Denniston and Partridge Company v. Mingus

179 N.W.2d 748, 1970 Iowa Sup. LEXIS 898
CourtSupreme Court of Iowa
DecidedSeptember 2, 1970
Docket54076
StatusPublished
Cited by10 cases

This text of 179 N.W.2d 748 (Denniston and Partridge Company v. Mingus) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Denniston and Partridge Company v. Mingus, 179 N.W.2d 748, 1970 Iowa Sup. LEXIS 898 (iowa 1970).

Opinion

MASON, Justice.

Denniston and Partridge Company, sometimes referred to in the record as Denniston & Partridge Co., instituted this equitable action to foreclose a mechanic’s lien for the balance alleged to be due for furnishing labor and material pursuant to an oral agreement with defendant Laura Mingus to build a double crib and granary on her Guthrie County farm. Defendant filed counterclaim for damages alleging plaintiff had failed to complete the building in a good workmanlike manner.

Defendant appeals from decree of the trial court awarding plaintiff judgment for $5574.51, interest and cost, foreclosure of its mechanic’s lien and dismissal of defendant’s counterclaim. Her propositions relied on for reversal present the questions whether the court erred in finding no express agreement was formed and that plaintiff had carried its burden of proof. Also involved is dismissal of defendant’s counterclaim and the question of burden of proof incumbent on plaintiff by its request for equitable relief in the nature of specific performance of an agreement.

I. Our review is de novo. Rule 334, Rules of Civil Procedure.

Laura Mingus, a Des Moines resident, desired to build a crib on her farm north of Guthrie Center. She sought the advice of a neighbor, Foster Purviance, in making ar *750 rangements to have it constructed. Before moving to Des Moines Mr. Purviance had been a farmer, had lived near Panora and had been around farm buildings most of his life. He was familiar with a crib which had been constructed by plaintiff in 1956 or 1957 on a Disney farm. Purviance went went to plaintiff’s manager, Harry Gibson at Linden, to inquire what it would cost to construct a building similar to Disney’s. Gibson examined the Disney invoices and advised Purviance it had cost about $5000.

About a week later Purviance took defendant to see this crib and the same day to see Gibson. There is some dispute as to the exact conversation between Gibson and defendant at that time. Defendant testified that after Gibson told her he could build a similar crib for $5000, “a little more or a little less,” she told him to build it. Gibson contends he told defendant one like it would cost between $5000 and $6000 to build. There was some conversation about another crib in this neighborhood which defendant had seen. When advised such a structure would cost $8000 defendant told Gibson she would not want to pay that amount. In any event, the Disney plans were to be used in construction of the Mingus crib and defendant’s tenant was to tell plaintiff’s carpenters where to build it.

There were no further conversations between defendant and Gibson or any other representative of plaintiff until after the crib was built. However, two or three days after the conversation at Linden and before work was commenced on the crib defendant’s tenant, with her approval, told Gibson he would like a crib four feet wider than Disney’s. When compared to the Disney crib the additional width enlarged the two 10 by 28-foot cribs to 10 by 32 feet and the driveway was widened from 11 to 12 feet and lengthened to 32 feet. The Mingus building would be 32 by 32 feet.

Purviance was at the Mingus farm when plaintiff’s builders staked out the crib and told them where defendant wanted the building.

Other later changes from the Disney plans authorized by defendant involved one cupola on the Mingus crib rather than two, composition shingles instead of wood shingles, a poured cement driveway — a feature not in the Disney crib — and additional ventilators. The footings on defendant’s crib were six inches deeper.

When the crib was completed defendant asked Purviance to stop and pick up her bill. When told the amount was $8574.51 Pur-viance told Gibson to present the bill. Later defendant received a letter from plaintiff enclosing invoices and statement for $8574.51. Of this amount $5152 was for material and $3422 was for labor. Following defendant’s receipt of the bill there were some negotiations between defendant and Gibson about the total cost of her crib compared to the price for the Disney crib with Gibson contending the site selected by defendant required considerably more labor and cement for foundation than the Disney crib. When their efforts failed to bring about a settlement plaintiff commenced the present lawsuit.

The court found the parties had agreed plaintiff would build a crib and granary for “$5000, more or less”; thereafter, changes were made and a site requiring additional leveling and concrete work was selected by defendant.

It concluded as a matter of law the parties had an estimate, not an express contract, and with the changes in construction authorized by defendant without any agreement or estimate between the parties as to what the additional costs would be plaintiff was entitled to recover on the theory of an implied contract for the fair and reasonable value of the material and labor.

II. In support of her first proposition defendant contends the court erred in finding no express agreement between the parties and in permitting plaintiff to recover on an implied contract after having pleaded an express contract. She asserts this constituted a variance from the pleadings and conflicts with the rule that one may not *751 plead an express contract and recover on an implied contract on quantum meruit. She argues the nature, terms and conditions of the contract are important because defendant’s obligation cannot exceed that for which she contracted and it was plaintiff’s burden to plead and prove the contract upon which it based its right to a mechanic’s lien.

Defendant’s argument is based on her interpretation that plaintiff alleged an express agreement for construction of the crib and an implied agreement for extras.

In its petition plaintiff alleged its corporate capacity, defendant’s ownership of the farm, the furnishing of labor and material pursuant to an oral agreement with defendant ; the prices set out in the hill of particulars attached to its petition were the reasonable prices and values of the items furnished; the double crib was completed and plaintiff in all respects had complied with its agreement with defendant; and there remained $5574.51 due from defendant. In its prayer plaintiff asks judgment for this balance and foreclosure of a mechanic’s lien previously filed.

In answer defendant admitted plaintiff’s corporate capacity, her ownership of the farm and asserted there was an oral agreement with plaintiff to build the double crib and granary. She denied all other allegations in plaintiff’s petition and affirmatively alleged the oral agreement was for plaintiff to build the crib for $5000; the amounts set out in the exhibit attached to plaintiff’s petition are not the fair and reasonable cost or the amounts agreed upon by the parties and that she had paid $3000 on account during construction. In a separate division defendant asserted the counterclaim mentioned.

In reply plaintiff denied defendant’s affirmative allegations and asserted there was an oral agreement to build the crib and granary as pleaded in its amended petition; that various changes which included making the crib larger, adding air vents and cementing the driveway were made at defendant’s instance and request; the bill rendered for construction of the crib included the cost of the additions and changes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sulzberger Excavating, Inc. v. Glass
351 N.W.2d 188 (Court of Appeals of Iowa, 1984)
Ruzicka v. Petersen
330 N.W.2d 913 (Nebraska Supreme Court, 1983)
Johnston-Clark Appraisal Co. v. State, Department of Revenue
392 So. 2d 1164 (Supreme Court of Alabama, 1980)
Maxwell v. Anderson
593 P.2d 29 (Montana Supreme Court, 1979)
Vester J. Thompson, Jr., Inc. v. CITMOCO SERV. INC.
371 So. 2d 35 (Court of Civil Appeals of Alabama, 1977)
Olberding Const. Co., Inc. v. Ruden
243 N.W.2d 872 (Supreme Court of Iowa, 1976)
Rinehart v. State
234 N.W.2d 649 (Supreme Court of Iowa, 1975)
Van Hosen v. Bankers Trust Company
200 N.W.2d 504 (Supreme Court of Iowa, 1972)
Frudden Lumber Co. v. Clifton
183 N.W.2d 201 (Supreme Court of Iowa, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
179 N.W.2d 748, 1970 Iowa Sup. LEXIS 898, Counsel Stack Legal Research, https://law.counselstack.com/opinion/denniston-and-partridge-company-v-mingus-iowa-1970.