Nordstrom v. Diamond International Corp.

710 P.2d 628, 109 Idaho 718, 1985 Ida. App. LEXIS 802
CourtIdaho Court of Appeals
DecidedNovember 21, 1985
Docket15428
StatusPublished
Cited by5 cases

This text of 710 P.2d 628 (Nordstrom v. Diamond International Corp.) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nordstrom v. Diamond International Corp., 710 P.2d 628, 109 Idaho 718, 1985 Ida. App. LEXIS 802 (Idaho Ct. App. 1985).

Opinion

SWANSTROM, Judge.

Richard Nordstrom, a logging contractor, sued Diamond International Corporation to recover lost profits allegedly caused by a breach of written and oral contracts to log in the Coeur d’Alene National Forest. The district court ruled that Nordstrom failed to prove the existence of an oral agreement. The court found that while Diamond suspended Nordstrom’s log hauling for a time the suspension did not amount to a material breach which would allow Nordstrom to treat the written contracts as cancelled. The court denied any relief to Nordstrom and he has appealed. For reasons hereinafter stated we affirm the judgment.

The issues raised by Nordstrom can be grouped into those concerning the alleged oral contract, and those involving the written contracts. Concerning his proof of an *720 oral contract, Nordstrom contends the trial court erred by failing to consider evidence of part performance, of road building by Nordstrom, and of custom and practice in the logging industry. He also contends that his entitlement to damages is supported by promissory estoppel. Nordstrom further contends that Diamond’s suspension of log hauling was a material breach of contract. He cites error by the court for failing to consider first whether the suspension was a breach, and second whether it was a material breach. He also argues that the court erroneously excused Diamond’s performance under written contracts due to actions of third parties.

In 1972 Nordstrom contacted Diamond International Corporation about performing contract logging. Diamond manufactures lumber products. To supply its mills with timber, Diamond contracts with independent loggers to harvest both Diamond’s private timber land and timber that Diamond purchases from the United States Forest Service (USFS). It was agreed that Nordstrom would log on Diamond’s private land and on USFS sale land, both located on Teddy Creek. A written contract was executed which provided that Nordstrom would cut and deliver designated timber within the area for a one year term. The amount of timber was estimated, but not guaranteed, in the contract. Diamond was empowered to suspend the contract whenever enumerated contingencies occurred. Nordstrom was responsible for building spur roads linking the logging sites to main haul roads. By oral agreement, Diamond was to construct the main haul roads.

Things went well on the private land, but Diamond encountered problems getting the main haul road built for the Teddy Creek USFS sale. Consequently alternate haul roads were used and the written contract between Diamond and Nordstrom was modified several times to reflect the changes. Diamond also gave Nordstrom new written contracts, similar in form to the first contract, to log other USFS sales, one at Jack Creek and one at Ash Creek. Diamond finally engaged a road builder and started the main haul road on Ash Creek. The work did not progress well and the road could not be used for hauling. After the Forest Service approved an alternate route for Ash Creek, Diamond moved its road contractor to Teddy Creek.

In May of 1973 new contracts were entered to log the Ash Creek and Teddy Creek USFS sales. Because Diamond had not completed the main haul road, Nordstrom used the alternate route on Ash Creek. Late in the summer the forest service informed Diamond that, due to dry weather, hauling would have to cease unless Diamond would apply road oil or water to abate the dust. Diamond determined that the hauling prohibition would be of short duration because fall rains would be forthcoming and that it would be too expensive to apply dust abatement for such a short time. A Diamond field representative told Nordstrom to cease hauling. Nordstrom testified he was informed that the contracts were being terminated in order to give the work to another contractor. He abandoned the job site and did not return until after the hauling prohibition was lifted, and then only to remove timber he had previously cut and decked. Diamond denies terminating the contract and insists that the hauling stoppage was only a temporary measure taken to comply with Forest Service regulations.

Nordstrom sued Diamond, seeking the profit he would have derived had he been allowed to log the entire USFS Teddy and Ash Creek sales. These sales were large enough that it would have taken more than the one year provided in the written contracts. To support his claim to the profits, Nordstrom alleges that the one-year contracts merely represented Diamond’s method of completing the overall oral contract with Nordstrom to log the entire sale. To prove the oral contract, Nordstrom presented evidence of his part performance, the fact that he had built spur roads beyond the areas covered by the written contracts, and custom and practice in the industry.

Nordstrom contends that the trial court ignored evidence that he began operating *721 after the oral agreement, but before any written contract was signed. This evidence, however, does not establish the terms of any oral agreement beyond those which were embodied in the subsequent written agreements. Further, Diamond denied any such oral agreement or knowledge that Nordstrom was working before the written contract had been executed.

Nordstrom presented evidence that he was required to build the spur roads a year in advance of their use. The evidence discloses that he did build spur roads throughout the sales areas. Payment for this work was incorporated into the contract rate for timber delivered to Diamond. Nordstrom contends that unless he logged an area and delivered the timber he was not fully compensated for his road building. Nordstrom argues that his road building shows the existence of an oral agreement to log the entire Ash and Teddy Creek sales, that it would be illogical to build roads not intended for use until after his contract expired. Diamond points out that Nordstrom was separately paid $16,-000 for the road work in addition to the compensation for road building that was included in the payments he received for log deliveries. According to Diamond, many of the roads were merely “pioneered” by Nordstrom, meaning that the roads were cleared but needed more work to be useable. Thus, there was substantial evidence to support Diamond’s contention that Nordstrom was fully paid for road building.

The advance road work done by Nordstrom is also used by him as support for his custom and practice arguments. He contends that it is the custom and practice in the logging industry that when a contractor is retained to work on a particular USFS sale he has a contract to log the entire sale. He points to deposition statements made by Diamond’s logging superintendent that it is customary for an entire sale to be logged under a series of one-year contracts with a single contractor. Nordstrom argues that Diamond’s habit of following this custom supports his claim that on this occasion also an overall oral agreement was made. He cites the general rule that the custom and practice of a trade become part of a contract between parties within the trade having knowledge of the custom, unless the contrary appears. Commercial Insurance Company v. Hartwell Excavating Co., 89 Idaho 531, 407 P.2d 312 (1965).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Meridian v. PETRA Inc.
299 P.3d 232 (Idaho Supreme Court, 2013)
Borah v. McCandless
205 P.3d 1209 (Idaho Supreme Court, 2009)
Tentinger v. McPheters
977 P.2d 234 (Idaho Court of Appeals, 1999)
Freeman & Co. v. Bolt
968 P.2d 247 (Idaho Court of Appeals, 1998)
R.D. Bischoff v. Quong-Watkins Properties
748 P.2d 410 (Idaho Court of Appeals, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
710 P.2d 628, 109 Idaho 718, 1985 Ida. App. LEXIS 802, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nordstrom-v-diamond-international-corp-idahoctapp-1985.