Peterman v. Hardenbergh

97 N.W.2d 152, 250 Iowa 931, 1959 Iowa Sup. LEXIS 424
CourtSupreme Court of Iowa
DecidedJune 9, 1959
Docket49581
StatusPublished
Cited by6 cases

This text of 97 N.W.2d 152 (Peterman v. Hardenbergh) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peterman v. Hardenbergh, 97 N.W.2d 152, 250 Iowa 931, 1959 Iowa Sup. LEXIS 424 (iowa 1959).

Opinion

Larson, J.

This is an action in equity to recover $2490.08 as the amount due for extras furnished defendants by plaintiff building contractor in connection with the construction of a dwelling and garage for defendants under an oral contract, and to establish and foreclose his mechanic’s lien in the sum of $1763.97. Defendants denied the indebtedness and filed a cross-petition claiming the sum of $4500 for plaintiff’s failure to complete his -contract 'and to- p erf com the services in a workmanlike manner.

The trial court found plaintiff had established items due as extras in the sum of $1114.15, and that several items of work were not furnished nor completed, and reduced plaintiff’s claim by $229. From a decree for plaintiff for $885.15 and the establishing -and foreclosing of mechanic’s- lien therefor, defendants have -appealed. Plaintiff’s eross^appeal argues that the court failed to allow certain items, clearly established by the evidence.

This case is in its simplest form. Only the original parties are involved, with no- subcontractors -nor subsequent ownership of the premises involved. There is no- dispute as to- the law. Only two propositions are urged by appellants-: (1) That the plaintiff failed to- establish his right to a mechanic’s lien, and (2) that plaintiff failed to- prove by a preponderance of -the credible evidence the terms of the oral contract, or performance thereof, and that the items claimed as extras were not included in the contract -but were required by defendants subsequent to tbe original oral agreement.

*933 I. "While our review is de novo (R. C. P. 334), we must give weight to- the trial court’s findings. The ease involved almost entirely questions of faat, -and the trial -count, with the witnesses before it, was in -a much better position to decide these questions than we with the oo-ld record before us. Huffman v. Hill, 245 Iowa 935, 938, 65 N.W.2d 205; Bell v. Pierschbacher, 245 Iowa, 436, 439, 62 N.W.2d 784, 786, and citations. The decision here largely rests on the credibility of the testimony.

II. The burden, of course, rests upon plaintiff to prove performance as well as the terms of the oral agreement declared upon by him. Huffman v. Hill, supra; Miller v. Gray, 205 Iowa 1305, 1307, 217 N.W. 228, 229; 57 G. J. S., Mechanics’ Liens, section 308f, p-age 963; 36 Am. Jur., Mechanics’ Liens, section 235, page 151.

However, as we pointed out in Huffman v. Hill, a technical, exact and perfect performance is not required nor necessary. If the terms of the contract are established by a preponderance of the credible evidence, and there is shown a substantial performance of its terms, the builder is entitled to- the .contract price pins extras, less reasonable sums for small items hot furnished and reasonable damages on -account o-f slight defects in performance. Lautenbach v. Meredith, 240 Iowa 166, 172, 173, 35 N.W.2d 870, 874. This is particularly true in equity suits, which -are somewhat mo-re liberal than actions at law. Littell v. Webster County, 152 Iowa 206, 215, 131 N.W. 691, 132 N.W. 426; Hayes v. Ramsey, 205 Iowa 167, 169, 217 N.W. 808, 809.

III. It would serve no useful purpose to consider each item involved herein and the evidence received in relation thereto-. The parities agreed that sometime in the summer of 1954 they fentered into- an oral contract whereby plaintiff would build a brick dwelling -and gar'age for defendants for the sum of $12,000. They do not -agree as to- its terms relating to- the length of the dwelling, the material for the basement, and the material to be used on the kitchen and bathroom floors and on the ro-o-f. The trial co-urt found plaintiff established his contention as to- the original -agreement on -all -but the basement material. We agree.

Plaintiff conceded he failed to lay the cement floor in the *934 garage, pay for the switch boxes and switches, put glass in the basement sash, .and install a cement step inside the basement door, 'as agreed in the oral contract. His explanations relating to' ground settlement, weather condition®, and oversight, were accepted by the trial court, and the proof as to the value of those items was properly considered in the deductions made by the court.

Defendants concede they asked for Fleetlite windows in place of wood ones, that they 'agreed to pay $200 more tor that extra, and .that they received a number of feet of soil pipe, gas pipe and water pipe as extras. Substantial evidence of this value appears in the record.

‘The disputed items related to (1) an alleged change in the length of the house from 38 feet to 40 feet, (2) a change from cement block basement to clay tile, (3) a change from 210 pound shingles to 300 pound shingles, (4) a change from vinyl tile to rubber tile on the floors of the bathroom and kitchen, and (5) a change from dry wall to colored plaster walls, and some other minor matters.

Plaintiffs evidence as to the terms of the original agreement consisted of his testimony, the working plan he drew of the proposed house, and the specifications and bill of material submitted to and figured for the job by Mr. Paul Haws, the manager of the Atlantic Building Supply Company, the testimony of Mr. Kenneth Beekman, a local contractor, Mr. Haws’ testimony, and that of the party who did the cement work, Mr. Kenneth Martin. At least one witness testified the defendant Frank Hardenbergh had seen those specifications at the supply company office.

The specifications, plan, and bill of materials, Exhibit 4, call for a dwelling 28 feet by 38 feet in length, a cement block basement, a 210 pound shingle roof, dry interior walls, and wood millwork.

Defendants’ evidence included testimony of Mr; and Mrs. Hardenbergh, Mr. Martin, and a valuation and building expert, Mr. Lyle Sabin, from Omaha, Nebraska.

It is defendants’ contention that the evidence of faulty workmanship consisted op failure to install rafter collars, cap *935 walls' leading from the basement door, install steps where needed, and other- less evident errors.

The trial court found the length of the dwelling had been changed -subsequent to the original agreement and allowed $11 per square foot as an extra, or the sum of $616'; that the weight of the shingles had been changed increasing -the cost $156.50; and that there had been a change in floor tile at an increased cost of $79.10. To this amount the court added the admitted sums of $200 for a change in millwork, and $62.55 for pipe furnished, making a total for extras of $1114.15 due plaintiff. It made no allowance for a change in material for basement walls.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flynn Builders, L.C. v. Matthew P. Lande and Chris Lande
814 N.W.2d 542 (Supreme Court of Iowa, 2012)
McDonald v. Welch
176 N.W.2d 846 (Supreme Court of Iowa, 1970)
Hetherington Letter Co. v. O. F. Paulson Construction Co.
171 N.W.2d 264 (Supreme Court of Iowa, 1969)
Theobald v. Weber
143 N.W.2d 418 (Supreme Court of Iowa, 1966)
A AND R CONCRETE AND CONSTRUCTION CO. v. Braklow
103 N.W.2d 89 (Supreme Court of Iowa, 1960)
Farrington v. Freeman
99 N.W.2d 388 (Supreme Court of Iowa, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
97 N.W.2d 152, 250 Iowa 931, 1959 Iowa Sup. LEXIS 424, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peterman-v-hardenbergh-iowa-1959.