A AND R CONCRETE AND CONSTRUCTION CO. v. Braklow

103 N.W.2d 89, 251 Iowa 1067, 1960 Iowa Sup. LEXIS 663
CourtSupreme Court of Iowa
DecidedAugust 2, 1960
Docket50001
StatusPublished
Cited by9 cases

This text of 103 N.W.2d 89 (A AND R CONCRETE AND CONSTRUCTION CO. v. Braklow) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A AND R CONCRETE AND CONSTRUCTION CO. v. Braklow, 103 N.W.2d 89, 251 Iowa 1067, 1960 Iowa Sup. LEXIS 663 (iowa 1960).

Opinion

Larson, C. J.

Plaintiff A and R Concrete and Construction Company, Inc., contractor, brings this suit to enforce two separate mechanic’s liens for material and labor furnished by it in the fall of 1958 in the remodeling of a building located at 2329 University Avenue in Des. Moines. The defendants Braklows owned the property and the defendant Evans leased the first floor of the building. In Division I of plaintiff’s petition it claimed the sum of $4273.05 with interest at five per cent per annum from the 8th day of December, 1958, for remodeling the building under an oral contract on a cost-plus basis. In Division II it claimed the sum of $3739.54 with interest at five per cent per annum from the 26th day of November, 1958, for interior remodeling under an oral contract on a cost-plus basis.

Both defendants answered admitting an oral contract was entered into between them and the plaintiff, but denied it was on a cost-plus basis and alleged it was for the performance of a job for a sum certain. The defendants Braklows contend the agreed price for their job, including extras, was $4311,87, upon which they had paid by cash and credit $3029, leaving a balance of $1282.87. They offered to confess judgment for $1500 plus accrued interest and costs to' cover any overlooked extra items. Plaintiff refused the offer. The defendant Evans contended the agreed price for his job was $2080 plus extras of $125 and $424, or a total of $2629, upon which $1500 had been paid, leaving a balance of only $1129 due plaintiff. He also offered to confess judgment for $1500 plus accrued interest and costs to cover any overlooked extra items, but plaintiff also refused this offer. During the trial of the case it was stipulated by counsel that on the Braklow job, if the contract was determined to be on a cost-plus basis, the materials and services from suppliers amounted to $2609.03 and on the Evans job the sum of $1656.75.

There are two principal issues: (1) Were the oral con *1070 tracts, or either of them, entered on a cost-plus basis, or a sum certain basis plus extras; and (2) if on a cost-plus basis, were the labor charges claimed actual, just, and reasonable for the respective jobs? As usual in cases of this kind, the answer depends largely on the record facts.

After the trial court had carefully studied the testimony of the witnesses and weighed its credibility and studied the many exhibits, it well expressed the problem by stating that “a definite decision is difficult for many reasons, including the fact that the plaintiff company is a newly organized group with little experience in actually contracting * * It did conclude, however, that as to the Braklow job, based upon an estimate made by a third party and on which there were some “22 changes or additions” alleged, the express contract was on a cost-plus basis, but on the Evans job, where the items of improvement were comparatively simple, clear and express, and the negotations between the parties were had as to the quality and cost of the material to be used, the contract was for a sum certain plus extras which was later evaluated and agreed to by the parties. After carefully reviewing the record, we are satisfied that for the most part those determinations were correct.

I. Plaintiff in both divisions contends, as it must, that it established by a preponderance of the evidence an express verbal contract. Defendants, on the other hand, contend they each proved an express verbal contract as to the jobs specified and an implied one as to the extras furnished. Both cannot be correct, nor can there be an express contract and an implied one relating to the same subject matter and covering the same terms. Lautenbach v. Meredith, 240 Iowa 166, 168, 35 N.W.2d 870; Maasdam v. Estate of Maasdam, 237 Iowa 877, 889, 24 N.W.2d 316, 321; 17 C. J. S., Contracts, section 5; 12 Am. Jur., Contracts, section 7. But as pointed out in the above cases, there may be an implied contract on a point not covered by an express one, which could apply to extras furnished at defendants’ request.

II. Of course it is plaintiff’s burden to prove the contract declared upon by him. Lautenbach v. Meredith, supra; Peterman v. Hardenbergh, 250 Iowa 931, 933, 97 N.W.2d 152, *1071 153; Economy Hog & Cattle Powder Co. v. Honett, 222 Iowa 894, 899, 270 N.W. 842; 17 C. J. S., Contracts, section 579a.

III. It is also true that while our review is de novo, we must give weight to the trial court’s findings. The wisdom of that rule was never more applicable. As in most eases of its kind, this one involves almost entirely questions of fact and credibility, and the trial court with the witnesses before it was in a much better position to decide these questions than are we with only the exhibits and the cold record to aid us. Peterman v. Hardenbergh, supra; Huffman v. Hill, 245 Iowa 935, 938, 65 N.W.2d 205; Bell v. Pierschbacher, 245 Iowa 436, 439, 62 N.W.2d 784, 786, and citations; 57 C. J. S., Mechanics’ Liens, section 308f, page 963; 36 Am. Jur., Mechanics’ Liens, section 235, page 151. The decision here must rest largely upon the credibility of the testimony. On many vital questions involved there seems to be a complete disagreement as to what was or was not said by the parties at the time of the agreement. The only thing perfectly clear is that the work was done as required by the defendants, part payment was made, and some balance is owed plaintiff by each.

IY. While it would serve no useful purpose to relate all the testimony on the disputed issues, we note these pertinent facts. The defendants Braklows, owners of the property described in the lien known as 2329 University Avenue, Des Moines, residing on the second floor, leased the main floor of the building to the defendant Doctor Evans. Each agreed to do extensive remodeling, the Braklows structurally and on the outside, and Doctor Evans on the inside. Evans was to divide the single room 18 by 54 feet into professional facilities, or consultation rooms, for his own use. The Braklows asked a Mr. J. B. Tusant, a well-known and respected contractor, to look their job over and make an estimate of its cost. This he did, but declined to take the job as he was quitting the contracting business. He recommended plaintiff, just starting in the general contracting business. Together with an officer of the company, Mr. Alvin C. Carter, and an employee, Mr. Albert J. Daniels, he and the Braklows talked over the estimate he prepared, known herein as Exhibit C. Mr. Tusant considered Exhibit C only an estimate.

*1072 Tending to support plaintiff’s claim of a cost-plus agreement, we find testimony that its representative Daniels told defendant Braklow that they could not give a firm bid on remodeling of an old building such as this one, for “you never know when you get into them old buildings what you are running into.” As to Exhibit C, Mr. Daniels, in explaining his statement that he thought the estimate was figured strong, told Braklow, “If I can save you money, I will do it.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re the Marriage of Racette
Court of Appeals of Iowa, 2018
Loudon v. State Farm Mutual Automobile Insurance Co.
360 N.W.2d 575 (Court of Appeals of Iowa, 1984)
Welter v. Heer
181 N.W.2d 134 (Supreme Court of Iowa, 1970)
Denniston and Partridge Company v. Mingus
179 N.W.2d 748 (Supreme Court of Iowa, 1970)
McDonald v. Welch
176 N.W.2d 846 (Supreme Court of Iowa, 1970)
Hetherington Letter Co. v. O. F. Paulson Construction Co.
171 N.W.2d 264 (Supreme Court of Iowa, 1969)
J. K. & W. H. Gilcrest Co. v. A. & R. Concrete Co.
112 N.W.2d 366 (Supreme Court of Iowa, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
103 N.W.2d 89, 251 Iowa 1067, 1960 Iowa Sup. LEXIS 663, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-and-r-concrete-and-construction-co-v-braklow-iowa-1960.