Beare v. Stowes' Builders Supply, Inc.

658 P.2d 988, 104 Idaho 317, 1983 Ida. App. LEXIS 205
CourtIdaho Court of Appeals
DecidedFebruary 2, 1983
Docket14296
StatusPublished
Cited by3 cases

This text of 658 P.2d 988 (Beare v. Stowes' Builders Supply, Inc.) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beare v. Stowes' Builders Supply, Inc., 658 P.2d 988, 104 Idaho 317, 1983 Ida. App. LEXIS 205 (Idaho Ct. App. 1983).

Opinion

WALTERS, Chief Judge.

Claude Beare, dba Yogi’s Diesel Repair, sued to collect the balance owing for labor and parts furnished in the repair of a loader *318 owned by Stowes’ Builders Supply, Inc. The loader was used to move lumber and logs at the owner’s sawmill. The owner defended against the complaint by alleging negligence and breach of contract in the repair of the loader. It further asserted a counterclaim for the costs of a second repair and for recoupment of other damages. The trial court allowed recovery of $2,148.87 to Beare, and denied the owner’s counterclaim. The owner appeals. We affirm.

We have consolidated the claims of error presented by the owner into the following four issues: First, did the trial court err in holding the owner liable for the repair of the loader by Beare? Second, was Beare liable to the owner for damages because his repair work was not performed with due care and in a workmanlike manner? Third, was Beare liable for damages because his repair work was not performed with due diligence and in a timely fashion? Fourth, did the owner present adequate proof of resulting damages to support a monetary award or an offset against any obligation owed to Beare?

The facts found by the trial court from the evidence presented at trial may be summarized as follows. In the fall of 1977, the diesel engine in the owner’s loader was malfunctioning. Claude Beare inspected the machine at the mill site and determined that an overhaul was needed. He indicated that he could overhaul the engine in a one-week period if parts were available.

On December 13, the loader was delivered to Beare’s garage. Grant Stowe, manager of operations at the mill, clearly explained to Beare the company’s dependence on the loader and the need to have the repair work completed as soon as possible. Beare assured Stowe that the job could be completed in one week. Stowe signed a work order requesting an “overhaul” and left Beare’s garage believing that Beare had guaranteed completion of the overhaul in one week. However, no completion date was expressed on the work order.

By December 17, the engine had been disassembled and its repair needs ascertained. From this point on, the repair job was fraught with delay and difficulty. Delivery of some parts was delayed by the holiday season. The parts suppliers took four-day holidays for both Christmas and New Year’s days. Beare had to subcontract the task of reboring the engine block. Extreme winter weather visited northern Idaho, freezing the water pipes in Beare’s garage, effectively shutting down the repair work for a short time, and additionally burdening Beare’s garage with emergency repair jobs on commercial trucks traveling interstate routes.

The owner could not keep the lumber mill closed longer than one week. On December 19, replacement equipment was hired to perform the work at the lumber mill until the loader was returned, which, as it turned out, was about one month later. The rental cost of the replacement loader also included the wages for an operator, because the owner of that loader insisted on operating his own machine.

Beare finally completed the repair job on or about January 20. Before the loader was returned, it was allowed to run nonstop for several hours at Beare’s garage to test the overhaul job. Beare testified that it operated satisfactorily. The vehicle was delivered to the owner’s mill on a Friday afternoon and sat without running until the following Monday morning. No antifreeze had been put in the coolant following the overhaul. On Monday, when an effort was made to start the engine, the cooling system was found to be frozen. Later that week Beare called the owner, demanding payment of the balance due on the repair job. The owner refused to pay until it could be ascertained whether the frozen coolant had damaged the engine. Beare threatened suit.

After the engine was thawed, it was started up, but it ran roughly, belched black smoke, vibrated excessively, and lacked-power. Several bolts connecting the engine to the transmission were missing and had to be installed. This stopped the vibrations, but the engine still did not have the power to carry a workload.

*319 A provision of the work order stated as follows: “All parts and labor thirty days warranty or four thousand miles whichever comes first. In our shop with Yogi’s approval.” 1 The owner did not call Beare, who had just threatened suit, to have him remedy the problem. Instead, the loader was delivered to Spokane Diesel where it was completely disassembled and rebuilt to factory specifications. Spokane Diesel replaced many of the parts installed at Beare’s garage. Several parts that Beare had not replaced, but had left in the engine, were also replaced by Spokane Diesel. It was also discovered that the compression seals situated on top of the piston liners had not been installed when the engine was reassembled by Beare. The final bill for this second repair job was $2,860.79. The loader was returned to work on February 22. The bill for the rental cost of the replacement loader from December 19 to February 22 came to $7,306.20.

We first address the question whether the trial court was correct in holding the owner liable for the repairs made by Beare. The owner argues that by requesting an engine overhaul, he contracted with Beare to have the engine rebuilt and placed in a “like-new” condition. However, the trial court found that there was no meeting of the minds regarding the precise work to be done in the requested “overhaul”. Moreover, conflicting evidence was presented by qualified mechanics as to precisely what work one would perform in an “overhaul.” The evidence also differed as to the quality of the repairs made by Beare. 2

The trial court did not find in favor of Beare solely upon a theory of complete performance, or even of substantial performance, of the contract to repair the loader. The court, instead, determined the matter upon a burden-of-proof approach. The court held that the owner failed to establish, by a preponderance of the evidence, that Beare had performed the repair improperly or that Beare had failed to do the work he was required to do.

The trial court’s approach was consistent with that approved in Dick v. Reese, 90 Idaho 447, 412 P.2d 815 (1966). There the appellant Reese refused to pay Dick for repairs to Reese’s diesel truck, contending that the repair job was performed in an improper manner. Affirming a judgment in favor of Dick, the Supreme Court noted that an automobile repairman must exercise ordinary care and skill in making repairs. Because an allegation of improper performance of repairs constitutes an affirmative defense under I.R.C.P. 8(c), the Court held that the burden of proving the repairman’s breach of duty rests upon the one who claims that the repairs were defectively made. The Court further held that Reese had failed to establish what act, if any, on the part of Dick constituted breach of the duty to make repairs with commensurate care and skill. The trial court was upheld on the basis that its finding of proper performance of the repairs was supported by substantial and competent, though conflicting, evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bailey v. Sanford
86 P.3d 458 (Idaho Supreme Court, 2004)
Nordstrom v. Diamond International Corp.
710 P.2d 628 (Idaho Court of Appeals, 1985)
Martsch v. Nelson
705 P.2d 1050 (Idaho Court of Appeals, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
658 P.2d 988, 104 Idaho 317, 1983 Ida. App. LEXIS 205, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beare-v-stowes-builders-supply-inc-idahoctapp-1983.