Iowa
DecidedJune 30, 1976
Docket2-57009
StatusPublished
Cited by12 cases

This text of 243 N.W.2d 872 (Olberding Const. Co., Inc. v. Ruden) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Olberding Const. Co., Inc. v. Ruden, 243 N.W.2d 872, 1976 Iowa Sup. LEXIS 955 (iowa 1976).

Opinion

*874 REES, Justice.

This is an appeal by defendants Elmer and Marie Ruden from a decree of the trial court foreclosing the plaintiffs mechanics’ lien against their dwelling house and dismissing defendants’ counterclaim. We modify the decree of the trial court and affirm the same as modified.

At all times material to the action defendants owned a home in Dyersville. Plaintiff Olberding Construction Company (hereinafter “Company”) maintained its principal place of business in the same city. After a flood in August of 1972, Mr. Ruden contacted Eugene Olberding, vice-president of plaintiff Company, about the possibility of waterproofing the Rudens’ basement wall, pouring a new wall outside the old one and doing some landscaping and sidewalk work on the premises. Ruden had been acquainted with Olberding for several years, and the Company had done work for the defendants previously. Olberding advised Mr. Ruden that the proposed work would not hold up or protect against further flood damage.

A second flood occurred September 13, 1972, and the area in which the Ruden home was situated was declared by the government to be a disaster area, making federal relief funds available. Ruden decided to have his home raised and a new basement put in with the aid of such disaster funds. About September 15 Ruden went to Olberd-ing’s home to discuss the proposed work. There is a conflict in the testimony regarding whether Olberding ventured a guess at that time as to the probable cost of such work. In any event, Ruden asked Olberd-ing to come to the Ruden house and prepare a cost estimate of the necessary work, including labor and materials. Ruden told Olberding it was his impression the estimate was necessary in order for the Rudens to secure the federal disaster funds.

On or about September 20 Olberding came to the Ruden home in order to see what work would be necessary. He advised the Rudens to contact a Mr. Aylsworth about raising the house so the foundation work could be done. About a week later Ruden, Olberding and Aylsworth met at the Ruden home to discuss the further details of the proposed work. According to Ruden, the figure of $2800 for the entire job was discussed, but Aylsworth suggested a figure of $3000 due to the possibility that unexpected difficulties could arise because of the age of the dwelling house. Olberding testified he could not remember the substance of such conversation.

The next day Olberding brought to the Ruden home two copies of an estimate and left them with Mrs. Ruden. The estimate, which had been prepared and signed by Olberding, called for digging out and replacing the existing foundation, backfilling the wall, replacing the floor, putting in new windows and filling with sand. It included labor. Olberding indicated a price range for the work of from $3200 to $4000 in his estimate.. Two or three weeks later Ruden told Olberding to go ahead with the work.

Olberding testified it was his understanding the work would be paid for on a “time and material” basis, but he admitted he did not explain such an arrangement to the Rudens.

Work on the Ruden home commenced October 21, 1972. On December 15 of the same year, while work was in process, Ru-den paid Olberding $3500. There is a dispute as to whether this payment was intended by the parties to constitute partial or complete satisfaction of the cost of all the work. The Company stopped work on the Ruden home December 31, and on January 31, 1973, sent to Rudens a bill for an additional sum due of $2,370.59. (

On July 31, 1973, the Company instituted the within action against Mr. and Mrs. Ru-den. In its petition the plaintiff alleged there was due and owing it $1,838.85 as the fair and reasonable value of the construction work done on the Rudens’ house, which sum was the balance due for the work performed in excess of the $3500 already paid by the Rudens. Plaintiff further prayed for a foreclosure of its mechanics’ lien and the issuance of a special execution.

In answer the Rudens denied the Company’s allegations of reasonable value and de *875 nied the debt was due and owing. They affirmatively alleged they had already paid the Company $3500 for the work it performed, that the agreement between the parties called for the work to be done for a sum not to exceed $4000 and that the work done was faulty, unsatisfactory and unacceptable, making the cost of satisfactorily repairing the residence $10,000.

The answer also contained a counterclaim in which the Rudens sought to collect $13,-000 damages from the Company as the result of the alleged faulty, unsatisfactory and unacceptable workmanship on the part of the Company.

In its reply the Company admitted receipt of the $3500 from the Rudens, but denied all other allegations in the answer and counterclaim.

Trial commenced October 16, 1973. On December 18 trial court entered judgment for the Company and against Rudens in the amount of $1,614.85, ordered foreclosure of the mechanics’ liens, directed the issuance of a special execution against the property and dismissed the Rudens’ counterclaim. Trial court arrived at the figure of $1,614.85 by correcting a $24 error in the computation as shown on the statement for a mechanics’ lien and subtracting from the resultant amount the sum of $200 for incomplete and defective work.

The defendants state the following issues for review:

(1) Trial court erred in finding the Company was entitled to $5,114.85 as reasonable compensation for the work performed.

(2) Trial court erred in holding the Company was entitled to $5,114.85 as reasonable compensation for the work performed in view of the fact the Company’s vice-president had submitted a signed written estimate to defendants which set out a price range of $3200 to $4000 for the work proposed.

(3) Trial court erred in failing to find the Company had accepted $3500 as payment in full for the work performed.

(4) Trial court erred in entering judgment against defendants for a sum of money with seven percent interest thereon from January 1, 1973.

(5)Trial court erred in dismissing defendants’ counterclaim.

I. This case sounded in equity and our review is de novo. Rule 334, Rules of Civil Procedure. We give weight to the trial court’s findings of fact, especially in matters' involving credibility, but we are not bound by them. Rule 344(f)(7), R.C.P.

II. In their first issue stated for review, defendants assert trial court erred in finding the Company was entitled to $5,114.85 as reasonable compensation for the work done on the Ruden home. All parties to this appeal agree the question is one of fact.

With respect to this issue, the parties have narrowed the question before us to one of the reasonable value of the services rendered by the Company. There is no claim that an express contract existed as to the amount of compensation to be paid. It is well settled that there may be an implied contract on a point not covered by an express one, and where there is no agreement as to the amount of compensation, the law implies a promise to pay reasonable compensation. Sitzler v. Peck, 162 N.W.2d 449, 451 (Iowa 1968).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frank Millard & Co. v. Housewright Lumber Co.
588 N.W.2d 440 (Supreme Court of Iowa, 1999)
Presidential Capital Corp. v. Reale
652 A.2d 489 (Supreme Court of Connecticut, 1994)
Frontier Properties Corp. v. Swanberg
488 N.W.2d 146 (Supreme Court of Iowa, 1992)
DeMuth Landscaping & Design v. Heggestad
461 N.W.2d 354 (Court of Appeals of Iowa, 1990)
Thomas v. Grooms & Co. Construction
448 N.W.2d 686 (Court of Appeals of Iowa, 1989)
Murdock-Bryant Construction, Inc. v. Pearson
703 P.2d 1206 (Court of Appeals of Arizona, 1984)
Sulzberger Excavating, Inc. v. Glass
351 N.W.2d 188 (Court of Appeals of Iowa, 1984)
Heninger & Heninger, P.C. v. Davenport Bank & Trust Co.
341 N.W.2d 43 (Supreme Court of Iowa, 1983)
Carnicle v. Swann
314 N.W.2d 311 (South Dakota Supreme Court, 1982)
Chicago, Rock Island & Pacific Railroad v. City of Iowa City
288 N.W.2d 536 (Supreme Court of Iowa, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
243 N.W.2d 872, 1976 Iowa Sup. LEXIS 955, Counsel Stack Legal Research, https://law.counselstack.com/opinion/olberding-const-co-inc-v-ruden-iowa-1976.